The Clark County Land Use Hearing focused on the proposed Ausland Acres subdivision, which aims to develop 8.78 acres into 98 single-family attached townhome lots within an R1-6 zone. To meet transportation concurrency requirements, the developer committed to extending local avenues, widening 88th Street, and ensuring a new traffic signal is operational at 88th Street and 94th Avenue prior to final plat approval. During public testimony, local residents raised substantial concerns regarding the high-density development's impact on neighborhood traffic, school capacity, and potential soil liquefaction risks near an on-site wastewater pump station. The applicant's engineering team and county staff directly responded to these objections, citing traffic studies and geotechnical soil testing to demonstrate the project's full compliance with existing county codes. Following the debate, the Hearing Examiner kept the public record open for one week to allow the community to submit additional written feedback before a final decision is issued.

Documents

Agenda

Slides / on-screen documents

Text read off slides, maps, and exhibits shown on screen — often never spoken aloud.

0:00 slide
Public Hearing Procedure

Chair/Vice-Chairperson's Opening Statements
1. Staff Report and Recommendation
2. Applicant's Testimony
3. Public Testimony
4. Applicant's Rebuttal
5. Close Public Hearing. Council will be allowed to move
and discuss among themselves on the item. The item will be
set for Council's vote and Concluding.
0:49 slide
Public Hearing Procedure

Hearing Examiner's Opening Statements
1. Staff Report and Recommendation
2. Applicant's Testimony
3. Public Testimony
4. Applicant's Rebuttal
5. Close Public Hearing - Decision will be issued within 14 days unless hearing is continued or the record is left open. There are fees for Open Records and Continuances

May 28, 2026
Clark County Land Use
3:16 slide
Land Use Hearing - May 28, 2026
Webinar Info
46:02
Layout
Richard Daviau
Daniel Kearns
David Jardin (Clark County)
Scott Taylor
Shared Timer
Unlocked
Sound on
Overtime off
Viewing Joe Kinsman's shared content
100%
Timer
20:00
+ 1m
+ 5m
+ 10m
+ Add timer
Public Hearing Procedure
Hearing Examiner's Opening Statements
1. Staff Report and Recommendation
2. Applicant's Testimony
3. Public Testimony
4. Applicant's Rebuttal
5. Close Public Hearing - Decision will be issued within 14 days
unless hearing is continued or the record is left open. There are fees
for Open Records and Continuances
May 28, 2026
CVTV
Clark County Land Use
5:43 slide
Land Use Hearing - May 28, 2026 Webinar Info
Richard Daviau
Daniel Kearns
David Jardin (Clark County)
Scott Taylor
48:29
Layout
Shared Timer
Unlocked
Sound on
Overtime off
Timer
20:00
+ 1m
+ 5m
+ 10m
+ Add timer
Viewing Joe Kinsman's shared content
Public Hearing Procedure
Hearing Examiner's Opening Statements
1. Staff Report and Recommendation
2. Applicant's Testimony
3. Public Testimony
4. Applicant's Rebuttal
5. Close Public Hearing - Decision will be issued within 14 days unless hearing is continued or the record is left open. There are fees for Open Records and Continuances
May 28, 2026
Clark County Land Use
CVTV_
Unmute
Raise
Shared Timer
Participants
Chat
11:26 slide
Land Use Hearing - May 28, 2026 Webinar Info
Richard Daviau
Daniel Kearns
David Jardin (Clark County)
Scott Taylor
Viewing Joe Kinsman's shared content
Public Hearing Procedure
Hearing Examiner's Opening Statements
1. Staff Report and Recommendation
2. Applicant's Testimony
3. Public Testimony
4. Applicant's Rebuttal
5. Close Public Hearing - Decision will be issued within 14 days unless hearing is continued or the record is left open. There are fees for Open Records and Continuances
May 28, 2026
Clark County Land Use
CVTV
13:53 slide
Webex Instructions
• Raise or lower hand (phone):
  • Dial *3
• Raise or lower hand (web):
  • Click hand in lower left-hand corner of your screen or next to your name in the list of participants
May 28, 2026
Clark County Land Use
CVTV
14:42 slide
Click hand in lower right-hand corner of your screen or next to name in list of participants You're sharing Microsoft PowerPoint Webex Instructions Raise or lower hand (web): - Click hand in lower right-hand corner of your screen Participants Q Search Panellist 1 Amy Wooten Host Attendee AW Amy Wooten Me
15:31 slide
Webex Instructions
• Raise or lower hand (web):
• Click hand in lower left-hand corner of your screen
• Raise or lower hand (phone):
• Dial *3
• Mute
• Open phone lines
• Chat disabled
May 28, 2026
Clark County Land Use
CVTV
16:20 slide
Land Use Hearing - May 28, 2026
Webinar Info
59:06
Layout
Richard Daviau
Joe Kinsman
David Jardin (Clark County)
Scott Taylor
Shared Timer
Unlocked
Sound on
Overtime off
Viewing Joe Kinsman's shared content
100%
Timer
20:00
+ 1m
+ 5m
+ 10m
Click microphone icon on the bottom of your screen
+ Add timer
Cisco Webex Meetings
Meeting Info Hide Menu Bar
You're sharing Microsoft PowerPoint
✓ Participants
Q Search
File Edit Share View Audio & Video Participant Meeting Breakout Sessions Help
✓ Panelist: 1
Webex Instructions
A
Amy Wooten
Host
✓ Attendee
• Raise or lower hand (web):
AW
Amy Wooten
Me
- Click hand in lower left-hand corner of your
screen
• Raise or lower hand (phone):
- Dial *3
Mute
Open phone lines
Chat disabled
Mute
May 28, 2026
Clark County Land Use
CVTV
16:46 slide
Land Use Hearing - May 28, 2026
Webinar Info
59:32
Layout
Shared Timer
Unlocked
Sound on
Overtime off
Richard Daviau
Joe Kinsman
David Jardin (Clark County)
Scott Taylor
Viewing Joe Kinsman's shared content
100%
Timer
20:00
+ 1m
+ 5m
+ 10m
+ Add timer
Land Use Public Hearing
Oslund Acres Subdivision
Joe Kinsman
May 28, 2026
May 28, 2026
Clark County Land Use
CVTV
Unmute
Raise
Shared Timer
Participants
Chat
17:58 slide
Presentation outline
* Provide an overview and summary of proposal
* Identify any major outstanding issues or concerns
* Make recommendation to the examiner
May 28, 2026
Clark County Land Use
Oslund Acres Subdivision
CVTV
18:47 slide
Zoning Map PF NE 92nd ST NE 91st ST NE 90th ST NE 88th ST NE 87th ST NE 92nd PL NE 91st PL NE 90th PL NE 89th PL NE 88th PL NE 87th PL NE 92nd AVE NE 91st AVE NE 90th AVE NE 89th AVE NE 88th AVE NE 87th AVE NE 92nd CT NE 91st CT NE 90th CT NE 89th CT NE 88th CT NE 87th CT NE 87th CR NE 86th WY IL R1-6 CC R1-7.5 May 28, 2026 Clark County Land Use Oslund Acres Subdivision CVTV
19:36 document
Land Use Hearing - May 28, 2026
Site Map
May 28, 2026
Clark County Land Use
Oslund Acres Subdivision
CVTV
20:25 document
OSLUND ACRES SUBDIVISION ENGINEERING & DESIGN PROFESSIONAL LAND SURVEYING CIVIL ENGINEERING – LAND PLANNING CONSTRUCTION STAKING LANDSCAPE ARCHITECTURE Proposed Plan PROPERTY ADDRESS PROPERTY LEGAL DESCRIPTION SETBACKS UTILITY INFORMATION GENERAL NOTES STORMWATER NOTES LANDSCAPING DISPOSAL PRELIMINARY SITE PLAN OSLUND ACRES SUBDIVISION WASHINGTON CLARK COUNTY PRELIMINARY REVISIONS Lot Numbers: 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20, 21, 22, 23, 24, 25, 26, 27, 28, 29, 30, 31, 32, 33, 34, 35, 36, 37, 38, 39, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 50, 51, 52, 53, 54, 55, 56, 57, 58, 59, 60, 61, 62, 63, 64, 65, 66, 67, 68, 69, 70, 71, 72, 73, 74 NE 76TH STREET NE 77TH STREET EXISTING RESIDENCE PROPOSED DETENTION LANDSCAPE LEGEND GUEST PARKING CALCULATION 87 RESIDENTIAL LOTS = 4C TYPICAL ON-STREET PARKING May 28, 2026 Clark County Land Use Oslund Acres Subdivision CVTV
21:14 slide
Land Use Hearing - May 28, 2026 Webinar Info Richard Daviau David Jardin (Clark County) Scott Taylor Viewing Joe Kinsman's shared content 100% NE 91st Ave looking north across NE 88th St. May 28, 2026 Clark County Land Use Oslund Acres Subdivision CVTV
22:03 slide
NE 88th looking north on NE 94th Ave
May 28, 2026
Clark County Land Use
Oslund Acres Subdivision
CVTV
22:52 slide
Looking south on NE 94th Ave at the intersection of NE 90th St.
May 28, 2026
Clark County Land Use
Oslund Acres Subdivision
23:41 slide
From the corner of 91st Place east facing towards NE 94th Ave
May 28, 2026
Clark County Land Use
Oslund Acres Subdivision
24:30 slide
Staff report
• The application submittal was received on November 26, 2025
• The application was deemed Fully Complete on January 29, 2026
• The Notice of Development Application was issued on February
06, 2026
• The Notice of Hearing Date change was issued on April 17, 2026
• Staff's recommendation to the Hearing Examiner was issued on
May 14, 2026 (Exhibit 76); there was no SEPA appeal, and the
SEPA is now finalized.
May 28, 2026
Clark County Land Use
Oslund Acres Subdivision
CVTV
25:19 slide
Project issues
For a full list of issues brought forth by the general public, see the public comment section of the staff report (Exhibit 76). Some of the items within the staff report are as follows:
• Street Width, Parking, and driveway standards that may prevent emergency services.
• The proposal adds additional traffic to an already constrained area. Additional traffic measures are needed.
• Stormwater management and drainage.
• ADA compliance for sidewalks and general sidewalk safety.
• Ingress and Egress points
• Current and future students and school capacity
• Geotech report and seismic concerns
May 28, 2026
Clark County Land Use
Oslund Acres Subdivision
CVTV_
26:08 slide
Land Use Hearing - May 28, 2026
Project issues
For a full list of issues brought forth by the general public, see the public comment section of the staff report (Exhibit 76). Some of the items within the staff report are as follows:
• Street Width, Parking, and driveway standards that may prevent emergency services.
• The proposal adds additional traffic to an already constrained area. Additional traffic measures are needed.
• Stormwater management and drainage.
• ADA compliance for sidewalks and general sidewalk safety.
• Ingress and Egress points
• Current and future students and school capacity
• Geotech report and seismic concerns
May 28, 2026
Clark County Land Use
Oslund Acres Subdivision
CVTV
26:57 document
Land Use Hearing - May 28, 2026 Webinar Info
Proposed Plan
OSLUND ACRES SUBDIVISION
ENGINEERING & DESIGN
CIVIL ENGINEERING • LAND PLANNING
SURVEYING • ARBORICULTURE
LANDSCAPE ARCHITECTURE
PRELIMINARY
PRELIMINARY SITE PLAN
OSLUND ACRES
SUBDIVISION
CLARK COUNTY WASHINGTON
REVISIONS
May 28, 2026
Clark County Land Use
Oslund Acres Subdivision
CVTV_
27:46 document
Proposed Plan
OSLUND ACRES SUBDIVISION
ENGINEERING & DESIGN
CIVIL ENGINEERING LAND PLANNING SURVEYING & MAPPING LANDSCAPE ARCHITECTURE
9110 NE 32ND WAY, SUITE 210, VANCOUVER, WA 98662
P (360) 906-1900, F (360) 906-1905
PRELIMINARY
WASHINGTON
OSLUND ACRES SUBDIVISION
PRELIMINARY SITE PLAN
PRELIMINARY REVISIONS
CLARK COUNTY
SHEET 1 OF 3
NORTH STREET
PRIVATE PROPERTY ADDRESS: 1234 NE 190TH ST, RIDGEFIELD WA 98642
PARCEL I TAX LOT: 04631024
PROJECT LOCATION: NORTH STREET & NE 192ND ST, RIDGEFIELD WA
OWNER / DEVELOPER: NW RESIDENTIAL DEV LLC, 13711 NW MEADOWS ROAD, VANCOUVER WA 98685
PROJECT NO: 021008
DATE: JAN 2022
SCALE: 1"=40'
ZONING DESIGNATION: R-1
EXISTING ZONING: R-1
REQUIRED SETBACKS: FRONT - 20', REAR - 10', SIDE - 5', SIDE - CORNER - 10'
PROPERTY INFORMATION
TOTAL LOTS: 82 LOTS
TOTAL ACREAGE: 5.00 AC
PROPOSED ROADWAY: 2750 LF +/-
OPEN SPACE: 0.70 AC
AVE LOT SIZE: 2800 SF +/-
NOTES:
1. THE PROPERTY IS CURRENTLY UNDEVELOPED WITH A SINGLE FAMILY RESIDENCE. A TYPE 3 VARIANCE FOR INCREASED DENSITY IS PENDING FOR RECONSIDERATION.
2. THE PROPERTY IS ZONED R-1 SINGLE FAMILY RESIDENTIAL.
Lot numbers visible on the plan range from 1 to 82.
May 28, 2026
Clark County Land Use
Oslund Acres Subdivision
CVTV
28:35 document
Proposed Plan
OSLUND ACRES SUBDIVISION
ENGINEERING & DESIGN
CIVIL ENGINEERING - LAND PLANNING
SURVEYING - MAPPING
LANDSCAPE ARCHITECTURE
3601 N.E. 112TH AVENUE SUITE 210
VANCOUVER, WASHINGTON 98682
PHONE (360) 254-2007 FAX (360) 254-2008
www.engineeringanddesign.us
PROPERTY
PRELIMINARY
REVISIONS
WASHINGTON
CLARK COUNTY
OSLUND ACRES SUBDIVISION
PRELIMINARY SITE PLAN
EXISTING DRIVEWAY APPROXIMATE LOCATION OFFSET +/- 5'
NORTH STREET
EAST SIDE DRIVING LANE
10' SIDE YARD SETBACK
(Lot numbers visible: 1-99)
LANDSCAPE LEGEND
OFF STREET PARKING CALCULATION
1.0 PARKING UNITS/DU. PER RES.
50 DWELLING LOTS = 50 SPACES
TYPICAL ON-STREET PARKING
May 28, 2026
Clark County Land Use
Oslund Acres Subdivision
29:24 document
Land Use Hearing - May 28, 2026
Webinar Info
01:12:10
Layout
Richard Daviau
David Jardin (Clark County)
Scott Taylor
Daniel Kearns
Viewing Joe Kinsman's shared content
Proposed Plan
OSLUND ACRES SUBDIVISION
ENGINEERING
& DESIGN
EXISTING
CONDITIONAL
USE PERMIT
CU-10-02
APRONNA
SP-01-002
CIVIL ENGINEERING - LAND PLANNING
SURVEYING - MAPPING
LANDSCAPE ARCHITECTURE
2013 BROADWAY
VANCOUVER WA 98663
PH (360) 694-8411
FAX (360) 694-8413
WWW.DANDYPDG.COM
69
70
68
71
67
66
72
73
74
65
75
64
76
63
77
62
78
61
79
60
80
59
81
58
82
57
83
56
84
55
85
54
86
53
87
52
88
51
89
PARCELS & PROPERTY ADDRESS
WASHINGTON
APPLICANT
OWNER
ADDRESS
PHONE
EMAIL
CONTACT
PROPERTY ADDRESS
TAX PARCEL NUMBER
ASSESSOR'S MAP
ZONING
OVERLAYS
TOTAL SITE AREA
NET SITE AREA
PARKING AREA
SITE COVERAGE
TOTAL SITE AREA
NET SITE AREA
PROPOSED USE
NUMBER OF UNITS
BUILDING HEIGHT
SETBACKS
MAXIMUM IMPERMEABLE AREA
PROPOSED IMPERMEABLE AREA
OPEN SPACE
PROPOSED OPEN SPACE
TOTAL SITE AREA
NET SITE AREA
OSLUND ACRES
SUBDIVISION
CLARK COUNTY
PRELIMINARY SITE PLAN
PRELIMINARY
REVISIONS
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
LANDSCAPE LEGEND
BIKE PARKING CALCULATION
20 BIKE SPACES REQUIRED
25 BIKE SPACES PROVIDED
20% PARKING LOTS
PARKING CALCULATION
1.5 PARKING SPACES PER UNIT
27 UNITS X 1.5 = 40.5 PARKING SPACES REQUIRED
41 PARKING SPACES PROVIDED
May 28, 2026
Clark County Land Use
Oslund Acres Subdivision
CVTV_
30:13 document
Land Use Hearing - May 28, 2026 Webinar Info Richard Daviau Daniel Kearns David Jardin (Clark County) Scott Taylor Viewing Joe Kinsman's shared content Proposed Plan OSLUND ACRES SUBDIVISION S. ENGINEERING & DESIGN CIVIL ENGINEERING LAND PLANNING SURVEYING PERMITTING LANDSCAPE ARCHITECTURE 2020 BROADWAY VANCOUVER, WA 98663 (360) 906-1188 WWW.S-E-D.COM PRELIMINARY OSLUND ACRES SUBDIVISION CLARK COUNTY WASHINGTON PRELIMINARY SITE PLAN REVISIONS DATE: 05/28/26 PROJECT NO.: 20042 SHEET: P-1.0 CALL FOR LOCATES: 811 ZONING: R-1-6 PARCEL NUMBERS: 169094000, 169096000, 169097000 SITE ADDRESS: 1222 NE SMITH DRIVE TOTAL ACREAGE: 15.65 AC NUMBER OF LOTS: 79 AVERAGE LOT AREA: 6,000 SF DENSITY: 5.05 DU/AC REQUIRED SETBACKS: FRONT: 20' SIDE: 5' REAR: 20' MINIMUM LOT WIDTH: 50' MINIMUM LOT DEPTH: 90' MAXIMUM BUILDING HEIGHT: 35' PARKING CALCULATION RESIDENTIAL 79 UNITS * 1.5 = 118.5 VISITOR 79 UNITS * 0.5 = 39.5 TOTAL 158 PARKING REQUIRED = 158 PARKING PROVIDED = 158 PREPARED BY: S. ENGINEERING & DESIGN EXISTING CONDITIONS APPROXIMATE WETLAND BOUNDARY SET-OFF LANDSCAPE LEGEND LOT NUMBERS: 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20, 21, 22, 23, 24, 25, 26, 27, 28, 29, 30, 31, 32, 33, 34, 35, 36, 37, 38, 39, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 50, 51, 52, 53, 54, 55, 56, 57, 58, 59, 60, 61, 62, 63, 64, 65, 66, 67, 68, 69, 70, 71, 72, 73, 74, 75, 76, 77, 78, 79 NE NEWTON ST NE FORD ROAD NE KELLEY DRIVE NE SMITH DRIVE THE NORTH STREET May 28, 2026 Clark County Land Use Oslund Acres Subdivision CVTV
31:02 document
Land Use Hearing - May 28, 2026 Webinar Info
Richard Daviau
Joe Kinsman
David Jardin (Clark County)
Scott Taylor
Viewing Joe Kinsman's shared content
100%
Proposed Plan
OSLUND ACRES SUBDIVISION
ENGINEERING & DESIGN
CIVIL ENGINEERING LAND PLANNING SURVEYING & MAPPING LANDSCAPE ARCHITECTURE
PROJECT NAME: OSLUND ACRES SUBDIVISION
PROPERTY ADDRESS: APPROXIMATELY AT 121 NE 172ND ST
LEGAL DESCRIPTION:
OWNER/APPLICANT: OSBORN DEVELOPMENT GROUP LLC
SITE AREA: 12.00 ACRES
APN: 110486-000
ZONING: R-1-6 (RESIDENTIAL)
OVERLAY DISTRICTS: NONE
COMPREHENSIVE PLAN DESIGNATION: R-1-6 (RESIDENTIAL)
MINIMUM LOT SIZE: 6,000 SF
MINIMUM LOT WIDTH: 60 FT
MINIMUM LOT DEPTH: 100 FT
MINIMUM FRONT YARD SETBACK: 20 FT
MINIMUM SIDE YARD SETBACK: 5 FT
MINIMUM REAR YARD SETBACK: 20 FT
MAXIMUM LOT COVERAGE: 50%
MAXIMUM BUILDING HEIGHT: 35 FT
MAXIMUM DENSITY: 7.2 DU/AC
MINIMUM OPEN SPACE: 20%
UTILITY PROVIDERS: CLARK PUBLIC UTILITIES (WATER), CLARK PUBLIC UTILITIES (SEWER), FRONTIER COMMUNICATIONS (COMMUNICATIONS), NW NATURAL GAS (NATURAL GAS), CLARK PUBLIC UTILITIES (ELECTRIC)
STORMWATER BASIN AREA: 0.50 AC
PROPOSED LOT COUNT: 90
PROPOSED LOT AREA: 9.00 AC
TOTAL SITE AREA: 12.00 AC
TOTAL LOT AREA: 9.00 AC
TOTAL OPEN SPACE AREA: 2.50 AC
PRELIMINARY
OSLUND ACRES SUBDIVISION
CLARK COUNTY
WASHINGTON
REVISIONS
PRELIMINARY REVISIONS
2023 PROPOSED
LANDSCAPE LEGEND
NORTH STREET
TYPICAL ON-STREET PARKING
BIKE PARKING CALCULATION
NO. RESIDENTIAL LOTS = 90
MINIMUM BIKE SPACES = 2 SPACES / 10 UNITS = 90/10*2 = 18 SPACES
May 28, 2026
Clark County Land Use
Oslund Acres Subdivision
CVTV
31:51 document
Proposed Plan
OSLUND ACRES SUBDIVISION
ENGINEERING & DESIGNS
CIVIL ENGINEERING LAND PLANNING
SURVEYING PERMITTING
LANDSCAPE ARCHITECTURE
PRELIMINARY
PRELIMINARY SITE PLAN
OSLUND ACRES SUBDIVISION
CLARK COUNTY
WASHINGTON
REVISIONS
P.E. & S.L.
PROJECT
LANDSCAPE LEGEND
TREE REMOVAL
IMPERVIOUS CALCULATION
TOTAL SITE AREA
NET SITE AREA
BUILDING FOOTPRINT
DRIVEWAY
PATIO/SIDEWALK
TOTAL IMPERVIOUS
PERVIOUS
STREETS
SIDEWALKS
CURB & GUTTER
UTILITIES
WATER
SEWER
STORM
SITE ADDRESS
LEGAL DESCRIPTION
VICINITY MAP
EXISTING ZONING
PROPOSED ZONING
APPLICANT
OWNER
CONTRACTOR
CONSULTANT
NOTES:
PROPERTY [red stamp]
NE 80TH STREET
Many lot numbers (e.g., 1-75, 76-100, 260-3070)
May 28, 2026
Clark County Land Use
Oslund Acres Subdivision
CVTV
32:40 document
OSLUND ACRES SUBDIVISION
S ENGINEERING & DESIGN
CIVIL ENGINEERS - LAND PLANNERS
SURVEYORS - ARBORISTS
LANDSCAPE ARCHITECTURE
3103 NW BROADWAY
VANCOUVER WA
98663
PHONE: (360) 695-1381
FAX: (360) 693-5705
Proposed Plan
PRELIMINARY SITE PLAN
OSLUND ACRES
SUBDIVISION
WASHINGTON
CLARK COUNTY
PRELIMINARY
REVISIONS
DESIGNED BY: CM
CHECKED BY: CM
JOB NUMBER: 2453
SHEET: PRE5.0
APPLICANT:
CONTACT:
SURVEYOR:
CONSULTING ENGINEER:
WATER SERVICE:
SEWER SERVICE:
PARCEL # PROPERTY ADDRESS
TOTAL ACRES: 10.15 AC
TOTAL NUMBER OF LOTS: 94
TOTAL NUMBER OF TRACTS: 2
AVERAGE LOT SIZE: 7,494 SF
AVERAGE LOT WIDTH: 65 FT
AVERAGE LOT DEPTH: 115 FT
SETBACKS:
FRONT: 20'
SIDE: 5'
REAR: 20'
CORNER SIDE: 10'
OPEN SPACE:
REQUIRED: 10.00% 1.015 AC
PROVIDED: 1.15 AC (11.33%)
PRIVATE OPEN SPACE
STREETS: PRIVATE
WETLANDS
NOTE:
THIS PROPERTY IS NOT LOCATED IN A FLOODPLAIN
THIS PROPERTY IS NOT LOCATED IN A GEOLOGIC HAZARD AREA
THIS IS A PRELIMINARY PLAN AND NOT FOR CONSTRUCTION
NORTH ARROW
SCALE: 1" = 80'
NE 76TH STREET
NE 72ND AVE
NE 75TH STREET
NE 75TH STREET
EXISTING
Lot numbers (various): 1-28, 39-67, 68-94
33:29 document
Proposed Plan
OSLUND ACRES SUBDIVISION
ENGINEERING & DESIGN
CIVIL ENGINEERING LAND PLANNING
SURVEYING PROJECT MANAGEMENT
LANDSCAPE ARCHITECTURE
2013 BROADWAY
VANCOUVER, WA 98663
PHONE (360) 906-1185
FAX (360) 906-1186
APPLICANT
DAVID JARDIN
CLARK COUNTY
APN
TAX LOTS
NUMBER OF PARCELS
SITE AREA
ZONING
COMPREHENSIVE PLAN
EXISTING USE
PROPOSED USE
PREPARED FOR
OSLUND ACRES SUBDIVISION
LOT AREA
MINIMUM LOT WIDTH
MINIMUM LOT DEPTH
SETBACKS
FRONT
SIDE
REAR
MAXIMUM HEIGHT
MAXIMUM LOT COVERAGE
REQUIRED PARKING
UTILITY PROVIDER
WATER
SEWER
STORM
POWER
CABLE
PHONE
FIRE DISTRICT
NOTES
LANDSCAPE LEGEND
PRELIMINARY SITE PLAN
OSLUND ACRES
SUBDIVISION
WASHINGTON
CLARK COUNTY
PRELIMINARY
REVISIONS
LANDSCAPE LEGEND
DWELLING UNITS
PARKING CALCULATION
TYPICAL ON-STREET PARKING
ZONING: R30
DATE: 2023
EXISTING
OFF SITE
BUFFER
APPROXIMATE
The North Street
Lot Numbers: 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20, 21, 22, 23, 24, 25, 26, 27, 28, 29, 30, 31, 32, 33, 34, 35, 36, 37, 38, 39, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 50, 51, 52, 53, 54, 55, 56, 57, 58, 59, 60, 61, 62, 63, 64, 65, 66, 67, 68, 69, 70, 71, 72, 73, 74, 75, 76, 77, 78, 79, 80
May 28, 2026
Clark County Land Use
Oslund Acres Subdivision
CVTV_
34:18 document
Proposed Plan
OSLUND ACRES SUBDIVISION
ENGINEERING & DESIGN
PRELIMINARY SITE PLAN
OSLUND ACRES SUBDIVISION
WASHINGTON
CLARK COUNTY
PRELIMINARY
REVISIONS
NE 199TH STREET
NE 197TH ST
NE 196TH ST
NE 24TH ST
Lot numbers: 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20, 21, 22, 23, 24, 25, 26, 27, 28, 29, 30, 31, 32, 33, 34, 35, 36, 37, 38, 39, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 50, 51, 52, 53, 54, 55, 56, 57, 58, 59, 62, 71, 74, 80, 81, 82, 83, 84, 85, 86, 87, 88, 89, 90, 91, 92, 93, 94, 95, 96, 97, 98, 99
PARCEL / PROPERTY ADDRESS
COUNTY
TOTAL ACREAGE
ASSESSOR
EXISTING ZONING
PROPOSED ZONING
MINIMUM LOT AREA
FRONTAGE
BUILDING SETBACKS:
SIDE YARD
REAR YARD
PARKING:
NOTES:
SETBACKS
UTILITY EASEMENTS:
STORMWATER:
LANDSCAPING:
LIGHTING:
GEOTECH:
SOILS:
WATER:
SEWER:
SURVEY:
APPLICABLE CITY AND COUNTY CODES
PROPERTY IS LOCATED
PROPOSED
TOTAL LOTS
PUBLIC RIGHT OF WAY
NEW PUBLIC STREETS
NEW PRIVATE STREETS
TOTAL PUBLIC STREET
TOTAL PRIVATE STREET
LANDSCAPE LEGEND
GATED COMMUNITY
COMMONS
OPEN SPACE
DUST PARKING CALCULATION
TYPICAL ON-STREET PARKING
May 28, 2026
Clark County Land Use
Oslund Acres Subdivision
CVTV
35:07 document
Land Use Hearing - May 28, 2026 Webinar Info
Richard Daviau
Daniel Kearns
David Jardin (Clark County)
Alister Dawson
Viewing Joe Kinsman's shared content
100%
OSLUND ACRES SUBDIVISION
Proposed Plan
20
PROPERTY
ENGINEERING
& DESIGN
OSLUND ACRES
SUBDIVISION
WASHINGTON
CLARK COUNTY
PRELIMINARY
REVISIONS
LANDSCAPE LEGEND
May 28, 2026
Clark County Land Use
Oslund Acres Subdivision
CVTV
Shared Timer
35:56 document
Proposed Plan
OSLUND ACRES SUBDIVISION
ENGINEERING
& DESIGN
CIVIL ENGINEERING • LAND PLANNING
SURVEYING • LANDSCAPE ARCHITECTURE
PROPERTY
PRELIMINARY SITE PLAN
OSLUND ACRES
SUBDIVISION
WASHINGTON
CLARK COUNTY
EXISTING
DETENTION POND
APPROVED IN
WR-225
EXISTING
WETLAND
APPROXIMATE
LOCATION
74 71 62 69
70 63
56
55 54 53 48 47
46
45 44 43 42 41 40 39
28 29 30 31 32 33 34 35 36 37 38
27
26 25 24 23 22 21 20 19
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
PRELIMINARY
REVISIONS
May 28, 2026
Clark County Land Use
Oslund Acres Subdivision
CVTV
LANDSCAPE LEGEND
PARKING CALCULATION
GUEST PARKING CALCULATION
MINIMUM LOTS = 48
36:45 document
Proposed Plan OSLUND ACRES SUBDIVISION ENGINEERING & DESIGN CIVIL ENGINEERING LAND PLANNING PROJECT MANAGEMENT SURVEYING LANDSCAPE ARCHITECTURE 3601 BROADWAY STREET SUITE 210 VANCOUVER, WA 98663 PHONE: (360) 693-5188 FAX: (360) 693-1960 Email: info@engrdes.com Web: www.engrdes.com PROPERTY PRELIMINARY REVISIONS OSLUND ACRES SUBDIVISION WASHINGTON CLARK COUNTY Existing Residence Approximate SF = 1200 THE 17TH STREET SW 17TH ST PARCEL HISTORY & PROPERTY ADDRESS PARCEL NUMBER: ADDRESS: DEVELOPMENT NAME: LEGAL DESCRIPTION: GROSS SITE AREA: BUILDABLE AREA: NET SITE AREA: AVERAGE LOT AREA: OPEN SPACE: RECREATION: LANDSCAPE: EXISTING TREES: NEW TREES: TOTAL TREES: SITE PARKING CALCULATION TOTAL PARKING LOTS = 40 PROPOSED LOTS = 40 TOTAL PARKING = 80 VISITOR PARKING SPACES = 40 TYPICAL ON-STREET PARKING LANDSCAPE LEGEND May 28, 2026 Clark County Land Use Oslund Acres Subdivision CVTV_
37:34 document
Proposed Plan
OSLUND ACRES SUBDIVISION
ENGINEERING & DESIGN
CIVIL ENGINEERS - LAND PLANNERS
SURVEYORS - ARBORISTS
LANDSCAPE ARCHITECTURE
PRELIMINARY
PRELIMINARY SITE PLAN
OSLUND ACRES SUBDIVISION
WASHINGTON
CLARK COUNTY
PRELIMINARY
REVISIONS
PROJECT PROPERTY ADDRESS
LOTS AND TRACKS
STORMWATER BASIN PROPERTY
COMMON AREAS
MINIMUM LOT AREA
LANDSCAPE LEGEND
TYPICAL ON-STREET PARKING
GUEST PARKING CALCULATION
May 28, 2026
Clark County Land Use
Oslund Acres Subdivision
CVTV
38:23 slide
Land Use Hearing - May 28, 2026 Webinar Info Scott Taylor Viewing Joe Kinsman's shared content David Jardin (Clark County) Allister Dawson 100% + OSLUND ACRES SUBDIVISION Proposed Plan ENGINEERING & DESIGN CIVIL ENGINEERING - LAND PLANNING SURVEYING - FORESTRY - LANDSCAPE ARCHITECTURE 1203 PROMONTORY STREET S.W., SUITE 300 OLYMPIA, WA 98502 PHONE: (360) 943-6900 FAX: (360) 943-4244 PROPERTY OWNER INFORMATION OSLUND PROPERTY ADDRESS: 1414 N.E. 119TH STREET VANCOUVER, WA 98665 TAX ACC'T #: 178550-000 PROJECT INFORMATION PROJECT NAME: OSLUND ACRES SUBDIVISION PROJECT ADDRESS: 1414 N.E. 119TH STREET APPLICANT: JERRY OSWALD ADDRESS: 1414 N.E. 119TH STREET VANCOUVER, WA 98665 CONTACT PERSON: JERRY OSWALD PHONE: (360) 567-2700 EMAIL: JOELOSWALD@Q.COM CONSULTANT: ENGINEERING & DESIGN DATE: MAY 28, 2026 NUMBER OF LOTS: 90 TOTAL SITE AREA: 19.33 AC MINIMUM LOT AREA: 4,000 SF AVERAGE LOT AREA: 6,000 SF TOTAL IMPERVIOUS AREA TOTAL IMPERVIOUS AREA (PROPOSED): 10.98 AC OSLUND ACRES SUBDIVISION WASHINGTON CLARK COUNTY PRELIMINARY REVISIONS PRELIMINARY SITE PLAN PARKING CALCULATION REQUIRED PARKING 1.5 SPACE PER DWELLING UNIT (1.5 X 90 = 135) 20% VISITORS (20% X 90 = 18) TOTAL: 153 SPACES PROPOSED PARKING 90 ON-STREET SPACES 63 OF-STREET SPACES TOTAL: 153 SPACES EXISTING RESIDENCE APPROXIMATE BOUNDARY LINE OF 1978 SEWAGE EASEMENT NE 11TH AVENUE A NE 12TH AVENUE A THE NANCY STREET LANDSCAPE LEGEND TYPICAL ON-STREET PARKING 01:21:09 Layout Shared Timer Unlocked Sound on Overtime off Timer II 17 : 51 + 1m + 5m + 10m + Add timer May 28, 2026 Clark County Land Use Oslund Acres Subdivision CVTV Unmute Raise Shared Timer Participants Chat
39:12 document
Land Use Hearing - May 28, 2026
Webinar Info
Scott Taylor
David Jardin (Clark County)
Allister Dawson
Viewing Joe Kinsman's shared content
100%
Proposed Plan
OSLUND ACRES SUBDIVISION
ENGINEERING
& DESIGN
CIVIL ENGINEERING - LAND PLANNING
SURVEYING - FORESTRY
LANDSCAPE ARCHITECTURE
PRELIMINARY
PROPERTY ADDRESS:
PARCEL NUMBER:
LEGAL DESCRIPTION:
ASSESSOR'S MAP REFERENCE:
PRELIMINARY SITE PLAN
OSLUND ACRES
SUBDIVISION
WASHINGTON
CLARK COUNTY
PRELIMINARY
REVISIONS
EXISTING DWELLING APPROXIMATELY 100 SF
LOTS: 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20, 21, 22, 23, 24, 25, 26, 27, 28, 29, 30, 31, 32, 33, 34, 35, 36, 37, 38, 39, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 50, 51, 52, 53, 54, 55, 56, 57, 58, 59, 60, 61, 62, 63, 64, 65, 66, 67, 68, 69, 70, 71, 72, 73, 74, 75, 76, 77, 78, 79, 80, 81, 82, 83, 84, 85, 86, 87, 88
LANDSCAPE LEGEND
SITE PARKING CALCULATION
PROPOSED DEVELOPMENT SUMMARY
TOTAL SITE AREA
NET SITE AREA
GROSS DENSITY
NET DENSITY
TOTAL LOTS
OPEN SPACE
OPEN SPACE AREA
OPEN SPACE PERCENT
STREET
DRIVEWAY
ROAD
CURB
SIDEWALK
UTILITY EASEMENT
WATER
SEWER
STORM
GAS
CABLE
POWER
TELEPHONE
FIRE
BUILDING SETBACKS
FRONT
SIDE
REAR
REVERSE FRONTAGE
LOT WIDTH
LOT DEPTH
LOT SIZE
BUILDING HEIGHT
MAXIMUM LOT COVERAGE
MINIMUM LOT AREA
MINIMUM LOT WIDTH
MINIMUM LOT DEPTH
MINIMUM FRONTAGE
MINIMUM SETBACKS
EXISTING ZONING
PROPOSED ZONING
COMPREHENSIVE PLAN
PLANNED ACTION
ENVIRONMENTAL REVIEW
WATER SERVICE
SEWER SERVICE
STORMWATER
TRANSPORTATION
TREES
PARKING
LANDSCAPING
LIGHTING
NOISE
GEOTECHNICAL
FIRE PROTECTION
PUBLIC SERVICES
SCHOOL DISTRICT
UTILITIES
POWER
TELEPHONE
CABLE
GAS
2023
SHEET
01:21:58
Layout
Shared Timer
Unlocked
Sound on
Overtime off
Timer
17:02
+ 1m
+ 5m
+ 10m
+ Add timer
May 28, 2026
Clark County Land Use
Oslund Acres Subdivision
CVTV_
40:01 slide
Land Use Hearing - May 28, 2026
Webinar Info
Scott Taylor
David Jardin (Clark County)
Alister Dawson
Viewing Joe Kinsman's shared content
Proposed Plan
EXISTING
STREET TREES
APPROXIMATE
LOCATION ONLY
DO NOT SCALE
OSLUND ACRES SUBDIVISION
ENGINEERING & DESIGN
CIVIL ENGINEERING • LAND PLANNING
SURVEYING • CONSTRUCTION
LANDSCAPE ARCHITECTURE
2030 BROADWAY
VANCOUVER WA 98663
P (360) 906-1111 F (360) 906-1112
E info@eandd.com W www.eandd.com
PARCEL NUMBER
PROPERTY ADDRESS
OWNERSHIP
GENERAL NOTES
ZONING: R-1-10 (RESIDENTIAL)
COMP. PLAN DESIGNATION: MEDIUM DENSITY RESIDENTIAL
TOTAL SITE AREA: 24.38 AC
REQUIRED F.A.R.: N/A
TOTAL BUILDABLE AREA: N/A
SETBACKS:
FRONT: 20'
SIDE: 5'
REAR: 10'
LOT COVERAGE: 35% MAX
MAX. HEIGHT: 35'
PARKING: MIN. 2 SPACES / DWELLING
OPEN SPACE: MIN. 10% (OF GROSS AREA) = 2.44 AC
LANDSCAPE BUFFER: 10' ALONG MAJOR STREETS, 5' ALONG MINOR STREETS
IRRIGATION: REQUIRED FOR ALL LANDSCAPING
DRAINAGE:
WATER:
SEWER:
UTILITY PROVIDER:
ACCESS:
DISPOSAL:
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51
52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90
NE 164TH STREET
LANDSCAPE LEGEND
PARKING CALCULATION
RESIDENTIAL LOTS = 4C
RESIDENTIAL LOTS = 4C
WASHINGTON
OSLUND ACRES SUBDIVISION
PRELIMINARY SITE PLAN
CLARK COUNTY
PRELIMINARY
REVISIONS
N
TYPICAL ON-STREET PARKING
2453
PRE.R.
SHEET
May 28, 2026
Clark County Land Use
Oslund Acres Subdivision
CVTV
40:50 document
Proposed Plan; OSLUND ACRES SUBDIVISION; ENGINEERING & DESIGN; CIVIL ENGINEERING LAND PLANNING; SURVEYING & GEOSPATIAL; LANDSCAPE ARCHITECTURE; 3600 JEFFERSON BLVD STE 130; VANCOUVER WA 98660; 360.258.9110; WWW.ENGINEERING-DESIGN.COM; PRELIMINARY; OSLUND ACRES SUBDIVISION; WASHINGTON; CLARK COUNTY; PRELIMINARY; REVISIONS; NORTH 88th STREET; NORTH STREET; EXISTING STORM WATER UTILITY EASEMENT; Lot Numbers: 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20, 21, 22, 23, 24, 25, 26, 27, 28, 29, 30, 31, 32, 33, 34, 35, 36, 37, 38, 39, 40, 41, 42, 43, 44, 45, 46, 47, 48, 50, 51, 52, 53, 54, 55, 56, 57, 58, 59, 60, 61, 62, 63, 64, 65, 66, 67, 68, 69, 70, 71, 72, 73, 74, 75, 76, 77, 78, 79, 80, 81, 82, 83, 84, 85, 86, 87, 88, 89, 90, 91; May 28, 2026; Clark County Land Use; Oslund Acres Subdivision; CVTV
41:39 document
Proposed Plan
OSLUND ACRES SUBDIVISION
ENGINEERING & DESIGN
CIVIL ENGINEERING LAND PLANNING LANDSCAPE ARCHITECTURE
2103 NORTHWEST STROH AVENUE
VANCOUVER, WASHINGTON
PRELIMINARY
PRELIMINARY SITE PLAN
OSLUND ACRES SUBDIVISION
WASHINGTON
CLARK COUNTY
REVISIONS
EXISTING
EXISTING
28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
NE 150th STREET
EAST 16th STREET
May 28, 2026
Clark County Land Use
Oslund Acres Subdivision
CVTV
42:28 document
Land Use Hearing - May 28, 2026
Webinar Info
01:25:14
Layout
Shared Timer
Unlocked
Sound on
Overtime off
Timer
13:46
+ 1m
+ 5m
+ 10m
+ Add timer
Scott Taylor
Joe Kinsman
Daniel Kearns
David Jardin (Clark County)
Allister Dawson
Viewing Joe Kinsman's shared content
100%
OSLUND ACRES SUBDIVISION
Proposed Plan
ENGINEERING & DESIGN
CIVIL ENGINEERING LAND PLANNING
SURVEYING & MAPPING
LANDSCAPE ARCHITECTURE
PROPRIETARY
PRELIMINARY
WASHINGTON
OSLUND ACRES SUBDIVISION
CLARK COUNTY
PRELIMINARY
REVISIONS
PARCEL & PROPERTY ADDRESS
OWNER/APPLICANT
DEVELOPER
PROJECT
PROPERTY DATA
PROPOSED
REMAINING
TOTAL
DEVELOPMENT STANDARDS
MIN. LOT SIZE
MIN. LOT WIDTH
MIN. SETBACKS
LANDSCAPE LEGEND
EXISTING
LANDSCAPING
NE 88TH STREET
SHEET NO.
DATE
REVISIONS
PROJECT NO.
May 28, 2026
Clark County Land Use
Oslund Acres Subdivision
CVTV
Unmute
Raise
Shared Timer
Participants
Chat
43:17 document
Land Use Hearing - May 28, 2026
Webinar Info
Scott Taylor
David Jardin (Clark County)
Alister Dawson
Viewing Joe Kinsman's shared content
100%
OSLUND ACRES SUBDIVISION
ENGINEERING
& DESIGN
Proposed Plan
SURVEYING
CIVIL ENGINEERING
LAND PLANNING
SITE DEVELOPMENT
LANDSCAPE ARCHITECTURE
2000 BROADWAY
VANCOUVER, WA 98663
(360) 571-0428
www.esdsurvey.com
OWNER/APPLICANT:
SITE AREA: 4.88 AC GROSS
ZONING: R-1-6
PARCEL NO.: 188372000, 188373000
PROPERTY ADDRESS:
10427 NE 117TH AVE, VANCOUVER, WA
10425 NE 117TH AVE, VANCOUVER, WA
LEGAL DESCRIPTION:
ASSESSOR'S MAP 2506, SECTION 23, TOWNSHIP 3 NORTH, RANGE
2 EAST, W.M., CLARK COUNTY, WASHINGTON.
CONDITIONS OF APPROVAL:
THIS FINAL PLAT IS SUBJECT TO THE APPROVAL OF CLARK
COUNTY PUBLIC WORKS, COMMUNITY DEVELOPMENT, AND THE FIRE
MARSHAL. A COPY OF THE APPROVED PRELIMINARY PLAT WITH THE
CONDITIONS OF APPROVAL HAS BEEN FILED FOR RECORDING.
NOTES:
1. ALL AREAS SHOWN ON THIS PLAN ARE APPROXIMATE AND ARE FOR
PLANNING PURPOSES ONLY.
2. ALL SETBACKS ARE TO BE PER THE R-1-6 ZONING CLASSIFICATION.
3. PARKING REQUIREMENTS ARE PER CLARK COUNTY CODE 40.260.030.
4. OPEN SPACE REQUIREMENTS ARE PER CLARK COUNTY CODE 40.230.010.
5. STORMWATER MANAGEMENT IS PER CLARK COUNTY CODE 40.380.010.
6. THE PROPERTY IS LOCATED WITHIN THE HAZARD OVERLAY DISTRICT.
7. MINIMUM LOT SIZE AREA: 6,000 SF
8. MINIMUM LOT WIDTH: 50 FT
9. ALL PRIVATE UTILITIES SHALL BE PLACED UNDERGROUND.
10. ACCESS TO NE 117TH AVENUE IS LIMITED TO THE PROPOSED
STREET.
PROPOSED SITE SUMMARY:
NUMBER OF LOTS: 46
GROSS SITE AREA: 4.88 ACRES
NET LOT AREA: 4.09 ACRES
TOTAL OPEN SPACE: 0.79 ACRES
AVERAGE LOT AREA: 3,846 SF
LOTS: 1-76
NE 117TH STREET
LANDSCAPE LEGEND
PUBLIC PARKING CALCULATION
OSLUND ACRES
SUBDIVISION
WASHINGTON
PRELIMINARY
REVISIONS
CLARK COUNTY
PRELIMINARY SITE PLAN
May 28, 2026
Clark County Land Use
Oslund Acres Subdivision
CVTV
44:06 slide
Proposed Plan
OSLUND ACRES SUBDIVISION
ENGINEERING & DESIGN
CIVIL ENGINEERING LAND PLANNING
SURVEYING WATER RESOURCES
PERMITTING LANDSCAPE ARCHITECTURE
2801 BROADWAY STREET, VANCOUVER WA 98663
PRELIMINARY SITE PLAN
PRELIMINARY
WASHINGTON
CLARK COUNTY
OSLUND ACRES SUBDIVISION
EXISTING SANITARY SEWER EASEMENT
EXISTING WATER MAINS
NW 179TH STREET
PUBLIC STREET
APPLICANT NAME & ADDRESS
PROPERTY OWNER
ASSESSORS PARCEL NUMBER
LEGAL DESCRIPTION
SITE ADDRESS
WATER
SEWER
ZONE
COMPREHENSIVE PLAN
PROPERTY SIZE
AVG. LOT SIZE
MAXIMUM BUILDING HEIGHT
MAXIMUM LOT COVERAGE
MINIMUM SETBACKS
MINIMUM LANDSCAPING
OPEN SPACE
DRAINAGE
PARKING
SIGNAGE
Lots 1-100
OFF STREET PARKING CALCULATION
LANDSCAPE LEGEND
PRELIMINARY REVISIONS
May 28, 2026
Clark County Land Use
Oslund Acres Subdivision
44:55 slide
Land Use Hearing - May 28, 2026 Webinar Info Scott Taylor David Jardin (Clark County) Allister Dawson Viewing Joe Kinsman's shared content Proposed Plan OSLUND ACRES SUBDIVISION ENGINEERING & DESIGNS CIVIL ENGINEERING LAND PLANNING SURVEYING PROJECT MANAGEMENT LANDSCAPE ARCHITECTURE 2020 BROADWAY VANCOUVER, WA 98663 PHONE: 360-906-8977 FAX: 360-906-8978 PRELIMINARY PROPERTY PRELIMINARY SITE PLAN OSLUND ACRES SUBDIVISION WASHINGTON CLARK COUNTY REVISIONS PROJECT NAME: OSLUND ACRES SUBDIVISION APPLICANT: JERRY OSWALD LOCATION: SW CORNER OF NE 132ND AVE & NE 104TH ST ASSESSOR'S TAX PARCEL #: 160039-000 SHEET #: 1 OF 1 DATE: MAY 28, 2026 SCALE: 1" = 50' APPLICANT: JERRY OSWALD PARCEL #: 160039-000 PROPERTY ADDRESS: 10405 NE 132ND AVE VANCOUVER, WA 98682 CURRENT ZONING: R1-7.5 (RESIDENTIAL) COMP PLAN DESIGNATION: URBAN LOW DENSITY RESIDENTIAL PROPERTY AREA: 10.15 AC GROSS, 9.20 AC NET AREA OF NEW LOTS: 5.76 AC LOTS: 74 EXISTING: 1 (SINGLE FAMILY) PROPOSED: 74 (SINGLE FAMILY) NUMBER OF LOTS: 74 OPEN SPACE: 1.48 AC DENSITY: 8.04 DU/AC NET PRIVATE ROAD: 0.81 AC UTILITY EASEMENT: 0.81 AC EXISTING STORM DETENTION LANDSCAPE LEGEND O RESIDENCE SITE PARKING CALCULATION REQUIRED: 1.5 SPACES PER LOT (74 LOTS X 1.5 SPACES) = 111 SPACES PROVIDED: 2 SPACES PER LOT (74 LOTS X 2 SPACES) = 148 SPACES TYPICAL DRIVEWAY PARKING PARKING May 28, 2026 Clark County Land Use Oslund Acres Subdivision CVTV 01:27:41 Layout Shared Timer Unlocked Sound on Overtime off Timer 11 : 19 + 1m + 5m + 10m + Add timer Unmute Raise Shared Timer Participants Chat
45:44 document
Land Use Hearing - May 28, 2026 Webinar Info Proposed Plan OSLUND ACRES SUBDIVISION ENGINEERING & DESIGN CIVIL ENGINEERING • LAND PLANNING • LANDSCAPE ARCHITECTURE 2013 BROADWAY VANCOUVER, WA 98663 PH (360) 906-1180 FAX (360) 906-1181 PRELIMINARY WASHINGTON PRELIMINARY SITE PLAN OSLUND ACRES SUBDIVISION CLARK COUNTY PRELIMINARY REVISIONS LANDSCAPE LEGEND PARKING CALCULATION TYPICAL ON-STREET PARKING NW 11TH STREET May 28, 2026 Clark County Land Use Oslund Acres Subdivision CVTV
46:33 slide
Land Use Hearing - May 28, 2026
Webinar Info
Scott Taylor
David Jardin (Clark County)
Alister Dawson
Viewing Joe Kinsman's shared content
100%
+
Proposed Plan
OSLUND ACRES SUBDIVISION
ENGINEERING
& DESIGN
CIVIL ENGINEERING LAND PLANNING
SURVEYING WATERSHED SCIENCES
LANDSCAPE ARCHITECTURE
2300 BROADWAY
VANCOUVER, WA 98663
PHONE 360-695-1800
FAX 360-695-2020
PRELIMINARY
OSLUND ACRES
SUBDIVISION
WASHINGTON
CLARK COUNTY
PRELIMINARY SITE PLAN
REVISIONS
LANDSCAPE LEGEND
BIKE PARKING CALCULATION
TOTAL BIKE PARKING REQUIRED: 120 (48.4 - 15) = 15 SPACES
TYPICAL ON-STREET PARKING
-N-
DEVELOPMENT SUMMARY
BUILDING SETBACKS
MINIMUM FRONT SETBACK: 10'
MINIMUM SIDE SETBACK: 5'
MINIMUM REAR SETBACK: 10'
PARKING PROVIDED
RESIDENTIAL
COMMERCIAL
TOTAL PARKING
ACCESSIBLE
COMPACT
STANDARD
TOTAL REQUIRED
(Numerous lot numbers and other small text details on the plan are present but not clearly legible)
May 28, 2026
Clark County Land Use
Oslund Acres Subdivision
CVTV
47:22 document
Proposed Plan
OSLUND ACRES SUBDIVISION
ENGINEERING & DESIGN
CIVIL ENGINEERING - LAND PLANNING
ARCHITECTURE
SURVEYING
LANDSCAPE ARCHITECTURE
PRELIMINARY
PARCEL 1 PROPERTY ADDRESS
APPLICANT
OWNER
PROPOSED USE
SITE AREA
PROPOSED LOTS
PROPERTY ACCESS
DEVELOPMENT STANDARD
TYPICAL UTILITY
STORMWATER
SEWER
WATER
FIRE
VEGETATION
SOILS
PARKING
PROPOSED STREET TREES
PRELIMINARY SITE PLAN
OSLUND ACRES SUBDIVISION
WASHINGTON
CLARK COUNTY
PRELIMINARY
REVISIONS
May 28, 2026
Clark County Land Use
Oslund Acres Subdivision
CVTV
48:11 document
Land Use Hearing - May 28, 2026 Webinar Info Viewing Joe Kinsman's shared content Proposed Plan OSLUND ACRES SUBDIVISION ENGINEERING & DESIGN PRELIMINARY WASHINGTON OSLUND ACRES SUBDIVISION CLARK COUNTY NE 164TH STREET NE 163RD STREET NE 119TH STREET PROPERTY ADDRESSES NOTES PARKING REVISIONS PLAT OF OSLUND ACRES LANDSCAPE LEGEND May 28, 2026 Clark County Land Use Oslund Acres Subdivision
49:00 document
Land Use Hearing - May 28, 2026
Webinar Info
Speaking: Jacob Weathers
Proposed Plan
OSLUND ACRES SUBDIVISION
ENGINEERING & DESIGN
CIVIL ENGINEERING LAND PLANNING
SURVEYING PROJECT MANAGEMENT
LANDSCAPE ARCHITECTURE
SITE CIVIL ENGINEERS
PRELIMINARY
WELLSPOINT SITE PLAN
OSLUND ACRES
SUBDIVISION
WASHINGTON
CLARK COUNTY
PRELIMINARY
REVISIONS
EXISTING HOUSE
PROPERTY ADDRESS
PROPERTY NUMBER
LOT AREA
OWNERSHIP
PROPOSED USE
PROPOSED LOTS
PROPOSED DRIVEWAYS
PROPOSED BUILDINGS
PROPOSED PARKING
PROPOSED LANDSCAPE
PROPOSED FENCING
PROPOSED UTILITIES
PROPOSED ROADWAYS
PROPOSED STORMWATER
PROPOSED GRADING
PROPOSED LIGHTING
PROPOSED SIGNAGE
PROPOSED ACCESS
PROPOSED DENSITY
DEVELOPMENT
LANDSCAPE LEGEND
PARKING CALCULATIONS
TOTAL REQUIRED SPACES
MINIMUM REQUIRED SPACES
TOTAL PROPOSED SPACES
REQUIRED PARKING
# DWELLING UNITS
# PARKING SPACES
# OF PARKING LOTS < 40
TYPICAL ON-STREET PARKING
May 28, 2026
Clark County Land Use
Oslund Acres Subdivision
CVTV_
49:49 document
Proposed Plan OSLUND ACRES SUBDIVISION ENGINEERING & DESIGN CIVIL ENGINEERING & LAND PLANNING SURVEYING LANDSCAPE ARCHITECTURE PROPERTY ADDRESS: APPLICANT: ADDRESS: PHONE: EMAIL: PROPERTY ADDRESS: TAX ID #: CURRENT ZONE: PROPOSED ZONE: GROSS SITE AREA: NET AREA: NUMBER OF LOTS: PROPOSED USE: EXISTING WATER: EXISTING SEWER: STORM DISPOSAL: FLOOD HAZARD: A-D WETLAND (UNREADABLE TEXT) SITE DATA TABLE EXISTING CONDITIONS: (UNREADABLE TEXT) This plan is preliminary and for review purposes only. Acreage: Average lot area: Minimum lot width: Proposed density: Maximum impervious: Pervious area: Recreation: REQUIRED: PROVIDED: BIKE PARKING CALCULATION: MINIMUM LOTS = 40 REQUIRED: 2.0 SPACES/LOT TOTAL REQUIRED: 90 LOTS * 2.0 = 180 SPACES TOTAL PROVIDED: 180 SPACES LOADING: LANDSCAPE LEGEND: RECREATION: PARK: OPEN SPACE: WASHINGTON PRELIMINARY SITE PLAN OSLUND ACRES SUBDIVISION CLARK COUNTY PRELIMINARY REVISIONS NORTH STREET (lot numbers visible: 1-93) PROPERTY EXISTING STORM EXISTING R/W EXISTING STREET PREPARED FOR: PROJECT NO: PHASE: DRAWING NO: TYPICAL ON-STREET PARKING May 28, 2026 Clark County Land Use Oslund Acres Subdivision CVTV
50:38 document
Land Use Hearing - May 28, 2026 Webinar Info
Viewing Joe Kinsman's shared content
Proposed Plan
OSLUND ACRES SUBDIVISION
ENGINEERING & DESIGN
CIVIL ENGINEERING - LAND PLANNING - WATER RESOURCES - SURVEYING - LANDSCAPE ARCHITECTURE
PROPERTY
OWNERS/APPLICANT: JEFFREY C. KENDALL & JULIE A. KENDALL
ADDRESS: 1109 SE 147TH AVE., VANCOUVER, WA 98683
PHONE: 360-608-8980
PROPERTY DESCRIPTION:
A PARCEL OF LAND LOCATED IN THE SOUTH HALF OF SECTION 12, TOWNSHIP 2 NORTH, RANGE 2 EAST OF THE WILLAMETTE MERIDIAN, CLARK COUNTY, WASHINGTON. PARCEL NUMBER: 121430000 DEED REFERENCE: INSTRUMENT NO. 5448378 TOTAL AREA: ±13.04 ACRES
LOCATION: THE SUBJECT PROPERTY IS LOCATED ON THE SOUTH SIDE OF NE HOTH STREET, APPROXIMATELY 1200 FEET WEST OF NE 77TH AVE., WITHIN THE URBAN GROWTH AREA OF THE CITY OF VANCOUVER, CLARK COUNTY, WASHINGTON.
ZONING: R-12 RESIDENTIAL (CITY OF VANCOUVER)
WATER: CITY OF VANCOUVER (EXISTING 12" MAIN ON NE HOTH STREET)
SEWER: CLARK REGIONAL WASTEWATER DISTRICT (EXISTING 10" MAIN ON NE HOTH STREET)
STORMWATER: SHALL BE MANAGED PER CITY OF VANCOUVER STORMWATER STANDARDS.
UTILITIES: POTENTIAL UNDERGROUND UTILITIES INCLUDING POWER, PHONE, AND CABLE TV.
FIRE: CITY OF VANCOUVER FIRE DEPARTMENT
SCHOOL: VANCOUVER PUBLIC SCHOOLS
SURVEYOR: A&D ENGINEERING & DESIGN INC.
CRITICAL AREAS NOTES:
CRITICAL AREAS REPORT DATED FEBRUARY 25, 2021, PREPARED BY S&W CONSULTING. NO CRITICAL AREAS, AS DEFINED BY VANCOUVER MUNICIPAL CODE 20.700.040, ARE LOCATED WITHIN THE SUBJECT PARCEL, INCLUDING WETLANDS, FISH AND WILDLIFE HABITAT CONSERVATION AREAS, FREQUENTLY FLOODED AREAS, GEOLOGICALLY HAZARDOUS AREAS, AND CRITICAL AQUIFER RECHARGE AREAS.
PROPOSED: 87 SINGLE-FAMILY RESIDENTIAL LOTS
DENSITY: 6.67 UNITS PER ACRE
AVE. LOT AREA: ±6,000 SF
PREPARED FOR:
PREPARED BY: A&D ENGINEERING & DESIGN INC.
PROJECT NAME: OSLUND ACRES SUBDIVISION
LOCATION: VANCOUVER, WA
PROJECT NUMBER: 20210007
DATE: 03/24/2021
SHEET NO: 1 OF 1
WASHINGTON
PRELIMINARY SITE PLAN
OSLUND ACRES SUBDIVISION
CLARK COUNTY
PRELIMINARY
REVISIONS
EXISTING ACCESS EASEMENT
EXISTING PUBLIC STREET DEDICATION
NE HOTH STREET
LANDSCAPE LEGEND
RESIDENTIAL OPEN SPACE
BEST PARKING CALCULATION
87 SF/LOTS @ 2 SPACES/LOT
TOTAL SPACES: 174
REQUIRED: 174
PROVIDED: 174
TYPICAL OFF-STREET PARKING
Lot Numbers: 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20, 21, 22, 23, 24, 25, 26, 27, 28, 29, 30, 31, 32, 33, 34, 35, 36, 37, 38, 39, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 50, 51, 52, 53, 54, 55, 56, 57, 58, 59, 60, 61, 62, 63, 64, 65, 66, 67, 68, 69, 70, 71, 72, 73, 74, 75, 76, 77, 78, 79, 80, 81, 82, 83, 84, 85, 86, 87
May 28, 2026
Clark County Land Use
Oslund Acres Subdivision
CVTV
51:27 document
Proposed Plan
OSLUND ACRES SUBDIVISION
ENGINEERING & DESIGN
CIVIL ENGINEERING LAND PLANNING
SURVEYING & GEOSPATIAL
LANDSCAPE ARCHITECTURE
PRELIMINARY
PRELIMINARY SITE PLAN
OSLUND ACRES SUBDIVISION
WASHINGTON
CLARK COUNTY
PRELIMINARY
REVISIONS
LANDSCAPE LEGEND
DATE SCALE
2023 1"=80.0'
May 28, 2026
Clark County Land Use
Oslund Acres Subdivision
CVTV
52:16 document
Proposed Plan
OSLUND ACRES SUBDIVISION
ENGINEERING & DESIGN
PRELIMINARY
OSLUND ACRES
SUBDIVISION
CLARK COUNTY
WASHINGTON
PRELIMINARY
REVISIONS
May 28, 2026
Clark County Land Use
Oslund Acres Subdivision
CVTV
53:05 document
OSLUND ACRES SUBDIVISION
Proposed Plan
S A A
ENGINEERING
& DESIGN
CIVIL ENGINEERS - LAND PLANNERS
SURVEYORS & WETLAND SCIENTISTS
LANDSCAPE ARCHITECTURE
2000 BROADWAY
VANCOUVER, WA 98663
(360)694-8507 FAX (360)694-8524
www.saaeng.com
REGISTERED PROFESSIONAL ENGINEER
WASHINGTON STATE OF WASHINGTON
PROPERTY
APPLICANT
TAX PARCEL NUMBERS
PROPERTY OWNER
ASSESSOR
ADDRESS
LEGAL DESCRIPTION
SIZE OF SITE
ZONING
COMP PLAN
TOTAL DWELLING UNITS
NET DENSITY
GROSS DENSITY
OPEN SPACE REQUIRED
PROPOSED
UTILITY PROVIDERS
WATER
SANITARY SEWER
POWER
GAS
CABLE
STORM
FIRE
SCHOOL
DISTRICT
EXISTING PROPERTY LINE
NE 164TH STREET
Lots 1 through 94
WASHINGTON
PRELIMINARY SITE PLAN
OSLUND ACRES
SUBDIVISION
PRELIMINARY
REVISIONS
CLARK COUNTY
LANDSCAPE LEGEND
NO PARKING CALCULATION
EXISTING ZONING
LDR (PLANNED)
EXISTING USE
SITE AREA
OPEN SPACE
COMMON AREA
May 28, 2026
Clark County Land Use
Oslund Acres Subdivision
CVTV
53:54 document
Land Use Hearing - May 28, 2026 Webinar Info
01:36:40 Layout
Shared Timer
Unlocked Sound on Overtime off
Scott Taylor
David Jardin (Clark County)
Richard Daviau
Timer
08:40
Viewing Joe Kinsman's shared content
100%
Timer 2
0
01:41
Proposed Plan
+ 1m
+ 5m
+ 10m
+ Add timer
OSLUND ACRES SUBDIVISION
ENGINEERING
& DESIGN
CIVIL ENGINEERING LAND PLANNING
STRUCTURAL ENGINEERING
LANDSCAPE ARCHITECTURE
PROPERTY
APPLICANT & PROPERTY ADDRESS
CONTACT: RYAN SCHOMMER
PHONE: 360-608-4688
EMAIL: RYAN@SSENGINEERING.COM
ADDRESS: 1400 BROADWAY ST, STE B VANCOUVER, WA 98663
OWNER
CONTACT: RYAN SCHOMMER
PHONE: 360-608-4688
EMAIL: RYAN@SSENGINEERING.COM
ADDRESS: 1400 BROADWAY ST, STE B VANCOUVER, WA 98663
GENERAL NOTES
1. ALL LOTS ARE SERVICED BY PUBLIC WATER AND SANITARY SEWER.
2. ALL LOTS ARE TO BE SERVICED BY CLARK PUD ELECTRIC POWER.
3. THIS PROJECT IS SUBJECT TO THE CLARK COUNTY CRITICAL AQUIFER RECHARGE AREA REGULATIONS, SECTIONS 40.240.310 AND 40.240.320.
4. ALL LOTS ARE TO BE SERVICED BY CLARK COUNTY PUBLIC STORMWATER SYSTEM.
5. THIS PROJECT WILL BE REVIEWED UNDER CLARK COUNTY DEVELOPMENT CODE TITLE 40.
6. THE PROPERTY IS CURRENTLY ZONED R-1-6.
7. MINIMUM LOT SIZE FOR R1-6 ZONE IS 6,000 SF.
8. THE SITE IS LOCATED IN SECTION 29, TOWNSHIP 3N, RANGE 2E, W.M.
9. THE PROPERTY IS NOT LOCATED IN A FLOOD ZONE PER FEMA MAP NUMBER 53011C0210E.
10. MINIMUM SETBACKS FOR R-1-6 ZONE: FRONT: 20', SIDE: 5', REAR: 5'.
11. ALL BUILDING PERMITS SHALL BE OBTAINED PRIOR TO CONSTRUCTION.
12. A COPY OF THE APPROVED SITE PLAN AND GRADING PLAN MUST BE KEPT ON SITE AT ALL TIMES.
13. THE NUMBER OF PARKING SPACES REQUIRED FOR THIS PROJECT IS 2 SPACES PER LOT.
14. THIS PLAN IS SUBJECT TO ALL APPLICABLE CITY, COUNTY, STATE, AND FEDERAL REGULATIONS.
15. ALL UTILITY SERVICES ARE TO BE UNDERGROUNDED.
16. EXISTING TOPOGRAPHY AND FEATURES TO BE FIELD VERIFIED BY THE CONTRACTOR PRIOR TO CONSTRUCTION.
17. ALL TREES NOT DESIGNATED FOR REMOVAL ON THIS PLAN ARE TO REMAIN.
18. THE APPLICANT IS RESPONSIBLE FOR ALL UTILITY CONNECTION FEES.
19. THIS PROPERTY IS LOCATED WITHIN THE FIRE PROTECTION DISTRICT #6.
20. THE OSLUND ACRES SUBDIVISION IS LOCATED IN THE CITY OF VANCOUVER.
PROPOSED
TOTAL LOTS: 90
LOT SIZE (AVG): 5,200 SF
AVG LOT DEPTH: 100 FT
MIN LOT WIDTH: 50 FT
AVG OPEN SPACE: 10,000 SF
TOTAL SITE AREA: 10 ACRES
PARCEL #: 123456789
DATE: 05/28/2026
DRAWN BY: R.S.
CHECKED BY: J.K.
SCALE: 1" = 50'
SHEET 1 OF 1
PRELIMINARY SITE PLAN
OSLUND ACRES
SUBDIVISION
WASHINGTON
CLARK COUNTY
PRELIMINARY
REVISIONS
R-1-6
EAST-WEST STREET
THE NORTH STREET
NW 57TH AVENUE
NW 56TH AVENUE
NW 55TH AVENUE
LANDSCAPE LEGEND
PARKING CALCULATION
90 PROPOSED LOTS X 2 SPACES / LOT = 180 REQUIRED SPACES
180 PROPOSED SPACES
180 REQUIRED SPACES
OSLUND ACRES SUBDIVISION
2413
PRP18-00055
May 28, 2026
Clark County Land Use
Oslund Acres Subdivision
N
Unmute Raise
CVTV
Shared Timer Participants Chat
54:43 document
OSLUND ACRES SUBDIVISION
Proposed Plan
ENGINEERING
& DESIGN
CIVIL ENGINEERING • LAND PLANNING
LANDSCAPE ARCHITECTURE
800 BROADWAY
SUITE 165
VANCOUVER, WA 98660
PRELIMINARY
WASHINGTON
OSLUND ACRES
SUBDIVISION
PRELIMINARY SITE PLAN
CLARK COUNTY
REVISIONS
DESCRIPTION
DATE
APPLICANT/OWNER
PROPERTY ADDRESS
ASSESSOR PARCEL NUMBERS
TOTAL ACRES
AVERAGE LOT AREA
SIZE
COMPREHENSIVE PLAN DESIGNATION
ZONING DESIGNATION
OVERLAY DISTRICTS
PROPOSAL
PROJECT NAME
PROPOSED USE
LOTS
BUILDING HEIGHT
SETBACKS
FRONT
SIDE
REAR
PROPOSED PARKING
OPEN SPACE
EXISTING SITE CONDITIONS
SURFACE WATER MANAGEMENT
UTILITIES
WATER
SEWER
STORM
POWER
CABLE
GAS
DEVELOPMENT STANDARDS
LANDSCAPE LEGEND
PARKING CALCULATIONS
PARKING LOTS 1-140 X 1/40 = 4C
MINIMUM LOTS = 4C
TYPICAL ON-STREET PARKING
2023
PREL.D
REVISIONS
May 28, 2026
Clark County Land Use
Oslund Acres Subdivision
CVTV
55:32 document
Land Use Hearing - May 28, 2026 Webinar Info Speaking: Lori & Christy Davis Scott Taylor David Jardin (Clark County) Richard Daviau Viewing Joe Kinsman's shared content 100% + OSLUND ACRES SUBDIVISION Proposed Plan ENGINEERING & DESIGN CIVIL ENGINEERING LAND PLANNING SURVEYING & GEOSPATIAL LANDSCAPE ARCHITECTURE 2030 BROADWAY STREET SUITE 100 VANCOUVER, WASHINGTON 98663 PHONE: 360-696-9811 EMAIL: INFO@EANDDS.COM PRELIMINARY WASHINGTON PRELIMINARY SITE PLAN OSLUND ACRES SUBDIVISION CLARK COUNTY PRELIMINARY REVISIONS NO DESCRIPTION DATE EXISTING PUBLIC ACCESS EASEMENT FOR ACCESS AND UTILITIES AF-900 PRIVATE ACCESS EASEMENT PRIVATE UTILITY EASEMENT NE FORD ROAD PROPOSED RIGHT OF WAY LANDSCAPE LEGEND SITE PARKING CALCULATION 100 PROPOSED LOTS x 2 = 200 NE 125TH AVENUE 100 99 98 97 96 95 94 93 92 91 90 89 88 87 86 85 84 83 82 81 80 79 78 77 76 75 74 73 72 71 70 69 68 67 66 65 64 63 62 61 60 59 58 57 56 55 54 53 52 51 50 49 48 47 46 45 44 43 42 41 40 39 38 37 36 35 34 33 32 31 30 29 28 27 26 25 24 23 22 21 20 19 18 17 16 15 14 13 12 11 10 9 8 7 6 5 4 3 2 1 May 28, 2026 Clark County Land Use Oslund Acres Subdivision Unmute Raise Shared Timer Participants Chat CVTV_ 01:38:18 Layout Shared Timer Unlocked Sound on Overtime off Timer 08 : 40 0 Timer 2 02 : 28 + 1m + 5m + 10m + Add timer
56:21 document
Land Use Hearing - May 28, 2026
Webinar Info
Speaking: Lori & Christy Davis
OSLUND ACRES SUBDIVISION
Proposed Plan
ENGINEERING & DESIGN
CIVIL ENGINEERING - LAND PLANNING
SURVEYING - WATER QUALITY
LANDSCAPE ARCHITECTURE
APPLICANT:
OSLUND ACRES SUBDIVISION
10901 NE 95TH STREET
VANCOUVER, WA 98662
OWNER:
OSLUND ACRES SUBDIVISION
10901 NE 95TH STREET
VANCOUVER, WA 98662
PROJECT ADDRESS:
9505 NE 95TH STREET
VANCOUVER, WA 98662
PARCEL #:
TOTAL AREA:
NO. OF PROPOSED LOTS:
SEWER:
WATER:
STORM WATER:
ACCESS:
ZONING:
OVERLAYS:
SETBACKS:
COMMERCIAL:
RESIDENTIAL:
FLOOR AREA:
BUILDING HEIGHT:
GARAGE SETBACK:
MAX IMPERVIOUS:
TOTAL NUMBER OF TREES:
LANDSCAPE:
EASEMENTS:
SITE LIGHTING:
FENCES:
SIGNAGE:
GENERAL NOTES
A. GENERAL
B. LEGAL DESCRIPTION
C. UTILITIES
D. EASEMENTS
E. FIRE PROTECTION
F. GEOTECHNICAL
G. SURVEY
H. WETLANDS
I. PARKING
J. LANDSCAPE
K. TREE PRESERVATION
PRELIMINARY
PRELIMINARY
WASHINGTON
OSLUND ACRES
SUBDIVISION
CLARK COUNTY
REVISIONS
NE 95TH PLACE
NE 96TH AVENUE
LANDSCAPE LEGEND
OPEN SPACE CALCULATION
PUBLIC PARKING CALCULATION
17 DWELLING UNITS = 17 SPACE
PROPOSED LOTS = 40
TYPICAL ON-STREET PARKING
NE 95TH STREET
May 28, 2026
Clark County Land Use
Oslund Acres Subdivision
CVTV
57:10 document
Land Use Hearing - May 28, 2026 Webinar Info Viewing Joe Kinsman's shared content Proposed Plan OSLUND ACRES SUBDIVISION S ENGINEERING & DESIGN CIVIL ENGINEERING LAND PLANNING SURVEYING & MAPPING LANDSCAPE ARCHITECTURE PRELIMINARY PRELIMINARY SITE PLAN OSLUND ACRES SUBDIVISION CLARK COUNTY WASHINGTON REVISIONS OSLUND ACRES SUBDIVISION FACTS & PROPERTY ADDRESS APPLICANT: RICHARD & CINDY DAVIAU 20002 NE 165TH STREET BRUSH PRAIRIE, WA 98606 LEGAL DESCRIPTION: TAX LOTS #1, #2, #3, #4 OF CLARK COUNTY ASSESSOR'S MAP #171630-000 ZONING: R-5 (RESIDENTIAL, 5 DU/ACRE) COMPREHENSIVE PLAN: RURAL RESIDENTIAL SITE AREA: 17.5 ACRES (TOTAL) DWELLING UNITS: 87 LOTS DENSITY: 4.97 DU/ACRE OPEN SPACE: 3.42 ACRES (MIN. 20%) STORMWATER: TO BE DESIGNED TO MEET CLARK COUNTY STANDARDS. WATER: CITY OF VANCOUVER SEWER: CITY OF VANCOUVER SCHOOLS: BATTLE GROUND SCHOOL DISTRICT FIRE: CLARK COUNTY FIRE DISTRICT 3 EXISTING ACCESS: NE 164TH STREET PROPOSED ACCESS: NE 165TH STREET & NE HORTON RD PROJECT: PROPOSED PLAT OF 87 LOTS, 2 OPEN SPACE TRACTS DISPOSAL: STORMWATER: TO BE TREATED AND DISPOSED ON-SITE VIA BIORETENTION FACILITIES SOLID WASTE: CITY OF VANCOUVER SOLID WASTE SEPTIC: NOT APPLICABLE WELLS: NOT APPLICABLE AVERAGE LOT SIZE: 7,500 SF MINIMUM LOT SIZE: 6,000 SF MAXIMUM LOT SIZE: 11,000 SF SITE DATA: 87 SINGLE FAMILY RESIDENTIAL LOTS 2 OPEN SPACE TRACTS 2 ACCESS TRACTS 2 STORMWATER TRACTS TOTAL AREA: 17.5 ACRES BIKE PARKING CALCULATION BIKE PARKING: 87 DWELLING UNITS X 1.0 SPACE/DU = 87 SPACES REQUIRED: 87 SPACES PROVIDED: 87 SPACES PARKING CALCULATION MINIMUM 2 SPACES / DWELLING UNIT 87 DWELLING UNITS X 2 SPACES/DU = 174 SPACES REQUIRED: 174 SPACES PROVIDED: 174 SPACES NE 164TH STREET NE HORTON RD NE 165TH STREET EXISTING APPROXIMATE FLOODPLAIN ON-SITE May 28, 2026 Clark County Land Use Oslund Acres Subdivision CVTV
57:59 document
Land Use Hearing - May 28, 2026 Webinar Info Speaking: Lori & Christy Davis Scott Taylor David Jardin (Clark County) Richard Daviau Viewing Joe Kinsman's shared content 100% + OSLUND ACRES SUBDIVISION ENGINEERING & DESIGN CIVIL ENGINEERING - LAND PLANNING SURVEYING - WATER RESOURCES LANDSCAPE ARCHITECTURE Proposed Plan PRELIMINARY PRELIMINARY SITE PLAN WASHINGTON OSLUND ACRES SUBDIVISION CLARK COUNTY PRELIMINARY REVISIONS LANDSCAPE LEGEND PARKING CALCULATION REQUIRED PROVIDED MINIMUM LOTS 40 NO MINOR LOTS < 40 May 28, 2026 Clark County Land Use Oslund Acres Subdivision CVTV
58:48 document
Land Use Hearing - May 28, 2026
Proposed Plan
OSLUND ACRES SUBDIVISION
ENGINEERING & DESIGN
PROPERTY
PROFESSIONAL ENGINEER
WASHINGTON
OSLUND ACRES SUBDIVISION
CLARK COUNTY
PRELIMINARY SITE PLAN
GENERAL NOTES:
THIS PLAT CONTAINS RESIDENTIAL LOTS, OPEN SPACE TRACTS, AND...
ALL RESIDENTIAL LOTS ARE PROVIDED FOR SINGLE FAMILY DWELLINGS
PROPERTY INFORMATION
TAX PARCEL NUMBER:
PROPERTY ADDRESS:
CURRENT OWNER:
APPLICANT:
ENGINEER:
SITE AREA:
NUMBER OF LOTS:
NUMBER OF OPEN SPACE TRACTS:
ZONING:
FRONTAGE:
AVERAGE LOT AREA:
SITE COVERAGE:
IMPERVIOUS AREA:
OPEN SPACE REQUIRED:
OPEN SPACE PROVIDED:
This property is located within an area identified as having archaeological...
All lots shall be served by public water, sanitary sewer, and storm sewer facilities.
THIS PROJECT IS WITHIN THE URBAN GROWTH AREA OF THE CITY OF RIDGEFIELD
PRELIMINARY
REVISIONS
EXISTING DRIVEWAY
NE HERFORD RD
NE 11TH ST
NE 10TH STREET
OLD NORTH STREET
1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20, 21, 22, 23, 24, 25, 26, 27, 28, 29, 30, 31, 32, 33, 34, 35, 36, 37, 38, 39, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 50, 51, 52, 53, 54, 55, 56, 57, 58, 59, 60, 61, 62, 63, 64, 65, 66, 67, 68, 70, 71, 72
LANDSCAPE LEGEND
BIKE PARKING CALCULATION
PROPOSED BIKES
NO MINIMUM LOTS 40 AC
TYPICAL ON-STREET PARKING
SCALE: 1" = 100'
May 28, 2026
Clark County Land Use
Oslund Acres Subdivision
CVTV
59:37 document
Land Use Hearing - May 28, 2026
Webinar Info
Speaking: Lori & Christy Davis
Scott Taylor
David Jardin (Clark County)
Richard Daviau
01:42:23
Layout
Shared Timer
Unlocked
Sound on
Overtime off
Timer
08:40
Timer 2
03:00
+ 1m
+ 5m
+ 10m
+ Add timer
Viewing Joe Kinsman's shared content
100%
OSLUND ACRES SUBDIVISION
A SUBDIVISION OF LOT 2 OF THAT CERTAIN (unreadable)
BEING IN THE NORTHEAST QUARTER OF SECTION 30, TOWNSHIP 3 NORTH, RANGE 2 EAST, WILLAMETTE MERIDIAN, CLARK COUNTY, WASHINGTON
PREPARED FOR
CVTV ENGINEERING
103 21ST STREET
WASHOUGAL, WA 98671
360-635-7798
PREPARED BY:
S & A ENGINEERING
& DESIGN
CIVIL ENGINEERING LAND PLANNING
STORM WATER DESIGN
WATER & SEWER DESIGN
GRADING & EROSION CONTROL
LANDSCAPE ARCHITECTURE
103 21ST STREET
WASHOUGAL, WA 98671
(360) 635-7798
PRELIMINARY
Proposed Plan
EXISTING (unreadable)
APPROXIMATE LOCATION
OF (unreadable)
PARCEL PROPERTY ADDRESS
LOT NO.
STREET ADDRESS
ZONING
OSWALD ST.
PERRY ST.
CLARK COUNTY
WASHINGTON
PRELIMINARY
REVISIONS
OSLUND ACRES SUBDIVISION
PRELIMINARY SITE PLAN
May 28, 2026
Clark County Land Use
Oslund Acres Subdivision
CVTV
1:00:26 document
Proposed Plan
OSLUND ACRES SUBDIVISION
ENGINEERING & DESIGN
CIVIL ENGINEERING LAND PLANNING
ENVIRONMENTAL CONSULTING
LANDSCAPE ARCHITECTURE
PRELIMINARY (stamped)
PRELIMINARY SITE PLAN
WASHINGTON
CLARK COUNTY
OSLUND ACRES SUBDIVISION (vertical)
PRELIMINARY
REVISIONS
LANDSCAPE LEGEND
EXISTING
NE 119TH STREET
PROPERTY ADDRESS
SITE AREA
ZONING
STREET FRONTAGE
STORMWATER
PARKING CALCULATION
BUILDING HEIGHT
UTILITIES
DISPOSAL
EXISTING TREES
FIRE PROTECTION
SITE ACCESS
EROSION CONTROL
GEOTECHNICAL
EXISTING WETLANDS
TRAFFIC IMPACT ANALYSIS
SCHOOL DISTRICT
PROPERTY TAX
WETLAND MITIGATION
BUFFERING
LOT AREA
DWELLING UNITS
COVERAGE
OPEN SPACE
TOTAL PARKING
AVG LOT AREA
(Lot numbers visible from 1-75)
2457
PAGE-3
May 28, 2026
Clark County Land Use
Oslund Acres Subdivision
CVTV
1:01:15 document
Land Use Hearing - May 28, 2026
Webinar Info
Proposed Plan
OSLUND ACRES SUBDIVISION
ENGINEERING & DESIGN
A & D SURVEYING
CIVIL ENGINEERING - LAND PLANNING
SURVEYING - WATER RESOURCES
LANDSCAPE ARCHITECTURE
PHONE: (360) 887-8888
FAX: (360) 887-8880
PROJECT: OSLUND ACRES SUBDIVISION
LOCATION: CLARKE COUNTY, WASHINGTON
TAX PARCEL NO: 160351000
APPLICANT: OSFUND FAMILY, LLC
SURVEYOR: A & D SURVEYING
OWNER: OSFUND FAMILY, LLC
DATE: 06/20/2026
REVISIONS
NO. DATE DESCRIPTION
1. 06/20/26 PRELIMINARY
GENERAL NOTES:
1. THIS PRELIMINARY PLAT IS SUBJECT TO FINAL REVIEW AND APPROVAL BY CLARK COUNTY.
2. ALL DIMENSIONS ARE IN FEET AND DECIMALS THEREOF, UNLESS OTHERWISE NOTED.
3. THE BASIS OF BEARINGS IS...
4. PROPERTY CORNERS ARE TO BE MARKED WITH...
5. THE PROPERTY IS CURRENTLY ZONED RESIDENTIAL...
6. PUBLIC UTILITIES ARE AVAILABLE TO THE SITE, INCLUDING WATER, SEWER, AND POWER.
7. ALL LOTS ARE SERVED BY PUBLIC SANITARY SEWER AND WATER.
8. ALL ROADS ARE TO BE CONSTRUCTED TO CLARK COUNTY STANDARDS.
9. ALL STREET LIGHTING TO BE INSTALLED IN ACCORDANCE WITH CLARK COUNTY STANDARDS.
10. ALL LANDSCAPING TO BE INSTALLED IN ACCORDANCE WITH APPROVED LANDSCAPE PLANS.
11. ALL UTILITY EASEMENTS ARE PRIVATE AND ARE TO BE MAINTAINED BY THE HOMEOWNERS ASSOCIATION.
12. SIDEWALK TO BE 5 FT WIDE ALONG BOTH SIDES OF ALL STREETS.
13. ALL SETBACKS ARE TO BE IN ACCORDANCE WITH CLARK COUNTY CODE.
14. ALL RESIDENTIAL LOTS ARE SINGLE FAMILY RESIDENTIAL.
15. ALL PARKING TO BE IN ACCORDANCE WITH CLARK COUNTY CODE.
16. ALL FENCING TO BE INSTALLED BY THE DEVELOPER ALONG PERIMETER...
LANDSCAPE LEGEND
TOTAL PARCEL CALCULATION
TOTAL ACREAGE: 18.5 ACRES
TOTAL NUMBER OF LOTS: 75 LOTS
NET USABLE LOT AREA: 9.3 ACRES
AVERAGE LOT SIZE: 5400 SQ FT
PERCENT IMPERVIOUS: 45%
TOTAL NUMBER OF OPEN SPACE LOTS: 3 LOTS
TOTAL NUMBER OF RESIDENTIAL LOTS: 72 LOTS
PRELIMINARY
PRELIMINARY SITE PLAN
OSLUND ACRES
SUBDIVISION
WASHINGTON
CLARK COUNTY
May 28, 2026
Clark County Land Use
Oslund Acres Subdivision
CVTV
1:02:04 document
Proposed Plan
OSLUND ACRES SUBDIVISION
ENGINEERING & DESIGN
CIVIL ENGINEERING - LAND PLANNING - SITE DEVELOPMENT - HYDROLOGY - LANDSCAPE ARCHITECTURE
S&S
PRELIMINARY
WASHINGTON
CLARK COUNTY
PRELIMINARY
REVISIONS
PRELIMINARY SHORT PLAT PLAN
Lot numbers: 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20, 21, 22, 23, 24, 25, 26, 27, 28, 29, 30, 31, 32, 33, 34, 35, 36, 37, 38, 39, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 50, 51, 52, 53, 54, 55, 56, 57, 58, 59, 60, 61, 62, 63, 64, 65, 66, 67, 68, 69, 70, 71, 72, 73, 74, 75, 76, 77, 78, 79, 80, 81, 82, 83, 84, 85, 86, 87
EXISTING WETLAND APPROXIMATE LOCATION
NE 164TH STREET
NE 166TH AVENUE
NE 166TH PLACE
PROJECT DESCRIPTION: THE PROJECT CONSISTS OF THE SUBDIVISION OF ONE EXISTING 4.90 ACRE PARCEL INTO 87 SINGLE-FAMILY RESIDENTIAL LOTS...
OWNER/APPLICANT: DAVID S. OSALUND
ENGINEER/SURVEYOR: S&S ENGINEERING & DESIGN
ADDRESS: 620 E. 1ST CIRCLE STE...
CODE COMPLIANCE WITH ZONING AND USE: THE PROPOSED DEVELOPMENT COMPLIES WITH ALL APPLICABLE CLARK COUNTY CODE TITLES...
SITE DATA:
SITE AREA: 4.90 AC (NET)
NO. OF PROPOSED LOTS: 87
MINIMUM LOT AREA: 3,000 SF
AVERAGE LOT AREA: 4,000 SF
OPEN SPACE: 0.88 AC
PARKING CALCULATION:
REQUIRED PER DWELLING UNIT: 2 (GARAGE OR CARPORT)
PROPOSED PER DWELLING UNIT: 2 (GARAGE OR CARPORT) + 2 (DRIVEWAY)
PARKING: 174 SPACES REQUIRED
TOTAL PROPOSED: 174 SPACES PROVIDED
EASEMENT DEDICATION
UTILITY EASEMENT
STORM DRAINAGE EASEMENT
ACCESS AND UTILITY EASEMENT
DISPOSAL:
SOLID WASTE
STORMWATER
TYPICAL ON-STREET PARKING
PARKING CALCULATION
REQUIRED: 2 PER DWELLING UNIT FOR 87 LOTS = 174 SPACES
PROPOSED: 2 PER DWELLING UNIT FOR 87 LOTS + 2 PER DRIVEWAY = 174 SPACES
LANDSCAPE LEGEND
May 28, 2026
Clark County Land Use
Oslund Acres Subdivision
CVTV
1:02:53 document
May 28, 2026
Clark County Land Use
Oslund Acres Subdivision

OSLUND ACRES SUBDIVISION
GENERAL NOTES:
APPLICANT:
CONTACT:
EXISTING SITE DATA:
PROJECT LOCATION:
SITE AREA:
APPLICABLE ZONING DISTRICT:
PROPOSED USE:
PROPOSED LOTS &...
PROPOSED OPEN SPACE:
PARCEL DESCRIPTION:
CRITICAL AREAS NOTES:
FLOODPLAIN:
WETLANDS:
STREAM:
SEISMIC:
GEOLOGIC HAZARDS:
ARCHEOLOGICAL:

ENGINEERING
& DESIGN
CIVIL ENGINEERING • LAND PLANNING
SURVEYING • WATER RESOURCES
LANDSCAPE ARCHITECTURE

2000 NE BROADWAY STREET
VANCOUVER, WA 98663
P (360) 546-2771
F (360) 546-2775
www.enadesign.com

PRELIMINARY

Proposed Plan

PRELIMINARY SITE PLAN
OSLUND ACRES
SUBDIVISION
WASHINGTON
CLARK COUNTY

REVISIONS
DATE
DESCRIPTION
SHEET

THE NORTH STREET

LANDSCAPE LEGEND
1:03:42 document
Proposed Plan OSLUND ACRES SUBDIVISION ENGINEERING & DESIGN CIVIL ENGINEERING LAND PLANNING SURVEYING & MAPPING LANDSCAPE ARCHITECTURE PR PRELIMINARY PRELIMINARY SITE PLAN OSLUND ACRES SUBDIVISION WASHINGTON CLARK COUNTY REVISIONS THE NORTH STREET LANDSCAPE LEGEND REOURED PARKING CALCULATION EXISTING TREES FOR REMOVAL Lot numbers 1 through 91 May 28, 2026 Clark County Land Use Oslund Acres Subdivision CVTV
1:04:31 slide
Proposed Plan
OSLUND ACRES SUBDIVISION
ENGINEERING & DESIGN
PROPERTY ADDRESS
PROJECT NUMBER
ZONING
OVERLAY
WATER
SANITARY
STORMWATER
STREETS
FIRE
PARKING
SITE AREA
SITE COVERAGE
LANDSCAPING
LAND USE
DWELLING UNITS
NET LOT AREA
OSLUND ACRES SUBDIVISION
PRELIMINARY SITE PLAN
WASHINGTON
CLARK COUNTY
PRELIMINARY
REVISIONS
NE 188TH STREET
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88
EXISTING
CONDITION
LANDSCAPE LEGEND
BIKE PARKING CALCULATION
May 28, 2026
Clark County Land Use
Oslund Acres Subdivision
CVTV
1:05:20 document
Proposed Plan OSLUND ACRES SUBDIVISION S & A ENGINEERING & DESIGN CIVIL ENGINEERING LAND PLANNING SURVEYING PERMITTING LANDSCAPE ARCHITECTURE PRELIMINARY WASHINGTON CLARK COUNTY REVISIONS DATE OSLUND ACRES SUBDIVISION LANDSCAPE LEGEND May 28, 2026 Clark County Land Use Oslund Acres Subdivision
1:06:09 document
Land Use Hearing - May 28, 2026 Webinar Info Speaking: Alison Ward Scott Taylor David Jardin (Clark County) Richard Daviau Viewing Joe Kinsman's shared content 100% + OSLUND ACRES SUBDIVISION ENGINEERING & DESIGN Proposed Plan 90 WELLHORN SUBDIVISION CLARK COUNTY WASHINGTON PRELIMINARY REVISIONS 75 74 73 72 71 70 69 68 67 66 65 64 63 62 61 60 59 58 57 56 55 54 53 52 51 50 49 48 47 46 45 44 43 42 41 40 39 38 37 36 35 NE 9TH STREET 24 23 22 21 20 19 18 17 16 15 14 13 12 11 10 9 8 7 6 5 4 3 2 1 25 26 27 28 29 30 31 32 33 LANDSCAPE LEGEND BIKE PARKING CALCULATION TYPICAL ON-STREET PARKING APPLICANT: PROPERTY ADDRESS: TAX PARCEL ID: SITE AREA: ZONING: FUTURE LAND USE: COMP PLAN DESIGNATION: LOT COVERAGE: OPEN SPACE: TOTAL PARKING REQUIRED: REQUIRED PARKING: PROPOSED PARKING: BUILDING SETBACKS: FRONT: 20' SIDE: REAR: MAX BLDG HT: EXISTING DUPLEX: APARTMENT UNITS: 72 SF AVG 12' & 20' SIDE YARD 10' SIDE YARD 20' REAR YARD 01:48:55 Layout Shared Timer Unlocked Sound on Overtime off Timer 08 : 40 = Timer 2 00 : 57 + 1m + 5m + 10m + Add timer May 28, 2026 Clark County Land Use Oslund Acres Subdivision Unmute Raise CVTV Shared Timer Participants Chat
1:06:58 document
May 28, 2026
Clark County Land Use
Oslund Acres Subdivision
CVTV
Proposed Plan
OSLUND ACRES SUBDIVISION
ENGINEERING & DESIGN
CIVIL ENGINEERING - LAND PLANNING
SURVEYING - LANDSCAPE ARCHITECTURE
CLARK COUNTY
WASHINGTON
PRELIMINARY SITE PLAN
OSLUND ACRES SUBDIVISION
PRELIMINARY
REVISIONS
PRELIMINARY
EXISTING DWELLINGS TO REMAIN
PRIVATE ROAD C
PRIVATE ROAD A
PRIVATE ROAD B
THE NORTH STREET
1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20, 21, 22, 23, 24, 25, 26, 27, 28, 29, 30, 31, 32, 33, 34, 35, 36, 37, 38, 39, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 50, 51, 52, 53, 54, 55, 56, 57, 58, 59, 60, 61, 62, 63, 64, 65, 66, 67, 68, 69, 70, 71, 72, 73, 74, 75, 76, 77, 78, 79, 80, 81, 82, 83, 84, 85, 86, 87, 88, 89, 90, 91, 92, 93, 94, 95, 96, 97, 98, 99
1:07:47 document
Proposed Plan
OSLUND ACRES SUBDIVISION
ENGINEERING & LAND PLANNING
PRELIMINARY
REVISIONS
PRELIMINARY SITE PLAN
OSLUND ACRES SUBDIVISION
CLARK COUNTY
WASHINGTON
ENGINEERING & DESIGN
RECEIVED
APR 15 2024
PROJECT ADDRESS:
PROPERTY DESCRIPTION:
SECTION 20 T3N R3E WM
ASSESSOR'S PARCEL NUMBER:
SITE AREA:
PARKING CALCULATION
TOTAL DWELLING UNITS: 68
NET DENSITY
PRIVATE OPEN SPACE
PUBLIC OPEN SPACE
STORMWATER POND
LANDSCAPE AREA
UTILITY PARCELS
STREETS & ALLEYS
TOTAL
ALL DIMENSIONS ARE IN FEET
PROPERTY BOUNDARIES
PROPOSED STREET NAMES:
EXISTING CATCH BASIN TO REMAIN
39' WIDE
38' WIDE
15' WIDE
20' PUBLIC
WEST FRONT ST
THE NORTH STREET
LANDSCAPE LEGEND
LOTS 1-80 (numbers visible on individual lots)
PARKING CALCULATION
68 DWELLING LOTS x 40
TOTAL 2720
May 28, 2026
Clark County Land Use
Oslund Acres Subdivision
CVTV
1:09:25 document
Land Use Hearing - May 28, 2026
Webinar Info
Scott Taylor
David Jardin (Clark County)
Richard Daviau
Viewing Joe Kinsman's shared content
Proposed Plan
OSLUND ACRES SUBDIVISION
S & S ENGINEERING & SURVEY
CIVIL ENGINEERING LAND PLANNING
SURVEYING & MAPPING
LANDSCAPE ARCHITECTURE
OSLUND ACRES SUBDIVISION
WASHINGTON
CLARK COUNTY
PRELIMINARY
REVISIONS
OWNERS/APPLICANT
OSLUND DEVELOPMENT LLC
1775 N 170TH AVE
PORTLAND OR 97229
PHONE: (503) 935-4300
EMAIL: OSLUNDDEVELOPMENT@GMAIL.COM
ATTN: SCOTT OSLUND
PARCEL # 193214000
TAX PARCEL ACCOUNT #193214-000
PROPERTY ADDRESS
1775 N 170TH AVE
VANCOUVER WA 98686
LEGAL DESCRIPTION
NE 170TH AVE
NE 164TH STREET
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100
May 28, 2026
Clark County Land Use
Oslund Acres Subdivision
CVTV
Shared Timer
Timer 2
05:58
03:00
1:10:14 document
Land Use Hearing - May 28, 2026 Webinar Info
Scott Taylor
Daniel Kearns
David Jardin (Clark County)
Richard Daviau
Viewing Joe Kinsman's shared content
Proposed Plan
100%
OSLUND ACRES SUBDIVISION
ENGINEERING
& DESIGN
CIVIL ENGINEERING LAND PLANNING
SURVEYING WATER RESOURCES
GIS SERVICES
LANDSCAPE ARCHITECTURE
2608 NE 114TH AVENUE SUITE 2
VANCOUVER, WA 98686
PHONE: 360.254.6710 FAX: 360.254.6719
PRELIMINARY
WASHINGTON
CLARK COUNTY
OSLUND ACRES
SUBDIVISION
PRELIMINARY SITE PLAN
OSLUND ACRES
SUBDIVISION
SHEET 1 OF 1
TAX PARCEL NUMBERS:
151528-000
PROPERTY ADDRESS:
N 134TH ST
VANCOUVER, WA 98686
TOTAL SITE AREA:
1.48 ACRES
EXISTING ZONING:
R1-5
PROPOSED USE:
RESIDENTIAL
NUMBER OF DWELLING UNITS:
13
NUMBER OF LOTS:
13
PROPOSED DENSITY:
8.78 DU/AC
UTILITY PROVIDERS:
WATER: CLARK PUD
SANITARY: CLARK REGIONAL WASTEWATER
ELECTRIC: CLARK PUD
GAS: NW NATURAL
CABLE: COMCAST
PHONE: FRONTIER
PROPOSED SETBACKS:
FRONT: 10'
SIDE: 5'
REAR: 10'
PUBLIC STREETS: 20' (GARAGE)
PROPOSED LOT AREA:
5000 SF (MIN)
PROPOSED LOT WIDTH:
50' (MIN)
PROPOSED LOT DEPTH:
90' (MIN)
PRELIMINARY
REVISIONS
EXISTING
RESIDENCE
APPROXIMATE
5800 SF
N 134TH ST
20' MIN BUILDING SETBACK
10' UTILITY EASEMENT
88
87
86
85
84
83
82
81
80
79
78
65
66
67
68
69
70
71
72
73
74
75
76
77
64
63
62
61
60
59
58
57
56
55
54
53
52
51
50
49
48
47
46
45
44
43
42
41
40
39
38
37
36
35
34
33
32
31
30
29
28
27
26
25
13
12
11
10
9
8
7
6
5
4
3
2
1
THE NE 13TH STREET
OFF-STREET
PARKING
LANDSCAPE LEGEND
REQUIRED PARKING CALCULATION
SITE DATA
TYPICAL ON-STREET PARKING
May 28, 2026
Clark County Land Use
Oslund Acres Subdivision
CVTV
Shared Timer Participants Chat
1:11:03 document
Land Use Hearing - May 28, 2026
Webinar Info
Scott Taylor
David Jardin (Clark County)
Richard Daviau
Viewing Joe Kinsman's shared content
100% +
OSLUND ACRES SUBDIVISION
ENGINEERING
& DESIGN
Proposed Plan
CIVIL ENGINEERING - LAND PLANNING
SURVEYING - MAPPING
LANDSCAPE ARCHITECTURE
2020 BROADWAY
VANCOUVER WA 98663
200.000.0000
www.
PRELIMINARY
PROPERTY ADDRESS
EXISTING STORM
DRAINAGE SYSTEM
TO BE ABANDONED
BY-GFI
NE 89TH STREET
NE 80TH
PARKING CALCULATIONS
OSLUND ACRES
SUBDIVISION
PRELIMINARY SITE PLAN
WASHINGTON
CLARK COUNTY
PRELIMINARY
REVISIONS
1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 20, 21, 22, 23, 24, 25, 26, 27, 28, 29, 30, 31, 32, 33, 34, 35, 36, 37, 38, 39, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 50, 51, 52, 53, 54, 55, 56, 57, 58, 59, 60, 61, 62, 63, 64, 65, 66, 67, 68, 69, 70, 71, 72, 73, 74, 75, 76, 77, 78, 79, 80, 81, 82, 83, 84, 85, 86, 87, 88
SITE AREA
PARKING
COVERED
TOTAL REQUIRED
PROVIDED
REQUIRED
PROVIDED
PARKING CALCULATIONS
ONSITE PARKING
DEVELOPMENT SUMMARY
GROSS SITE AREA
NET SITE AREA
NUMBER OF LOTS
AVE LOT SIZE
OPEN SPACE
PUBLIC STREETS
DETENTION
LANDSCAPE
NEIGHBORHOOD STREET
SIDEWALK
LANDSCAPE LEGEND
RESERVED
LANDSCAPE
LANDSCAPE BUFFER
P.U.E.
DETENTION POND
TYPICAL ON-STREET PARKING
May 28, 2026
Clark County Land Use
Oslund Acres Subdivision
CVTV
1:11:52 document
Land Use Hearing - May 28, 2026
Webinar Info
Scott Taylor
David Jardin (Clark County)
Richard Daviau
Viewing Joe Kinsman's shared content
- 100% +
OSLUND ACRES SUBDIVISION
ENGINEERING
& DESIGN
Proposed Plan
CIVIL ENGINEERING - LAND PLANNING
ENVIRONMENTAL CONSULTING
LANDSCAPE ARCHITECTURE
1800 N.W. 167TH PL, SUITE A
BEAVERTON, OREGON 97006
PHONE: (503) 645-0909 FAX: (503) 645-8125
PRELIMINARY
LOTS: 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 27, 28, 29, 30, 31, 32, 33, 34, 35, 36, 37, 38, 39, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 50, 51, 52, 53, 54, 55, 56, 57, 58, 59, 60, 61, 62, 63, 64, 65, 66, 67, 68, 69, 70, 71, 72, 73, 74, 75, 76, 77, 78, 79, 80, 81, 82, 83, 84, 85, 86, 87, 88, 89, 90, 91, 92, 93, 94, 95, 96, 97, 98
PARCEL HISTORY & ADDRESS
ASSESSOR'S MAP REFERENCE
TOTAL SITE AREA: ±6.48 AC.
NUMBER OF LOTS: 98
TOTAL RESIDENTIAL DWELLING UNITS: 98
AVERAGE LOT SIZE: ±6,480 SF
TOTAL OPEN SPACE: ±0.32 AC. (5.0%)
STREET TREES TO BE PLANTED: 104
EXISTING STREET TREES TO REMAIN: 40
STREET NAME
DRAINAGE
UTILITY PROVIDERS
FENCE
SIDEWALK
PRELIMINARY
REVISIONS
WASHINGTON
OSLUND ACRES
SUBDIVISION
CLARK COUNTY
PRELIMINARY SITE PLAN
ON-SITE PARKING CALCULATION
REQUIRED: 2 PER DWELLING UNIT. 2 X 98 = 196 SPACES
PROVIDED: 2 PER DWELLING UNIT. 2 X 98 = 196 SPACES
PLUS 24 VISITOR LOTS = 220
SIDEWALK WIDTH: 5 FEET
TYPICAL STREET SECTION
EXISTING DRIVEWAY
THE NORTH STREET
May 28, 2026
Clark County Land Use
Oslund Acres Subdivision
CVTV
1:12:41 document
Land Use Hearing - May 28, 2026 Webinar Info 01:55:27 Layout Shared Timer Unlocked Sound on Overtime off Timer 02 : 42 + 1m + 5m + 10m Timer 2 03 : 00 + Add timer Viewing Joe Kinsman's shared content Scott Taylor David Jardin (Clark County) Richard Daviau 100% OSLUND ACRES SUBDIVISION ENGINEERING & DESIGN CIVIL ENGINEERING - LAND PLANNING - SURVEYING - MAPPING - LANDSCAPE ARCHITECTURE 300 BROADWAY SUITE 200 VANCOUVER, WA 98660 PH. 360-699-2700 FAX 360-695-9430 WASHINGTON OSLUND ACRES SUBDIVISION PRELIMINARY SITE PLAN PRELIMINARY REVISIONS CLARK COUNTY Proposed Plan PREPARED BY PROJECT LOCATION PROPERTY OWNER PROPERTY ADDRESS ZONING R-20 TOTAL AREA TOTAL SF SITE AREA NET BUILDABLE AREA GROSS DENSITY NET DENSITY BUILDING HEIGHT BUILDING COVERAGE BUILDING SETBACKS FRONT SIDE REAR EAVES WALKWAYS DRIVEWAYS LANDSCAPE AREA TOTAL IMPERVIOUS AREA STORMWATER UTILITY PLAN FIRE ACCESS WATER SEWER DRAINAGE STREETS SIDEWALKS TYPICAL ON-STREET PARKING N NORTH STREET EXISTING STORM EXISTING SANITARY SEWER SURFACE PARKING CALCULATION 183,189 SF X .0016 AC/SF = 2.93 AC MINIMUM LOTS = 40 NUMBER OF LOTS = 40 Lots: 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20, 21, 22, 23, 24, 25, 26, 27, 28, 29, 30, 31, 32, 33, 34, 35, 36, 37, 38, 39, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 50, 51, 52, 53, 54, 55, 56, 57, 58, 59, 60, 61, 62, 63, 64, 65, 66, 67, 68, 69, 70, 71, 72, 73, 74, 75, 76, 77 May 28, 2026 Clark County Land Use Oslund Acres Subdivision CVTV Unmute Raise Shared Timer Participants Chat
1:13:30 document
Land Use Hearing - May 28, 2026 Webinar Info
Scott Taylor
David Jardin (Clark County)
Richard Daviau
Viewing Joe Kinsman's shared content
100%
OSLUND ACRES SUBDIVISION
Proposed Plan
PRELIMINARY
SITE PLAN
OSLUND ACRES
SUBDIVISION
WASHINGTON
CLARK COUNTY
PRELIMINARY
REVISIONS
May 28, 2026
Clark County Land Use
Oslund Acres Subdivision
CVTV_
Unmute
Raise
Shared Timer
Participants
Chat
1:14:19 slide
Land Use Hearing - May 28, 2026
Webinar Info
Scott Taylor
David Jardin (Clark County)
Richard Daviau
Viewing Joe Kinsman's shared content
Proposed Plan
OSLUND ACRES SUBDIVISION
PARCEL #120023000
SECTION 20, TWP 3 N, RGE 2 E, WM
ASSESSOR'S MAP #120023
PARCEL DESCRIPTION:
OWNER/APPLICANT/PROPERTY ADDRESS:
STREET
BATTLE GROUND, WA
PROPERTY
ENGINEERING
LAND PLANNING
LANDSCAPE ARCHITECTURE
PHONE
360-687-9759
FAX
360-687-9764
OSLUND ACRES
SUBDIVISION
CLARK COUNTY
WASHINGTON
PRELIMINARY
REVISIONS
PARKING CALCULATION
PARKING LEGEND
SCALE: 1" = 50'
N.E. 119TH STREET
May 28, 2026
Clark County Land Use
Oslund Acres Subdivision
1:15:08 document
Proposed Plan
OSLUND ACRES SUBDIVISION
ENGINEERING
& DESIGN
CIVIL ENGINEERING - LAND PLANNING
SURVEYING - FORESTRY - MAPPING
LANDSCAPE ARCHITECTURE
PARCEL & PROPERTY ADDRESS:
PROPERTY
WASHINGTON
OSLUND ACRES
SUBDIVISION
CLARK COUNTY
PRELIMINARY
REVISIONS
EXISTING
LANDSCAPE LEGEND
NEW PARKING CALCULATION
May 28, 2026
Clark County Land Use
Oslund Acres Subdivision
CVTV
1:15:57 document
Proposed Plan OSLUND ACRES SUBDIVISION ENGINEERING & DESIGN CIVIL ENGINEERING - LAND PLANNING SURVEYING - MAPPING LANDSCAPE ARCHITECTURE PARCEL & PROPERTY ADDRESS ASSESSOR'S PARCEL NUMBER LEGAL DESCRIPTION ZONING SITE AREA LOT COUNT BUILDING SETBACKS FRONT SIDE REAR UTILITY PROVIDERS WATER SEWER ELECTRIC GAS STORMWATER CABLE/PHONE PROPOSED EXISTING EXISTING WETLAND BUFFER NE 164TH STREET NE 165TH COURT WASHINGTON CLARK COUNTY PRELIMINARY REVISIONS LANDSCAPE LEGEND GUEST PARKING CALCULATION TYPICAL ON-STREET PARKING 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 May 28, 2026 Clark County Land Use Oslund Acres Subdivision CVTV
1:16:46 document
Land Use Hearing - May 28, 2026 Webinar Info
Proposed Plan
OSLUND ACRES SUBDIVISION
ENGINEERING & DESIGN
CIVIL ENGINEERING - LAND PLANNING
WETLAND & CRITICAL AREA SERVICES
LANDSCAPE ARCHITECTURE
2000 BROADWAY
VANCOUVER, WA 98663
PHONE (360) 695-1631
FAX (360) 695-1635
PRELIMINARY
PRELIMINARY SITE PLAN
OSLUND ACRES SUBDIVISION
WASHINGTON
CLARK COUNTY
PRELIMINARY
REVISIONS
PROPERTY ADDRESS:
OWNER/DEVELOPER:
LEGAL DESCRIPTION:
PROJECT NO.:
DATE:
SHEET NO.:
SURVEYOR:
CONSULTANTS:
GENERAL NOTES:
STORM WATER NOTES:
GEOTECHNICAL REPORT:
WATER NOTES:
SANITARY SEWER NOTES:
FIRE NOTES:
LANDSCAPE LEGEND
TREE PROTECTION NOTES
DEVELOPMENT STANDARDS TABLE
SITE PARKING CALCULATION
EXISTING OVERHEAD UTILITY EASEMENT
NEW PUBLIC STREET
THE NEW ROAD
N
May 28, 2026
Clark County Land Use
Oslund Acres Subdivision
CVTV
2022 FINAL
1:17:35 document
Land Use Hearing - May 28, 2026
Webinar Info
Scott Taylor
Chris Brehmer, Kittelson
Richard Daviau
Viewing Joe Kinsman's shared content
- 100% +
Proposed Plan
OSLUND ACRES SUBDIVISION
ENGINEERING
& DESIGN
CIVIL ENGINEERING - LAND PLANNING
SURVEYING - WATER RESOURCES
LANDSCAPE ARCHITECTURE
8905 NE HORTON ROAD, SUITE 103
VANCOUVER, WA 98662
360-750-7111
360-750-7112
www.engineeringanddesign.com
EXISTING
ACCESS
EASEMENT
TO BE
VACATED
PROPERTY INFORMATION
APPLICANT
TOTAL ACRES
GROSS AREA
NET AREA
PROPOSED
NUMBER OF LOTS
DENSITY
MINIMUM LOT AREA
MINIMUM LOT WIDTH
MINIMUM LOT DEPTH
AVERAGE LOT AREA
AVERAGE LOT WIDTH
AVERAGE LOT DEPTH
TOTAL OPEN SPACE
PUBLIC OPEN SPACE
PRIVATE OPEN SPACE
TOTAL IMPERVIOUS
UTILITY EASEMENTS
RIGHT-OF-WAY
GENERAL NOTES:
1. OSLUND ACRES SUBDIVISION
2. THIS PRELIMINARY PLAT IS SUBJECT TO THE APPROVALS AND
CONDITIONS OF APPROVAL OF CLARK COUNTY AND/OR THE CITY OF...
3. THE SUBJECT PROPERTY IS LOCATED WITHIN...
4. PROPERTY IS ZONED R-12 AND...
5. ACCESS TO THE SITE SHALL BE FROM NEW...
6. THIS PRELIMINARY PLAT IS INTENDED TO...
7. SETBACKS:
FRONT YARD:
SIDE YARD:
REAR YARD:
8. BUILDING HEIGHT:
9. PARKING:
10. THE PROJECT SHALL CONFORM TO THE...
11. THE PROPOSED PLAN SHOWS A LAYOUT OF 76 SINGLE FAMILY...
12. ALL NEW UTILITIES (WATER, SEWER, POWER...
13. STREET IMPROVEMENTS...
14. A GEOTECHNICAL INVESTIGATION...
15. STORM WATER MANAGEMENT FOR THIS...
16. REFUSE & RECYCLING COLLECTION...
17. ALL NEW OR REPLACEMENT SIDEWALKS...
18. ALL NEW STREET TREES...
19. FIRE DEPARTMENT ACCESS...
20. FIRE HYDRANT...
21. ALL FENCES ALONG PUBLIC RIGHT-OF-WAY...
22. WETLAND DELINEATION...
23. ON-SITE AND OFF-SITE LANDSCAPE...
24. PRIVATE OPEN SPACE IS PROVIDED...
25. A HOMEOWNERS ASSOCIATION...
PRELIMINARY
PRELIMINARY SITE PLAN
OSLUND ACRES
SUBDIVISION
WASHINGTON
CLARK COUNTY
PRELIMINARY
REVISIONS
LANDSCAPE LEGEND
REQUIRED PARKING CALCULATION
76 SINGLE-FAMILY RESIDENCES @ 2 PARKING LOTS = 152 SPACES
76 SINGLE-FAMILY RESIDENCES @ 2 VISITOR LOTS = 152 SPACES
TOTAL REQUIRED PARKING 304 SPACES
PROPOSED PARKING
ON STREET PARKING
OFF STREET PARKING
TOTAL PROPOSED PARKING
May 28, 2026
Clark County Land Use
Oslund Acres Subdivision
CVTV_
1:18:24 document
Proposed Plan
OSLUND ACRES SUBDIVISION
ENGINEERING
& DESIGN
CIVIL ENGINEERING - LAND PLANNING LANDSCAPE ARCHITECTURE
704 BROADWAY STREET VANCOUVER WA 98660 360.695.1226 FAX 360.695.2755
PRELIMINARY
WASHINTON
PRELIMINARY SITE PLAN
OSLUND ACRES
SUBDIVISION
CLARK COUNTY
REVISIONS
May 28, 2026
Clark County Land Use
Oslund Acres Subdivision
CVTV
18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
THE NORTH STREET
LEGAL DESCRIPTION
PROPERTY OWNER ADDRESS
BASIS OF BEARING
BENCHMARK
SETBACKS
MINIMUM LOT SIZE
MAXIMUM LOT COVERAGE
MAXIMUM HEIGHT
PARKING
UTILITY PROVIDERS
WATER
SEWER
POWER
NATURAL GAS
PHONE
CABLE
SURFACE WATER
SCHOOL DISTRICT
FIRE DISTRICT
FLOOD INFORMATION
PARCEL # 185078000
ASSESSOR'S MAP
OSLUND ACRES SUBDIVISION
1:19:13 document
Land Use Hearing - May 28, 2026 Webinar Info
Proposed Plan
OSLUND ACRES SUBDIVISION
ENGINEERING & DESIGN
CIVIL ENGINEERING - LAND PLANNING
STREETS & UTILITIES
LANDSCAPE ARCHITECTURE
850 Broadway
Suite 220
Vancouver, WA 98660
360.695.1221
PROPRIETARY
PRELIMINARY
REVISIONS
SHEET TITLE
GENERAL NOTES
ZONING: R1-20 (SINGLE FAMILY RESIDENCE)
COMPREHENSIVE PLAN DESIGNATION: URBAN RESIDENTIAL (UR)
PARCEL ID PROPERTY ADDRESS
PARCEL 1, 13702 NE 29TH AVE, VANCOUVER, WA 98684
PARCEL 2, 13706 NE 29TH AVE, VANCOUVER, WA 98684
PARCEL 3, 13708 NE 29TH AVE, VANCOUVER, WA 98684
PARCEL 4, 13710 NE 29TH AVE, VANCOUVER, WA 98684
WATER: CLARK PUBLIC UTILITIES
SEWER: CLARK COUNTY WASTEWATER
STORMWATER: CLARK COUNTY - APPROVED STORMWATER PLAN
FIRE PROTECTION: CLARK COUNTY FIRE & RESCUE DISTRICT
SCHOOLS: EVERGREEN SCHOOL DISTRICT
SCHOOLS: CRESTLINE ELEMENTARY, SHAMROCK MIDDLE SCHOOL, MT. VIEW HIGH SCHOOL
SOLID WASTE: WASTE CONNECTIONS
PROPERTY OWNER: MICHAEL OSLUND, 13706 NE 29TH AVE, VANCOUVER, WA 98684
TOTAL SITE AREA: 3.39 ACRES
DEVELOPABLE AREA: 3.39 ACRES
NET DEVELOPABLE AREA: 3.39 ACRES
NUMBER OF NEW LOTS: 47
AVERAGE LOT AREA: 5,695 SF
DENSITY: 13.86 DWELLINGS/ACRE
NUMBER OF EXISTING PARCELS: 4
NUMBER OF PROPOSED PARCELS: 47
PARKING REQUIRED: 2 SPACES/DWELLING UNIT = 94 SPACES
PARKING PROVIDED:
ON-STREET PARKING: 52 SPACES
OFF-STREET PARKING: 94 SPACES
TOTAL PARKING PROVIDED: 146 SPACES
OPEN SPACE REQUIRED: 0.70 ACRES (20% OF SITE)
OPEN SPACE PROVIDED: 0.70 ACRES
OPEN SPACE NOTES: OPEN SPACE INCLUDES ALL TRACTS. ALL COMMON OPEN SPACE TO BE OWNED AND MAINTAINED BY A HOMEOWNER'S ASSOCIATION.
SITE PARKING CALCULATION
47 NEW DWELLING UNITS
2 SPACES/DWELLING UNIT
94 SPACES REQUIRED
LANDSCAPE LEGEND
OSLUND ACRES SUBDIVISION
WASHINGTON
CLARK COUNTY
May 28, 2026
Clark County Land Use
Oslund Acres Subdivision
CVTV
1:20:02 document
Land Use Hearing - May 28, 2026
Webinar Info
OSLUND ACRES SUBDIVISION
ENGINEERING & DESIGN
Proposed Plan
200 NE 181ST AVENUE, SUITE A
PORTLAND, OREGON 97230
PHONE: (503) 667-8857
FAX: (503) 667-1601
CIVIL ENGINEERING - LAND PLANNING
SURVEYING - MAPPING
LANDSCAPE ARCHITECTURE
DESCRIPTION OF PROPERTY
A RE-DIVISION OF...
LOCATED IN THE...
TOWNSHIP... RANGE... SECTION...
OWNER/APPLICANT:
ADDRESS:
PHONE:
DEVELOPER:
ADDRESS:
PHONE:
CONTACT PERSON:
APPLICANT: RYAN CONSTRUCTION & PROPERTIES, LLC
CONSULTANT: ESA LAND SURVEYING & ENGINEERING, LLC
STORMWATER NOTES
ALL PRIVATE & PUBLIC STORMWATER FACILITIES ARE...
THE FINAL STORMWATER REPORT WILL BE...
ACCESS & CIRCULATION
A PRIVATE STREET, 'NE NORTH STREET', WILL PROVIDE ACCESS TO THE...
ALL INTERNAL STREETS ARE PRIVATE AND WILL BE MAINTAINED BY THE...
UTILITY NOTES
WATER SERVICE WILL BE PROVIDED BY THE CITY OF...
SEWER SERVICE WILL BE PROVIDED BY THE CITY OF...
ELECTRIC SERVICE WILL BE PROVIDED BY CLARK PUBLIC UTILITIES
CABLE AND TELEPHONE SERVICE WILL BE PROVIDED BY...
LANDSCAPE NOTES
ALL LANDSCAPE AREAS SHALL BE MAINTAINED BY THE HOA.
COMMERCIAL DEVELOPMENT
A TOTAL OF 8 COMMERCIAL LOTS ARE PROPOSED FOR THE...
PARKING
PARKING CALCULATIONS ARE BASED ON CLARK COUNTY CODE...
SITE DATA
TOTAL SITE AREA
TOTAL IMPERVIOUS AREA
AVERAGE LOT AREA
NUMBER OF LOTS
OPEN SPACE
PREVIOUS
EASEMENT
ZONING
PRELIMINARY
OSLUND ACRES
SUBDIVISION
WASHINGTON
CLARK COUNTY
PRELIMINARY
REVISIONS
NE 10TH STREET
NE 8TH STREET
Lot numbers: 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20, 21, 22, 23, 24, 25, 26, 27, 28, 29, 30, 31, 32, 33, 34, 35, 36, 37, 38, 39, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 50, 51, 52, 53, 54, 55, 56, 57, 58, 59, 60, 61, 62, 63, 64, 65, 66, 67, 73, 74, 75, 76, 77, 78, 80, 81, 82
May 28, 2026
Clark County Land Use
Oslund Acres Subdivision
CVTV_
2023 PROJ #
1:20:51 document
Proposed Plan
OSLUND ACRES SUBDIVISION
ENGINEERING & SURVEY
CIVIL ENGINEERING - LAND PLANNING
STRUCTURAL ENGINEERING
LANDSCAPE ARCHITECTURE
2000 BROADWAY VANCOUVER, WA 98663 WWW.DHC-ENG.COM
PRELIMINARY
PRELIMINARY SITE PLAN
OSLUND ACRES SUBDIVISION
WASHINGTON
CLARK COUNTY
PRELIMINARY
REVISIONS
PROPERTY ACCESS
APPLICANT: JON DILLON 2600 NE 111TH STREET VANCOUVER, WA 98686
PREPARED BY: DHC 2000 BROADWAY VANCOUVER, WA 98663 CONTACT: DHCENG.COM PHONE: 360-699-7311
CIVIL PROJECT NUMBER: C2021-001
DATE: FEBRUARY 2023
REVISIONS: NOV 11, 2022; NOV 18, 2022; NOV 28, 2022; NOV 30, 2022; DEC 20, 2022; DEC 22, 2022; JAN 17, 2023; JAN 25, 2023; FEB 14, 2023
TOTAL PARKING CALCULATION: 135 DWELLING UNITS; 1.75 SPACES PER UNIT; 237 REQUIRED SPACES; 237 PROVIDED SPACES
TYPICAL ON-STREET PARKING
LANDSCAPE LEGEND
NE 10TH STREET
Lot numbers: 1-90, and other miscellaneous numbers on lots and plan features.
May 28, 2026
Clark County Land Use
Oslund Acres Subdivision
1:21:40 document
Land Use Hearing - May 28, 2026 Webinar Info Scott Taylor Chris Brehmer, Kittelson Richard Daviau Viewing Joe Kinsman's shared content Proposed Plan OSLUND ACRES SUBDIVISION ENGINEERING & SURVEY CIVIL ENGINEERING LAND PLANNING STRUCTURAL ENGINEERING LANDSCAPE ARCHITECTURE 2923 BROADWAY VANCOUVER, WA 98663 PHONE (360) 696-6029 FAX (360) 696-6023 WWW.PSPLAZA.COM P.S. & PLAZA PRELIMINARY WASHINGTON CLARK COUNTY PRELIMINARY SITE PLAN OSLUND ACRES SUBDIVISION PRELIMINARY REVISIONS SHEET EXISTING PROPOSED STREET STREET DEDICATION SITE PLAN APPLICANT ENGINEER SURVEYOR CONTACT DATE PARCEL # 103254000 ZONING R-20 TOTAL ACRES GROSS AREA NUMBER OF LOTS NET SITE AREA DENSITY TOTAL OPEN SPACE NUMBER OF BLOCKS PROPOSED DEVELOPMENT PARKING REQUIRED OFF-STREET PARKING ON-STREET PARKING TOTAL PARKING TYPICAL OFF-STREET PARKING LANDSCAPE LEGEND PARKING CALCULATION 2 PARKING SPACES PER DWELLING UNIT 53 DWELLING UNITS X 2 SPACES/DWG UNIT = 106 PARKING SPACES REQUIRED: 106 SPACES PROVIDED: OFF STREET LOTS = 106 ON STREET LOTS = 40 TOTAL: 146 53 DWELLING UNITS May 28, 2026 Clark County Land Use Oslund Acres Subdivision CVTV Shared Timer Unlocked Sound on Overtime off Timer 20:00 + 1m + 5m + 10m Timer 2 03:00 Add timer
1:22:29 document
Proposed Plan
OSLUND ACRES SUBDIVISION
ENGINEERING & DESIGN
KITELSON
CIVIL ENGINEERING - LAND PLANNING
LANDSCAPE ARCHITECTURE
203 BROADWAY
VANCOUVER, WA 98660
P. 360.573.0805 F. 360.573.0806
KITELSONANDASSOC.COM
PROPERTY
PRELIMINARY SITE PLAN
OSLUND ACRES SUBDIVISION
CLARK COUNTY
WASHINGTON
PRELIMINARY
REVISIONS
EXISTING ADJACENT RESIDENTIAL DEVELOPMENT
PARCEL 1 PROPERTY ACCESS
PART OF THE NORTHEAST QUARTER
OF SECTION 12, TOWNSHIP 2 NORTH,
RANGE 2 EAST, WILLAMETTE MERIDIAN,
CLARK COUNTY, WASHINGTON.
SITE AREA
TOTAL GROSS SITE AREA 15.65 AC
TOTAL NET SITE AREA 13.91 AC
EXISTING ZONING R1-6
PROPOSED ZONING R1-6
MIN. LOT SIZE 6,000 SF
AVG. LOT SIZE 8,000 SF
MAX. LOT SIZE 10,000 SF
TOTAL NO. OF LOTS 46
FUTURE LOTS YES
AVG. LOT DIMENSION 23 LOTS
MINIMUM LOT WIDTH 60 FT
MINIMUM LOT DEPTH 100 FT
FRONT SETBACK 15 FT
REAR SETBACK 20 FT
SIDE SETBACK 5 FT
STORMWATER FACILITIES YES
OPEN SPACE
TOTAL OPEN SPACE REQUIRED 73.2 ACRES
TOTAL OPEN SPACE PROVIDED 1.39 ACRES
PERCENT OF TOTAL SITE AREA 10.0%
UTILITY PROVISIONS
WATER YES
SEWER YES
POWER YES
GAS YES
TELEPHONE YES
CABLE YES
GENERAL NOTES:
1. THIS PLAN IS FOR REVIEW PURPOSES ONLY, AND IS NOT FOR CONSTRUCTION UNTIL ALL APPROVALS ARE RECEIVED AND ALL CONDITIONS OF APPROVAL ARE SATISFIED. THE SITE IS MAPPED IN ZONE (R-1-6) BY THE CITY OF VANCOUVER.
2. ALL EXISTING EASEMENTS, COVENANTS, CONDITIONS & RESTRICTIONS OF RECORD SHALL BE SHOWN ON THIS PLAN.
3. PROPOSED TREE PRESERVATION & REPLACEMENT PLAN SHALL BE PROVIDED PER THE CITY OF VANCOUVER REQUIREMENTS.
4. BUILDING SETBACKS TO BE PER THE CITY OF VANCOUVER STANDARDS.
5. REFER TO THE CIVIL ENGINEERING PLANS FOR GRADING, DRAINAGE, EROSION CONTROL AND UTILITY DESIGN.
DATE
SCALE
SHEET
CITY OF VANCOUVER
PUBLIC WORKS
DEVELOPMENT ENGINEERING
APPROVED:
DATE:
BY:
COUNTY PLANNING
LANDSCAPE LEGEND
DUST PARKING CALCULATION
NO. OF NEW LOTS = 46
MINIMUM LOTS = 46
CITY OF VANCOUVER
203
MEETS
May 28, 2026
Clark County Land Use
Oslund Acres Subdivision
CVTV
1:23:18 document
Land Use Hearing - May 28, 2026 Webinar Info
Scott Taylor
Chris Brehmer, Kittelson
Richard Daviau
Viewing Joe Kinsman's shared content
Proposed Plan
OSLUND ACRES SUBDIVISION
ENGINEERING & DESIGNS
CIVIL ENGINEERING • LAND PLANNING
SURVEYING • WATER RESOURCES
LANDSCAPE ARCHITECTURE
2000 BROADWAY STREET
VANCOUVER, WA 98663
PH: (360) 573-0941
FAX: (360) 573-0940
PROPOSED STORM
DRAINAGE EASEMENT
TYP.
EXISTING
APPROXIMATE
BUILDING
TO BE
REMOVED
PRELIMINARY
FACTS OF PROPERTY ACCESS
TAX LOT NO.
PROPERTY OWNER
ASSESSORS ADDRESS
SITE ADDRESS
ZONING
COMPREHENSIVE PLAN
OVERLAYS
NUMBER OF LOTS
PROPOSED LOT AREA
MINIMUM LOT SIZE
MINIMUM LOT AREA
GROSS DENSITY
NET DENSITY
OPEN SPACE REQUIRED
OPEN SPACE PROVIDED
STORMWATER
UTILITY PROVIDER
WATER
SANITARY SEWER
ELECTRICITY
NATURAL GAS
TELEPHONE
CABLE
DISTRICT
DISPOSAL
WASHINGTON
PRELIMINARY SITE PLAN
OSLUND ACRES
SUBDIVISION
CLARK COUNTY
PRELIMINARY
REVISIONS
NE 112TH AVENUE
NE 109TH STREET
LANDSCAPE LEGEND
GUEST PARKING CALCULATION
REQUIRED: 1.25 SPACES / LOT x 49 LOTS = 61.25 SPACES
PROVIDED: 63 SPACES
TYPICAL ON-STREET PARKING
35 SPACES
May 28, 2026
Clark County Land Use
Oslund Acres Subdivision
CVTV
Shared Timer
Unlocked
Sound on
Overtime off
Timer
20 : 00
+ 1m
+ 5m
+ 10m
Timer 2
03 : 00
+ Add timer
1:24:07 slide
Proposed Plan OSLUND ACRES SUBDIVISION ENGINEERING & DESIGN CIVIL ENGINEERING LAND PLANNING LAND SURVEYING LANDSCAPE ARCHITECTURE 300 BROADWAY, WASHINGTON APPLICANT: CLARK COUNTY PLANNING DEPT, P.O. BOX 9810, VANCOUVER, WA 98668 PROPERTY OWNER: OSLUND ACRES LLC, 13511 SE 260TH STREET, KENT, WA 98042 SURVEYOR: PIONEER SURVEYING INC., 1210 WASHINGTON ST SUITE 110, VANCOUVER WA 98660 ENGINEER: ENGINEERING & DESIGN INC., 300 BROADWAY, VANCOUVER WA 98660 PROJECT DESCRIPTION: PROPOSED SUBDIVISION OF 92 SINGLE-FAMILY LOTS, ONE 0.6 ACRE PARK, AND NEW PUBLIC STREETS ON 17.5 ACRES. THE PROJECT SITE IS LOCATED AT NE 10TH STREET AND NE RUTH STREET. ZONING: R-6 PROPOSED PLAN GENERAL NOTES PARKING CALCULATION LANDSCAPE LEGEND PRELIMINARY OSLUND ACRES SUBDIVISION WASHINGTON CLARK COUNTY PRELIMINARY SITE PLAN PRELIMINARY REVISIONS EXISTING RESIDENCES APPROXIMATELY 97-105 NE RUTH STREET NE 10TH STREET Lot numbers: 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 26, 27, 28, 29, 39, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 50, 51, 52, 53, 54, 55, 56, 57, 58, 59, 60, 61, 62, 63, 64, 65, 66, 67, 68, 69, 70, 71, 72, 73, 74, 75, 76, 77, 78, 79, 80, 81, 82, 83, 84, 85, 86, 87, 88, 89, 90, 91, 92. May 28, 2026 Clark County Land Use Oslund Acres Subdivision CVTV
1:24:56 document
Land Use Hearing - May 28, 2026
Webinar Info
Scott Taylor
Chris Brehmer, Kittelson
Richard Daviau
Viewing Joe Kinsman's shared content
100%
Proposed Plan
EXISTING RESIDENTIAL APPROXIMATELY 97-100 FT
OSLUND ACRES SUBDIVISION
APPLICANT
ENGINEERING
& DESIGN
CIVIL ENGINEERING - LAND PLANNING
SURVEYING - FORESTRY
LANDSCAPE ARCHITECTURE
8608 NE 117TH AVENUE, SUITE 105
VANCOUVER, WA 98662
PH. 360-604-9426 FAX. 360-604-9430
WEB: WWW.WH.COM
ENGINEER
JURISDICTION
DATE
PROJECT NO.
COUNTY
STATE
SHEET
OF
PRELIMINARY
NE 119TH STREET
76
65
66
64
63
62
61
60
59
58
57
56
55
54
53
52
51
50
49
48
47
46
45
44
43
42
41
75
74
73
72
71
70
69
68
67
NE 24TH AVENUE
PRELIMINARY
REVISIONS
OSLUND ACRES
SUBDIVISION
PRELIMINARY SITE PLAN
WASHINGTON
CLARK COUNTY
77
78
79
80
81
82
83
84
85
15
14
13
12
11
10
9
8
7
6
5
4
3
2
1
16
17
18
19
20
21
22
23
24
25
26
30
29
28
27
31
32
33
34
35
36
37
38
39
40
NE 117TH STREET
LANDSCAPE LEGEND
DUST PARKING CALCULATION
NE 25TH AVENUE
TYPICAL ON-STREET PARKING
May 28, 2026
Clark County Land Use
Oslund Acres Subdivision
CVTV
1:25:45 document
Land Use Hearing - May 28, 2026
Webinar Info
Proposed Plan
OSLUND ACRES SUBDIVISION
ENGINEERING & DESIGN
CIVIL ENGINEERING
LAND PLANNING
SURVEYING
HYDROLOGY & HYDRAULICS
LANDSCAPE ARCHITECTURE
PROPERTY DESCRIPTION
PRELIMINARY
OSLUND ACRES
SUBDIVISION
WASHINGTON
CLARK COUNTY
PRELIMINARY
REVISIONS
LANDSCAPE LEGEND
REVISIONS
BIKE PARKING CALCULATION
NO. MINIMUM LOTS = 46
VIEWING LOTS = 46
N
May 28, 2026
Clark County Land Use
Oslund Acres Subdivision
CVTV
1:26:34 document
OSLUND ACRES SUBDIVISION
Proposed Plan
ENGINEERING & DESIGN
CIVIL ENGINEERING
LAND PLANNING
LANDSCAPE ARCHITECTURE
SURVEYING
4110 SW BARBUR BLVD, SUITE 215
PORTLAND, OR 97205
PHONE: (503) 766-3199
WWW.ENGINEERINGDESIGNLLC.COM
PROPRIETARY
PRELIMINARY SITE PLAN
OSLUND ACRES
SUBDIVISION
WASHINGTON
CLARK COUNTY
PRELIMINARY
REVISIONS
SHEET
NORTH STREET
EXISTING STORM
EXISTING WATER
PROPERTY ADDRESS
16541 NE 82ND STREET, VANCOUVER, WA
LANDSCAPE LEGEND
BULK PARKING CALCULATION
RESIDENTIAL
1 STORY WITH 400
2 STORY WITH 400
TYPICAL ON-STREET PARKING
May 28, 2026
Clark County Land Use
Oslund Acres Subdivision
CVTV
1:27:23 document
Land Use Hearing - May 28, 2026
Webinar Info
Scott Taylor
Chris Brehmer, Kittelson
David Jardin (Clark County)
Viewing Joe Kinsman's shared content
OSLUND ACRES SUBDIVISION
Proposed Plan
ENGINEERING & DESIGN
CIVIL ENGINEERING - LAND PLANNING
TRAFFIC ENGINEERING
LANDSCAPE ARCHITECTURE
PRELIMINARY
PRELIMINARY SITE PLAN
OSLUND ACRES SUBDIVISION
WASHINGTON
CLARK COUNTY
PRELIMINARY
REVISIONS
NE 78TH AVENUE
NE 76TH STREET
EXISTING ATTACHMENT APPROXIMATE STREET 50'
Lot numbers: 1-15, 20-40, 41-55, 56-64, 65-76, 77-92 (multiple sections)
LANDSCAPE LEGEND
SITE PARKING CALCULATION
33 DU UNITS
2.5 SPACES PER UNIT
83 MINIMUM SPACES
40 LOTS x 2.5 = 100 SPACES
ZONING: R 1-6
APPLICANT: OSLUND ACRES LLC
CONTACT: JONAH OLSON
May 28, 2026
Clark County Land Use
Oslund Acres Subdivision
CVTV
1:28:12 document
Land Use Hearing - May 28, 2026 Webinar Info 02:10:58 Layout Shared Timer Unlocked Sound on Overtime off Scott Taylor Chris Brehmer, Kittelson David Jardin (Clark County) Viewing Joe Kinsman's shared content 100% OSLUND ACRES SUBDIVISION Proposed Plan ENGINEERING & DESIGN CIVIL ENGINEERING - LAND PLANNING SURVEYING - FORESTRY LANDSCAPE ARCHITECTURE 2901 BROADWAY VANCOUVER, WA 98663 PH 360.695.1228 FAX 360.695.0514 PROPERTY WASHINGTON OSLUND ACRES SUBDIVISION PRELIMINARY REVISIONS CLARK COUNTY PRELIMINARY SITE PLAN EXISTING STORM APPROXIMATE GAS 80 81 68 69 70 71 72 73 74 75 76 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 40 41 42 43 44 45 46 47 48 49 50 39 30 31 32 33 34 35 36 37 38 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 THE NORTH STREET EXISTING STORM DETENTION LANDSCAPE LEGEND PARKING CALCULATIONS TOTAL TYPICAL ON-STREET PARKING N May 28, 2026 Clark County Land Use Oslund Acres Subdivision CVTV Timer 20:00 + 1m + 5m + 10m Timer 2 03:00 + Add timer
1:29:01 document
OSLUND ACRES SUBDIVISION Proposed Plan ENGINEERING & DESIGN CIVIL ENGINEERING LAND PLANNING SITE SURVEY LANDSCAPE ARCHITECTURE 320 BRIDGEWAY VANCOUVER, WA 98661 360-604-0400 PRELIMINARY SITE PLAN WASHINGTON OSLUND ACRES SUBDIVISION CLARK COUNTY PRELIMINARY REVISIONS SITE DATA PROJECT ADDRESS CLARK COUNTY, WA APPLICANT / OWNER PROPERTY ID #: SUBDIVISION SIZE: TOTAL PARCELS: PROPOSED USE: SINGLE FAMILY MINIMUM LOT AREA: AVERAGE LOT AREA: MAXIMUM LOT COVERAGE: SETBACKS: FRONT: SIDE: REAR: COMMON OPEN SPACE: RETAINAGE: OPEN SPACE: BUFFER: PARKING PROPOSED PARKING: GUEST PARKING: TOTAL PARKING: REQUIRMENT: OVERALL DENSITY: NET DENSITY: PLANNER: ENGINEER: CONTACT: PHONE: EMAIL: LAND USE DESIGNATION: EXISTING ZONING: R 1-6 PROPOSED ZONING: PLANNING JURISDICTION: BUILDING HEIGHT: ACCESS: LANDSCAPE REQUIREMENTS TREES REQUIRED: TREES PROPOSED: SHRUBS REQUIRED: SHRUBS PROPOSED: EXISTING UTILITIES STORMWATER: WATER: SEWER: STREETS: POWER: PHONE: CABLE: GARBAGE: NATURAL GAS: ZONING CODES NOTES LEGAL DESCRIPTION LANDSCAPE LEGEND PARKING CALCULATION ON STREET PARKING 2023 REVISIONS PREP. May 28, 2026 Clark County Land Use Oslund Acres Subdivision CVTV
1:29:50 document
Land Use Hearing - May 28, 2026 Webinar Info Scott Taylor Allister Dawson David Jardin (Clark County) Viewing Joe Kinsman's shared content Proposed Plan OSLUND ACRES SUBDIVISION ENGINEERING & DESIGN CIVIL ENGINEERING - LAND PLANNING LANDSCAPE ARCHITECTURE PROFESSIONAL LAND SURVEYING LANDSCAPE ARCHITECTURE PRELIMINARY PRELIMINARY SITE PLAN OSLUND ACRES SUBDIVISION CLARK COUNTY WASHINGTON PRELIMINARY REVISIONS May 28, 2026 Clark County Land Use Oslund Acres Subdivision CVTV
1:30:39 document
Land Use Hearing - May 28, 2026 Webinar Info Scott Taylor Daniel Kearns Allister Dawson David Jardin (Clark County) Viewing Joe Kinsman's shared content 100% OSLUND ACRES SUBDIVISION PRELIMINARY PLAT APPLICATION PREPARED FOR CHURCH OF NEW HOPE 10408 NE 131ST AVE VANCOUVER, WA 98682 ATTN: MARK GUSTAFSON (360) 906-0371 PREPARED BY ENGINEERING & DESIGN CIVIL ENGINEERING - LAND PLANNING SURVEYING & MAPPING LANDSCAPE ARCHITECTURE 1304 SE 10TH STREET VANCOUVER WA 98662 (360) 882-9993 FAX (360) 882-9995 www.eandd.net E&D PROJECT NO: 15-224 Proposed Plan 88 87 86 85 84 83 82 81 80 79 78 77 76 75 74 73 72 71 70 69 68 67 66 65 64 63 62 61 60 59 58 57 56 55 54 53 52 51 50 49 48 47 46 45 44 43 42 41 40 39 38 37 36 35 34 33 32 31 30 29 28 27 26 25 24 23 22 21 20 19 18 17 16 15 14 13 12 11 10 9 8 7 6 5 4 3 2 1 ENGINEERING & DESIGN CIVIL ENGINEERING - LAND PLANNING SURVEYING & MAPPING LANDSCAPE ARCHITECTURE 1304 SE 10TH STREET VANCOUVER, WA 98662 (360) 882-9993 PRELIMINARY NOT AN OFFICIAL RECORDED DOCUMENT COPY WASHINGTON CLARK COUNTY OSLUND ACRES SUBDIVISION PRELIMINARY SITE PLAN PRELIMINARY REVISIONS May 28, 2026 Clark County Land Use Oslund Acres Subdivision CVTV 02:13:25 Layout Shared Timer Unlocked Sound on Overtime off Timer 20:00 + 1m + 5m + 10m Timer 2 03:00 + Add timer Unmute Raise Chat
1:31:28 document
Land Use Hearing - May 28, 2026 Webinar Info OSLUND ACRES SUBDIVISION Proposed Plan ENGINEERING & DESIGNS CIVIL ENGINEERING - LAND PLANNING SURVEYING - WATER RESOURCES LANDSCAPE ARCHITECTURE WASHINGTON CLARK COUNTY PRELIMINARY SITE PLAN OSLUND ACRES SUBDIVISION PROPERTY ADDRESS TAX PARCEL # ZONE COMPREHENSIVE PLAN DESIGNATION TOTAL ACRES NUMBER OF LOTS AVERAGE LOT SIZE EXISTING WATER SERVICE PROPOSED WATER SERVICE EXISTING SEWER SERVICE PROPOSED SEWER SERVICE UTILITY PROVIDER PROPOSED ELECTRIC SERVICE PROPOSED TELEPHONE/CABLE SITE AREA EXISTING IMPERVIOUS AREA PROPOSED IMPERVIOUS AREA NET SITE AREA OVERALL DENSITY AVERAGE LOT DEPTH PROPOSED MAX. BUILDING HT. PROPOSED LOT COVERAGE PARKING REQUIRED PARKING PROVIDED TOTAL OPEN SPACE REVISIONS LANDSCAPE LEGEND PARKING CALCULATION MINIMUM LOTS = 40 May 28, 2026 Clark County Land Use Oslund Acres Subdivision CVTV
1:32:17 document
Proposed Plan
OSLUND ACRES SUBDIVISION
ENGINEERING
& DESIGN
CIVIL ENGINEERING LAND PLANNING
SURVEYING GEOTECHNICAL
LANDSCAPE ARCHITECTURE
203 EAST 4th STREET SUITE 200
VANCOUVER, WA 98660
PHONE: (360) 695-1011
FAX: (360) 695-1021
PROJECT ADDRESS:
0000 N.E. 89th STREET
VANCOUVER, WA 98660
S.W. 1/4 SECTION 22, T.3N., R.2E., W.M.
CLARK COUNTY, WASHINGTON
CURRENT LAND USE DESIGNATION:
SINGLE FAMILY RESIDENTIAL R-10
CURRENT ZONING:
SINGLE FAMILY RESIDENTIAL R-10
PROPERTY OWNER:
RICHARD OSULUND
10115 N.E. 89th STREET
VANCOUVER, WA 98682
PHONE: (360) 896-1936
CONTACT:
RICHARD OSULUND
PHONE: (360) 896-1936
APPLICANT:
RICHARD OSULUND
10115 N.E. 89th STREET
VANCOUVER, WA 98682
PHONE: (360) 896-1936
AREA OF PROJECT:
TOTAL AREA: 19.53 ACRES
GROSS DENSITY: 5.79 DU/AC
NET DENSITY: 6.96 DU/AC
PROPOSAL:
CREATE 101 SINGLE FAMILY RESIDENTIAL LOTS AND 2 TRACTS.
NOTE: ALL DIMENSIONS, BEARINGS & DATA SHOWN HEREON ARE APPROXIMATE
AND MAY BE SUBJECT TO REVISION.
WASHINGTON
PRELIMINARY
OSLUND ACRES
SUBDIVISION
CLARK COUNTY
PRELIMINARY
REVISIONS
NO.
DATE
BY
DESCRIPTION
DESIGNED BY:
CHECKED BY:
DRAWN BY:
JOB NUMBER:
2453
SHEET
PRES.0
SCALE: 1" = 80'
Joe Kinsman
Planner II, Clark County Community Development
1:33:06 document
Proposed Plan
ENGINEERING & SURVEY
OSLUND ACRES SUBDIVISION
PROPERTY ADDRESS:
OWNER:
APPLICANT:
A-2 ZONING
TOTAL AREA:
PRELIMINARY SITE PLAN
OSLUND ACRES SUBDIVISION
WASHINGTON
CLARK COUNTY
PRELIMINARY
REVISIONS
DESIGNED BY:
DRAWN BY:
CHECKED BY:
APPROVED BY:
JOB NUMBER
SHEET
2453
PRES.O
-N-
Scale 1" = 100 ft
THE NATH STREET
1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20, 21, 22, 23, 24, 25, 26, 27, 28, 29, 30, 31, 32, 33, 34, 35, 36, 37, 38, 39, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 50, 51, 52, 53, 54, 55, 56, 57, 58, 59, 60, 61, 62, 63, 64, 65, 66, 67, 68, 69, 70, 71, 72, 73, 74
1:33:55 document
Proposed Plan OSLUND ACRES SUBDIVISION PARCEL PROPERTY ADDRESS PROPERTY DESCRIPTION TAX ASSESSOR SITE SIZE ZONING OVERLAY COMPREHENSIVE PLAN DESIGNATION EXISTING USE PROPOSED USE FLOOD PLAIN STATUS WETLANDS SHORELINE TOPOGRAPHY UTILITY PROVIDER WATER SEWER POWER GAS TELEPHONE CABLE STORMWATER WASHOUGAL RIVER 99103 URBAN HOLDING COUNTY AGRICULTURAL RURAL RESIDENTIAL CLARK COUNTY RESIDENTIAL OFFICE RESIDENTIAL FLOOD PLAIN WETLANDS SHORELINE UTILITY PROVIDER S G ENGINEERING & DESIGN CIVIL ENGINEERING LAND PLANNING CONSTRUCTION MANAGEMENT LANDSCAPE ARCHITECTURE 320 BRIDGET WAY SUITE 100 WASHOUGAL WA 98671 TEL 360-835-2127 FAX 360-835-2128 PROPERTY WASHINGTON OSLUND ACRES SUBDIVISION PRELIMINARY SITE PLAN PRELIMINARY REVISIONS NE 128TH AVENUE NE 128TH AVENUE 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 NE RUTH STREET LANDSCAPE LEGEND PARKING CALCULATION EXISTING DRAINAGE EASEMENT May 28, 2026 Clark County Land Use Oslund Acres Subdivision CVTV
1:34:44 document
Land Use Hearing - May 28, 2026
Webinar Info
Proposed Plan
OSLUND ACRES SUBDIVISION
ENGINEERING
& DESIGN
CIVIL ENGINEERING - LAND PLANNING
SITE DEVELOPMENT - WATER RESOURCES
LANDSCAPE ARCHITECTURE
4632 NE 46 STREET
VANCOUVER, WA 98661
360-696-8575
fax 360-696-8576
www.eanddinc.com
PROPERTY
WASHINGTON
OSLUND ACRES
SUBDIVISION
CLARK COUNTY
PRELIMINARY
REVISIONS
LOCATION: CLARION ANDERSON ROAD
APPLICANT: JOHN DOE
CONTACT: JOHN DOE
AGENT: JOHN DOE
OWNER: JOHN DOE
TAX PARCEL NO.: 33-146-000
ZONING: R1-7.5
WATER SERVICE: CLARK PUD
SEWER SERVICE: CITY OF VANCOUVER
STORMWATER: CVWS
PROPERTY SIZE: 2.79 +/- ACRES
PROJECT SCOPE: PRELIMINARY PLAT APPLICATION
LAND USE FILE NO.: N/A
SUBMITTED: 10/26/2025
APPROVAL: N/A
PROPOSAL: 24-LOT SUBDIVISION
TOTAL ACRES: 2.79 +/- ACRES
OPEN SPACE: 0.22 +/- ACRES
NET LOT AREA: 8711 SF
AVERAGE LOT SIZE: 8711 SF
MIN LOT SIZE: 7500 SF
MAX LOT SIZE: 9756 SF
TOTAL LOTS: 24
AVERAGE DENSITY: 8.6 L/A
PARKING: ON-STREET PARKING - 48, OFF-STREET PARKING - 48, TOTAL PARKING PROVIDED - 96
LOTS: 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20, 21, 22, 23, 24, 25, 26, 27, 28, 29, 30, 31, 32, 33, 34, 35, 36, 37, 38, 39, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 50, 51, 52, 53, 54, 55, 56, 57, 58, 59, 60, 61, 62, 63, 64, 65, 66, 67, 68, 69, 70, 71, 72, 73, 74, 75, 76, 77, 78, 79, 80
EXISTING DWELLING
SFR
PUBLIC OPEN SPACE
PRIVATE PROPERTY ACCESS EASEMENT
LANDSCAPE LEGEND
SITE PARKING CALCULATION
May 28, 2026
Clark County Land Use
Oslund Acres Subdivision
CVTV
1:35:33 document
OSLUND ACRES SUBDIVISION ENGINEERING & DESIGN CIVIL ENGINEERING - LAND PLANNING SURVEYING - MAPPING LANDSCAPE ARCHITECTURE PROFESSIONAL PRELIMINARY PRELIMINARY OSLUND ACRES SUBDIVISION WASHINGTON CLARK COUNTY PRELIMINARY REVISIONS PRELIMINARY SITE PLAN Proposed Plan EXISTING PROPERTY APPROXIMATE SQ FT 505 THE 10TH STREET LANDSCAPE LEGEND LOT AREAS PARKING CALCULATION TYPICAL ON-STREET PARKING May 28, 2026 Clark County Land Use Oslund Acres Subdivision CVTV
1:36:22 document
OSLUND ACRES SUBDIVISION
Proposed Plan
ENGINEERING
& DESIGN
CIVIL ENGINEERING LAND PLANNING
SURVEYING
PROJECT MANAGEMENT
LANDSCAPE ARCHITECTURE
2901 NE 73RD AVENUE, SUITE 100
VANCOUVER, WA 98661
PHONE: (360) 546-1772
FAX: (360) 546-1775
EMAIL: info@eandd.com
WEB: www.eandd.com
PRELIMINARY
NOT FOR CONSTRUCTION
WASHINGTON
CLARK COUNTY
OSLUND ACRES
SUBDIVISION
PRELIMINARY SITE PLAN
PRELIMINARY
REVISIONS
APPLICANT
DATE
2023
PROJECT NO
DESCRIPTION
REV. BY
DATE
LANDSCAPE LEGEND
PARKING CALCULATION
EXISTING
OFF-SITE
75 MIN LOTS
74 MIN LOTS
May 28, 2026
Clark County Land Use
Oslund Acres Subdivision
CVTV

Discussions

building_development 0:34–0:54 · 1 match(es)

The hearing examined the proposed Ausland Acres subdivision, a plan to divide 8.78 acres into 98 single-family lots within an R16 zone using narrow lot standards. Development discussions highlighted infrastructure and transportation concurrency plans, including the extension of local avenues and the incorporation of an existing wastewater pump station into a newly recorded tract. To address traffic concerns and secure final plat approval, the developer committed to ensuring a new traffic signal is constructed and operational at the intersection of 88th Street and 94th Avenue.

cross_cutting 2:13–13:09 · 5 match(es)

During the hearing for the Ausland Acres subdivision, the Hearing Examiner detailed the procedures for public testimony, noting a three-minute limit for speakers and the option to submit written comments while the record remains open. The applicant was instructed to track and prepare responses to public concerns, particularly regarding functional impacts such as traffic and stormwater management. Additionally, a resident provided public comment expressing concerns about potential traffic congestion and school capacity issues resulting from the proposed development and nearby apartment construction.

building_development 17:05–17:19 · 1 match(es)

The Auslan Acres subdivision proposal seeks to divide an 8.78-acre property zoned R16 into 98 single-family lots utilizing narrow lot standards. Infrastructure plans to meet concurrency requirements include extending adjacent avenues, dedicating a sewer tract, and ensuring a new traffic signal is operational at 88th Street and 94th Avenue prior to final plat approval. During public testimony, nearby residents expressed concerns that the development's high density will strain local traffic and school capacities, and questioned the validity of the project's geotechnical report regarding seismic soil stability.

cross_cutting 25:14–25:27 · 1 match(es)

The hearing examiner and county staff outlined the procedures for providing public testimony, which included WebEx instructions, a three-minute time limit for oral comments, and a one-week open record period for submitting written feedback. During the public comment session, local residents raised specific concerns about the proposed development's impact on traffic congestion, school capacity, and potential seismic and environmental hazards related to a past wastewater spill.

wildlife_habitat 29:48–30:02 · 1 match(es)

There is no actual discussion of wildlife habitat in this hearing. The examiner briefly used the term "riparian" merely as a hypothetical example of environmental resources that often prompt the public to request additional environmental conditioning. Meanwhile, stormwater management was only mentioned in passing as a standard engineering review item and a general area of public concern regarding the proposed subdivision.

building_development 34:27–34:40 · 1 match(es)

The hearing focused on the proposed Ausland Acres subdivision, which aims to develop 8.78 acres into 98 single-family attached townhome lots within an R16 zone using narrow lot standards. Key development discussions centered on transportation concurrency, with the developer volunteering to ensure a new traffic signal is operational at 88th Street and 94th Avenue prior to final plat approval. Additional infrastructure and development concerns raised by the public included stormwater management, school capacity, and potential seismic soil issues near an existing wastewater pump station.

building_development 44:46–44:58 · 1 match(es)

The proposed Auslan Acres Subdivision seeks to divide 8.78 acres into 98 single-family attached townhome lots within an R16 zone. The discussion focused heavily on development impacts and infrastructure mitigation, specifically the coordinated installation of a new traffic signal at 88th Street and 94th Avenue, road extensions, and archaeological survey conditions. Additional public and applicant discussions addressed the adequacy of geotechnical soil testing near an existing wastewater pump station and the project's potential impact on local school capacity.

cross_cutting 46:47–46:58 · 1 match(es)

The hearing examiner established clear procedures for public participation, including a three-minute limit for verbal testimony, instructions for using the "raise hand" function, and a one-week open record period for submitting written comments. During the public comment session, nearby residents voiced specific concerns regarding the proposed subdivision's impact on local traffic congestion, school capacity, and potential geological hazards near an adjacent wastewater pump station. In response, the applicant's engineering team directly addressed these public testimonies, explaining how their traffic studies and soil testing comply with existing county code requirements.

building_development 57:18–57:31 · 1 match(es)

The hearing centered on the proposed Auslan Acres subdivision, a 98-unit single-family attached townhome development on land zoned R1-6. Key discussions addressed transportation concurrency and infrastructure improvements, specifically the extension of local roads, widening 88th Street, and a cost-shared traffic signal at 88th Street and 94th Avenue. County staff and the applicant also responded to public concerns regarding local school capacity, traffic congestion, and the geotechnical stability of the soil near an existing wastewater pump station on the property.

cross_cutting 1:02:42–1:02:55 · 1 match(es)

During public testimony, nearby residents raised concerns about a proposed 98-unit townhome development, specifically highlighting issues with increased traffic congestion, school capacity, and soil liquefaction risks near a wastewater pump station. The applicant’s engineers and county staff addressed these public comments by detailing traffic study results, code compliance, and planned infrastructure improvements such as a new traffic signal. To ensure all neighborhood concerns are considered, the hearing examiner established a one-week open record period for the submission of any further written public comments before rendering a final decision.

cross_cutting 1:31:39–1:35:19 · 2 match(es)

Residents provided public testimony raising concerns about the proposed Auslan Acres subdivision, including traffic impacts at nearby intersections, soil liquefaction hazards, an unresolved wastewater spill, and the specific type of housing being built. Applicant engineers and county staff directly responded to these public comments by explaining the technical parameters of their traffic and geotechnical studies to demonstrate compliance with county codes. Following the testimony, the Hearing Examiner established a one-week open record period for the community to submit any additional written comments before a final decision is issued.

Topic Matches (16)
TopicConfidenceTimestampKeywords
building_development direct 0:34 plat, concurrency, Subdivision, infrastructure, zoning, density, subdivision View
building_development direct 17:05 plat, concurrency, Subdivision, infrastructure, zoning, density, subdivision View
building_development direct 34:27 plat, concurrency, Subdivision, infrastructure, zoning, density, subdivision View
building_development direct 44:46 plat, concurrency, Subdivision, infrastructure, zoning, density, subdivision View
building_development direct 57:18 plat, concurrency, Subdivision, infrastructure, zoning, density, subdivision View
cross_cutting cross_cutting 2:13 public testimony, public comment View
cross_cutting cross_cutting 4:22 public testimony, public comment View
cross_cutting cross_cutting 7:34 public testimony, public comment View
cross_cutting cross_cutting 11:06 public testimony, public comment View
cross_cutting cross_cutting 12:58 public testimony, public comment View
cross_cutting cross_cutting 25:14 public testimony, public comment View
cross_cutting cross_cutting 46:47 public testimony, public comment View
cross_cutting cross_cutting 1:02:42 public testimony, public comment View
cross_cutting cross_cutting 1:31:39 public testimony, public comment View
cross_cutting cross_cutting 1:35:05 public testimony, public comment View
wildlife_habitat direct 29:48 stormwater, riparian View
Full Transcript (13178 words)

0:00 (upbeat music) - All right, we're live. - Okay, thank you. Good evening, everyone. Welcome to the May 28th, 2026 hearing of the Clark County Land Use Hearings Examiner. My name is Daniel Cairns and I'll be presiding over tonight's agenda, which consists of a single item. It is Ausland Acres subdivision PLD number 2025-00112. I think there might've been another item set for tonight, but got switched to another evening. So Ausland Acres is the only item on tonight's agenda. If you're here for something else, communicate with the planner in charge of that case

0:59 to find out when it has been rescheduled for. Let me begin with a brief introduction to me and an explanation as to how the process is gonna work for everybody tonight. First of all, I and one other person, we serve by appointment from the Board of County Counselors to review and decide development proposals in unincorporated Clark County. We are both experienced land use attorneys and we live outside of the jurisdiction so we don't have any personal connections. We're required to provide an impartial evaluation of each of these items. And I believe that I am impartial with regard to this one tonight. I don't have any personal business or familial connection to the applicant or the owners or any of the parties that have weighed in on this item so far. But I know about the proposals, what I have gleaned from the record,

1:58 which I've had for approximately two weeks now. And if anyone has any questions or wishes to challenge my impartiality, feel free to do so during the public testimony portion of tonight's hearing. My job tonight is to take public testimony, but I'm also required to evaluate and review the application, all of the public comments, the staff report, all the various staff comments. And ultimately it is my job to decide if this proposal meets or does not meet the applicable approval criteria. Those are the standards that are in the Clark County development code that existed on the day this application came in. And those are the standards that control the outcome of the decision. I can't take into account any issues that don't relate to those approval criteria. I can't be more stringent than they allow.

2:54 I can't be more lenient than they require, but I'm required to fairly interpret the standards and decide if they have been met or not. And to just make that decision, I look to evidence in the record and the applicant and the opponent's arguments about those criteria and decide whether there's sufficient credible evidence in the record to demonstrate that those standards are met or can be met through the imposition of conditions. And if that evidence is in the record, I'm obligated by state law and the local code to approve the development. My decisions are the county's final decision in these matters, but they can be, my decision can be appealed by anyone who has participated. That appeal would go to the Clark County Superior Court through the Land Use Petition Act. To appeal one of my decisions, you need to participate,

3:51 either orally tonight or by submitting written comments before the record closes. And you need to raise before me any issue you wish to preserve for a subsequent appeal. And you need to present to me any evidence that you want me to take into account or that you might want to rely upon in a subsequent appeal. So all that has to happen while the record is still open. And so the open close part of the record is a very important distinction. I typically close the record at the conclusion of public testimony, but in this post pandemic era, we always leave the record open for at least one week following the hearing. So any of you out there tonight who wish to respond to a testimony that comes in tonight or to formulate more or different arguments, you can submit those comments for at least a week following tonight's hearing

4:49 by emailing them, regular mailing them, or hand delivering them to Mr. Kinsman, who is the staff planner on this item. Let me give a few procedural dos and don'ts for participating tonight in this WebEx internet-based platform. We will get a primer on how to function when I'm done with my comments from the staff planner. But the order of events will be first, we take testimony from the county staff. That would be a verbal rendition of the written staff report that was issued prior to tonight's hearing. After that, I'll take the applicant's presentation. Applicant, you can assume that I'm generally familiar with the proposal and I need to know a couple of things from you.

5:45 First of all, I need to know what is the most current form of this proposal with the latest revised set of plans, which according to my records is exhibit 71, the revised site plan for this, but I need you to confirm that so I and everyone else knows what the current configuration is. Secondly, staff has prepared a report, it's exhibit 76, and it goes through all of the applicable approval criteria and analyzes each of those and the evidence that the applicant has submitted in support of the application here. So I need from the applicant in your opening comments, if you have any changes, corrections, challenges, objections to any of the findings that are in the staff report

6:42 or any of the proposed conditions in the staff report. And I understand we have at least one memo from the applicant, exhibit 78 just came in dealing with concurrency findings and condition. So I need to know with specificity what corrections, changes, challenges you have to the staff report. And finally, a lot of times we'll get testimony, public testimony in these hearings in a form of opposition, nominally opposition, but a lot of people want to know how this development when it is up and running is going to impact them, how it's gonna affect the local stormwater, how it's gonna affect the transportation system, how it's gonna look, those sorts of functional things. And oftentimes the applicant is in the best position to respond to those public comments, those public objections. And so I would look to you applicant to keep track of those comments

7:42 as they come in in tonight's testimony and be prepared to respond to them in your final rebuttal this evening or in writing, written responses are very useful as well. So that's the applicant's presentation. After the applicant presentation, then anyone else in favor of the application can testify. Then anyone with neutral testimony or questions can testify. And then finally, the third category, anyone who is opposed can testify. So I'll take each of those groups in that particular order. After the opponent testimony is over, I will go back to the applicant for final rebuttal. In all of these cases, the applicant gets the last word. They have the burden of proof and I always, in state law always allows applicants to bear that burden by getting the final word in response to opposition testimony

8:40 So the applicant, I'll look to you to give final rebuttal tonight, but understand the record will be left open at least a week and you can do your final rebuttal in writing, in written form at the end of that open record period. So it's helpful to get verbal final rebuttal tonight because people are tuned in, want to have some sort of response to their comments, but also you'll have a written opportunity. After the applicant's final rebuttal this evening, I'll go back to staff to see if there are any additional or parting comments that staff has based on the testimony that comes in tonight. And then my typical habit, as I mentioned, is to close the record and take the matter under consideration. We'll keep it open a week, perhaps longer, depending upon people's need for additional time. When you give your testimony, if you need additional time to formulate your comments, you can ask for more than just that one week. We can talk about it

9:40 and schedule an open records sequence at the end. But if you want additional time, you need to make that request while the record is still open so that we, all of us can talk about it and decide what that schedule is. Let's see, as I mentioned, my decisions, if you want a copy of my decision, you need to let us know that by providing us your contact information so that we can get that to you. I usually issue my decisions in writing approximately two weeks after the record closes. So again, when the record closes, matters. When you testify, do so in that order I just recited. You will have to, when you come to each category of people, you'll need to raise your hand. There's a little raise your hand function here and you'll be called on and your microphone will be unmuted. Begin with your name and give me some notion

10:38 like where you live or where your property is relative to this development so I can understand better your comments and your concerns. Let me know if you represent somebody else so I understand who has a stake in the outcome here. If you have any evidence you want me to consider, make sure you submit that by way of an exhibit. Everything that comes in will be assigned an exhibit number, be placed in the record. We have a lot of public comments already in the record that have all been assigned exhibit numbers. For those of you wishing to testify tonight, it is super helpful for me as I evaluate everything in the record when it comes time to write this decision, if I have your comments in writing. So the written comments that are in are great. That's exactly what I need. I'm a terrible note taker. So if you're gonna be reading your testimony, submit a copy of it as an exhibit,

11:37 just email it to Mr. Kinsman and that way I won't make any mistakes about what points you are raising. And by the same token, if you have already submitted comments and you wanna testify tonight, testify about something that isn't in your written comments or hit the high points. You don't need to read your written comments or recite what you have already submitted. If you agree with testimony that someone else has made, you can just say, "Hey, I agree with so-and-so. Thank you very much." And I'll ascribe those points to you. Remember that you need to raise any issue you wanna appeal on in your written comments or in your verbal testimony tonight. You need to raise the specificity, any code issue that you believe applies and explain why you think it is not met.

12:33 See what other basic do's and don'ts here. I think that's about it. If you have any procedural questions going forward, feel free to ask those when the testimony's proceeding. So with that, I think it's time for a... Oh, we will be... We have quite a few public testimony comments. If we, since it's likely we'll have a lot of public testimony tonight, we're gonna limit public comments to three minutes maximum. So again, because there's a time constraint, you might wanna submit your comments in writing. Three minute comment limitation. The applicant gets a maximum of 20 minutes for your opening presentation. I don't know if you need that. Your application has gone through several iterations and it's pretty well baked. So I think that's it by way of introduction and we're ready for a primer on how to function on WebEx, if you don't mind.

13:32 Mr. Kinsman. - Yes, thank you, Mr. Examiner. Sorry, I was sending David Jardine a copy of something real quick. So let me get on my screen. Apologize for that. Okay, thank you, Mr. Examiner, for everyone participating in tonight's hearing. If you wish to testify about a specific agenda item, staff ask that you raise your hand so that we can gauge who wishes to testify. If you are a call-in user, you can dial star three. If you are a web participant, you need to click on the hand icon located in the lower right hand corner of your screen or next to your name in the list of participants. Here is a graphic showing where you may find the hand icon shown by the red arrows.

14:27 There we go, sorry. You may first need to turn on the list of participants. You can do this by clicking the participants button shown by the purple arrow. The hand icon locations are indicated by the red arrows. Once you have given your testimony, we would ask that you put your hand down. You can accomplish this action by either clicking the hand icon again or dialing star three again. We will also ask everyone to keep their microphones on mute at any time they are not speaking. I will show you how to do that in the next slide. Prior to the close of each agenda item, we will open all microphones for everyone in attendance to ensure that everyone who wants to testify has the opportunity.

15:26 Please be aware that any noise in your personal environment will be broadcast at this time. If you miss your opportunity to testify for some reason, the record on each case will be open for a period of time so that you can submit your testimony in writing. Finally, the chat function has been disabled for public records purposes. As I mentioned, we ask everyone to keep their microphones muted at any time they are not speaking. There are a few ways in which to mute yourself. If you are a web user and are using your computer for audio, you can simply click the mute button at the bottom of your screen or next to your name in the list of participants shown by the red arrows. If you are a web user and using a phone for audio, you can either mute yourself on your computer

16:25 or use your phone's mute capability. Phone only users can use the mute capability on their phone. We would ask that you stay muted anytime you are not speaking. Thank you, everyone. And with that, I will jump into tonight's presentation for Auslan Acres Subdivision. Good evening, Mr. Examiner, county staff, and the general public. For the record, my name is Joe Kinsman and I'm the land use planner for this project. The name of this project is, again, the Auslan Acres Subdivision. The case before the hearings examiner this evening is a request to divide 8.78 acres into 98 new single family lots within the R16 zone, utilizing the narrow lot standards.

17:24 As I said, my name is Joe Kinsman and I'm the review planner for this project. Alistair Dawson is the review engineer. Jason Noble reviewed this for the fire marshal's office and Mr. David Jardine and Craig Coddle reviewed this proposal for transportation concurrency. Tonight, during our presentation, staff will provide an overview and summary of the proposal, identify any major outstanding issues or concerns, and make our recommendation to the examiner. On the vicinity map, the subject property is identified by the two black dots. North is oriented to the top of the page. We can see on this map

18:21 that it lies southeast of Sunset Elementary, east of Northeast 72nd Avenue or Andreessen Road, and west of Northeast 94th Avenue and north of Paden Parkway. The zoning map provides a closer look at the parcelization of the subject and abutting lots. The site is highlighted in red. The site and surrounding parcels are zoned R16 with the exception of the east, which is zoned IL. There are other single family developments to the north, south, and west, and to the east lies the city of Vancouver's jurisdiction and the future site of their operations building.

19:16 This slide is an aerial view of the subject property with the subject property lines in red. In this view, we can see the surrounding developments in the area. We can also see Northeast 88th Street to the south, Northeast 92nd Avenue to the north, which is proposed to be extended into the site. To the east, we have Northeast 94th Avenue, and to the west, we have Northeast 91st Avenue, which currently dead ends at the subject parcel but is proposed to extend under this proposal, as we will see in the next slide. This slide shows the proposed plan for the site. On this plan, north is oriented to the top of the slide.

20:16 This view shows the extension of Northeast 92nd Avenue into the site, the extension of Northeast 91st Avenue, and the general layout and configuration of the proposed lots. - So that's exhibit 71, that's the revised plan? - Yes, sir. - Okay, thanks. - This time, staff will show photos of the site. This photo is 91st Avenue looking east onto Northeast 88th Street. This photo is 91st Avenue looking west on Northeast 88th Street. This photo is Northeast 91st Avenue looking north across Northeast 88th Street.

21:12 This photo is north across Northeast 88th Street into the site, and also showing the sign posting. This is from the current driveway onto Northeast 88th Street facing east to 94th Avenue. This is the current driveway on Northeast 88th Street facing west. Here we have Northeast 94th Avenue looking west down Northeast 88th Street. And now we have Northeast 88th looking south onto Northeast 94th Avenue. This is a photo of Northeast 88th looking north onto Northeast 94th Avenue.

22:08 And this is looking northwest into the site from the intersection of 88th and 94th. And this is southwest facing into the site across Northeast 94th Avenue. This is northwest facing into the site across Northeast 94th Avenue. And then we have looking north onto Northeast 94th Avenue at the intersection of Northeast 90th Street and 94th Avenue. This is looking south on Northeast 94th Avenue at the intersection of Northeast 90th Street. This one is looking west down Northeast 90th Street from Northeast 94th Avenue.

23:04 And this one's southwest facing looking into the site from Northeast 90th Street on the north side of the property. This is looking south at the pump station from the corner of Northeast 90th Street and 91st Place. - So the pump station is preexisting? - Yes, sir, yep. - That's a, whose is that, the city of Vancouver? - Clark Regional Wastewater. - Okay. - This photo is from the corner of 91st Place east facing towards Northeast 94th Avenue. And the pump station would be over here on our right hand side. And this is looking south into the site from Northeast 90th Street. And again, the pump station is right over here on the right hand side.

24:03 And this is looking southwest into the site on Northeast 90th Street.

24:13 And staff report comments on this case. The application submittal was received on November 26th, 2025. The application was deemed fully complete on January 29th, 2026. The notice of development application was issued on February 6th, 2026. And the notice of hearing date change was then subsequently issued on April 17th of 2026. Staff's recommendation to the hearings examiner was issued on May 14th, 2026 and is in the record as exhibit 76. There was no SEPA appeal and the SEPA is now finalized. And project issues with this case.

25:11 For a full list of issues brought forth by the general public, see the public comment section of the staff report known as exhibit 76 in the record. Some of the items within the staff report are as follows. Street width was brought up, parking and driveway standards that may prevent emergency services. The proposal adds additional traffic to an already constrained area. Additional traffic measures are needed. These are all comments from the public. The stormwater management and drainage was an issue that was brought up as well as ADA compliance for sidewalks and general sidewalk safety. Then we have ingress and egress points, current and future students and school capacity. And then we have a geotech report and seismic concerns.

26:09 Okay, and now we have the recommendation to the examiner and staff recommends this application be approved subject to conditions of approval identified within the staff report, also known as exhibit 76. And this concludes my presentation for this project. Staff will remain available for any questions. - Okay, thank you. There was a change in the CEPA determination. Wanna kind of give me the, tell me what happened there. - Yeah, so the staff report was issued one day late and the CEPA was finalized at 5 p.m. today. So it has not been appealed and is final. - Didn't it start out as a determination of non-significance and then was changed to mitigated determination

27:07 of non-significance based on DAP comments? - Let me look in the record real quick. I don't remember a notice being sent out for, I know, so DAP did comment 100% and that is within the staff report. But I don't see that we sent out a non-CEPA notice and then followed that with a CEPA notice, at least not in this case. I may be wrong, but I can dive into that a little bit deeper as well within the open record period. - Take a look at page 30 of the staff report where it talks about the change. The reason it strikes me as strange is that DAP submitted the standard set of comments.

28:05 In this case, this is a moderate to high probability mapped area for finding archeological resources. And a standard condition is that if any cultural resources, human remains are discovered during the course of development, all work has to stop. The county, DAP and the affected tribe have to be notified. That's a standard condition. I haven't really seen it added as a separate CEPA condition. It's a condition that's part of the normal land use approval. So is there anything different or weird here? Because the condition was dealt with differently this time with no apparent explanation. - Yeah, now that you say that, it completely refreshed my memory and reading the paragraph there as well. So yes, we did an MDNS on that. Sorry about that, because of the DAP comment, as you said,

29:05 and put that as a condition of approval within the final staff report. - Okay, and so the other thing that has come up, I've seen this in a number of proposals where people argue that the impacts of the project are warrant CEPA conditions, but the way the law works in the state of Washington is that CEPA mitigated determination of non-significance and CEPA conditions are only warranted if the local code and code chapters and ordinances are not sufficient to address the particular impact. So it comes up a lot when they're a wetland or riparian resources and people are very focused on those sorts of things and they say this is a CEPA issue. It's not because the county has very elaborate, detailed ordinances that address those issues

30:02 and therefore there's no need to go to CEPA as an additional layer of conditioning because the local ordinances address it. So in this case, are there any issues that you saw raised in public comments that are not adequately addressed under the county's transportation concurrency ordinance or the engineering standards or the development standards, the narrow lot standards? Is there anything, any issue that is not addressed there? - Not to my knowledge, no. Everything has been addressed within the final staff report. - Based on the code? - Yes, based on the code. The recommendation from DAP we felt was accurate based on their comment that additional or findings were,

30:59 that based on the archeological findings on an adjacent site that having an archeologist out onsite during the dirt work portion, but everything else is covered by code. - Okay, all right, I just wanted to pin that down. Okay, let's see, who is here on the staff side? I guess is Alistair Dawson, the engineer on this case for county review engineering? - Yes, yes, sir. - Is Alistair online? Any? - Yes, sir, I'm here. - Oh, great, thank you, welcome. - Thank you. - Anything on the engineering, development engineering side of this that you want to especially bring to my attention? - No, there isn't.

31:55 - Okay, yeah, in terms of the street design, stormwater, those sorts of issues, this is already in an urban area, so it's pretty well set, so I just wondered. - Okay, there were a lot of comments about the adequacy of the surrounding transportation system to accommodate the additional traffic. Who is the concurrency engineer on this for the county? Is that Mr. Jardine? - Good evening, Mr. Harrington's examiner, David Jardine, traffic engineering section manager. I'm standing in for Craig Cottle, the concurrency engineer on this project. - Okay, you're familiar with the project? - I, yes, and just one of the things that I understand was kind of a big deal was the folks in the area were looking

32:51 for additional traffic controls, specifically at like 88th Street and 94th Avenue. One of the things that was required by the city development, which is immediately across the street, the city has proposed to construct a signalized intersection at that intersection at 88th Street and 94th Avenue. As a result, one of the things that was evaluated

33:34 as a part of this development was that same signal and the applicant had volunteered to provide, to ensure that that signalized intersection was in place and operational prior to approval of the final plat. So I just wanted to point that out 'cause there was a lot of public comment that was talking about traffic control in the area. - So the signal will be installed by the developer for the project under city jurisdiction? - So the city development is required to construct it. If this development moves faster than the city and that signal is not up yet, this development has volunteered to ensure that that signal is constructed and operational prior to final plat approval. - What is the city project that's underway?

34:33 - It will be their operations center. - Oh, okay, so it's actual city facility. - That's correct, yes, sir. - Okay. And this is to install a signal at the intersection of 88th and 94th Avenue? - That's correct. - Okay. Okay, I did see a lot of concurrency concerns expressed in those comments. And so I just wondered if that improvement will address those concerns. And it sounds like in your view that does the trick. - For the immediate frontage, yes, absolutely.

35:32 - Any other issues that you saw raised that you want to provide any elaboration on? - Not at this time, but I am available for questions, but I'll leave most of the explanation work up to the applicant. It looks like they might've brought their traffic engineer. - Fair enough. Okay, anything else from the staff side of things? - No, sir, Mr. Examiner, nothing from me at this time. - Okay, then just stand by. I'll take the applicant's presentation now, please. - Wonderful. Good evening, Mr. Examiner, Scott Taylor with SGA Engineering representing the applicant. With me tonight in our conference room, I have members of the applicant's team and our legal counsel. We also have the traffic engineers on the call as well from Kittleson and can help answer any technical questions.

36:30 I'd like to start off by thanking staff and examiner for your time and efforts on this, and look forward to sort of working through all the questions and clarifications, open record period, and getting this one pushed through. And I think everything was explained quite well with the overview of the site, the photos, the explanation of the traffic signal with the city of Vancouver's operations yard. We are showing that in our plans, you know, our layout reflects that future signal. So our right of way and sidewalk and ADA ramps there. As you confirmed, and just to verify for you, exhibit 71 is this proposed plan that's on the screen. You know, we took access originally at the Northeast corner of the site off 93rd Avenue, and realized that taking access off 92nd Avenue to the West

37:30 would actually help with our block spacing and our block perimeter, and therefore meeting cross circulation standards outright. So the nice thing of this project, there are no requests for road modifications. There are no substandard, you know, deficiencies, you know, with cross circulation or intersection spacing, driveway spacing. So that's great. We have some other clarification points, and I have a couple edits for the staff report. And so for the pump station that is located in the Northwest corner of the site, that is Clark Regional Wastewater's pump station. And so it was confirmed that that is part of the property. It was legally described before, and our surveyor even thought it was not part of the site, but it was confirmed that it is part of the site, and it's just an easement currently. And so that will become a recorded tract. - You said it was in the Northeast. It's in the Northwest corner, isn't it?

38:30 - Yeah, I'm sorry about that, Northwest. So we are calling that sewer tract. It's approximately 6,000 square feet, and it will utilize the existing fence lines and the existing easement line that's recorded as that tract. And so then that could be, I think, quit claimed to the sewer district. They already have perpetual rights, you know, for access and maintenance of it and utilization. So that will take care of that condition of approval. Frontage improvements will be completed along that tract, and those are shown on the plans. So new street and curb and gutter and sidewalk. We are connecting into 91st Avenue, as was explained there at the Southwest corner. And that immediately turns east and becomes 89th Street. All the roads internal to the site are local access streets. And then there's a handful of shared driveways

39:29 that access up to four parcels. I think, you know, the DAP comments and this MDNS SEPA determination has been explained. You know, we agree with that findings and process. I reached out to Jessica Stone from DAHP about two weeks ago and she got back to me last week. So even though there's been three surveys done around this site and adjacent to the site, they still would like to see a little more survey work done. What they would like us to do is an archeological survey that fills in the blanks and fills in the gaps. And so the areas that were not covered with the three previous studies is what we will have applied archeological complete here in the following weeks. And so that'll be completed, you know, prior to construction plan approval. So that condition of approval will be taken care of and that MDNS, we agree with that.

40:28 You know, obviously there's no appeals to that. All right, so in the staff report, I have a couple items. I just found one more as we're talking and reading through. So on page nine, this is from staff's responses to public comments in the second paragraph. There is a concern for the existing degraded condition of Northwest 21st Avenue. That street name I believe is an old carry over from another project. I believe people are probably talking about 90th street on the North side. That one I think is one of the older streets. Staff could probably confirm for us which street they were referring to in this paragraph. - Okay.

41:26 - Northwest 21st Avenue is over in Felida, so. - Yes, I'm sure there are concerns about that one just not associated with this project. - Yeah, that was Felida Crest. - Okay, so that was one minor edit that I just noticed. We had reached out to staff and I believe this is what you referred to before as exhibit 78. And so the concurrency responses. So on page 26 at the bottom of the page under the conclusion, staff says in summary concurrency staff recommends approval of the development application with the following conditions. And then that next sentence I think got omitted. So this next sentence should read conditions A10 and D8. And is that what that exhibit says? I don't have that exhibit 78 in front of me.

42:25 - It is, Scott adds the email. - Yeah, perfect. So that piece sounds like it's covered. - Okay, any other comments on the staff report? - Yeah, so two more and they're related. And so in the conditions of approval, page 31, condition A1A. So on this one, the first conditions as removal, existing structures on site are proposed to be removed. These structures shall be removed prior to construction plan approval. That's a little early and not typical. Typically these structures should be removed prior to construction, but having them removed prior to construction plan approval seems earlier than it needs to be. I feel like this could be worded differently to just say removed prior to construction, or this condition could be placed in the B section of conditions that are prior to construction,

43:23 not prior to construction plan approval. - Okay, we'll see what Mr. Kinsman recommends for that. - Okay, and then related to that condition is back on page 43, condition E1C. Same language under the demo. The structures on the site shall be removed prior to construction plan approval. I would recommend that that just says removed prior to construction and strike plan approval. - Okay. And those were the only staff report edits that we noticed and would like to put on the record. And we covered the DAP comments, and I think staff has done well talking about the other items that have come up with this project. You know, the revised site plan. I feel that this is a better layout than connecting to 93rd Street and should help keep a little more traffic

44:23 away from 94th Avenue. The traffic signal going in at 94th Avenue and 88th Street is nearing its completion with reviews with Clark County, and so it's ahead of us. And so should be approved, I think, before construction plans are approved for this project. And so we're fine with the voluntary, you know, making sure that that signal is installed, you know, prior to our final plat. And I think that should definitely help alleviate some of the traffic congestion in this area. As part of our mitigation traffic recommendations, I think they're going to adjust some of the timing of the traffic light that is down at Patton Parkway and 94th Avenue. And by increasing some timing there, that should help also relieve some of this congestion between the two. - That's not a subject of any conditions on your project? - Not specifically, no. It was more discussions between our traffic engineer and the city and the county on designing

45:22 of this signal and function of this corridor. So that was just the other piece that should hopefully help alleviate, you know, some of the traffic flow in this area. - Okay, okay. And there were an abundant number of public comments. A lot of them dealt with traffic. They were not terribly specific, so it's hard really to pin a particular intersection on those comments. And is your read of those comments any other intersection or street segment implicated? - No, no, I think we've covered it. - Okay, and I see you did not specifically respond to any of the public comments, but Mr. Kinsman did address all of those that were in the record by the time the staff report was issued. I take it you concur with his response

46:22 to all of those comments that he addressed? - Yes, and we have some information prepared and wanted to get through the hearing this evening. And then if necessary, submit, you know, formal responses in the one week open record, so. - Okay, that would be useful 'cause, you know, for members of the public, they like, as I mentioned, this applicant is in the best position to respond to a lot of public comments. And so it matters to the public to hear what the developer, what the applicant has to say about their issues. - For sure, yeah. And one clarification point too that might not be obvious for people is, you know, 88th Street is also being widened similar to 90th Street. And so that will help facilitate, you know, smoother traffic flow and, you know, this new signal that's being installed as well with, you know, turn lanes as part of that, so. - Okay, all right, very good.

47:21 Anything else you'd like to add? - None at this time. We're available for answering questions and we'll take good notes for the neighbor's comments. - Perfect, thank you. Okay, with that, we'll switch to public testimony. Anyone out there wish to testify in favor of this proposal? Raise your hand. Anyone, Richard, you see? - No, sorry, I hit the wrong button. I know nobody's raising their hand for it in favor. - Okay, anyone with neutral questions or a neutral testimony or questions on this, neither for nor against? Raise your hand. - None. - Okay, anyone out there in Zoomland wish to testify in opposition to this proposal? Raise your hand.

48:15 - Yes, we have Jacob Weathers and I will unmute. Well, I'll send the, you can now, you should be able to unmute yourself, James. - Hello. - Jacob. - Jacob. You're good. - Okay. - I'm gonna start the timer as soon as he gives his address. - Okay. Okay, my address is 9917 Northeast 92nd Avenue, a couple of streets north. So good evening. My name is Jacob Weathers. I'm a nearby residents. Wanna speak here about the proposal. I think that, you know, it's been brought up that most of the trafficked items are been talked about, but the project, I think estimated about 700 daily trips, if that's correct. And so it sounds like some of those impacts

49:14 have been addressed, but there's also, you know, the new added apartment development across by Costco on the west side that will add some traffic to that area, which suggests that the corridor may be approaching its operational limits and then adding additional 98 attached units with multiple access points where it's concerned about, you know, congestion, queuing and intersections during the peak hours, especially there on 94th and Patton. - Okay, wait, could you tell me again where these, these are condos, multifamily projects, where is it going? - This project or the apartments? - Apartments you're talking about. - Yeah, it's gonna be on the east, east at the end of the 88th and it's behind the Costco.

50:13 I think that road is 72nd and that's a, it's a large apartment complex. - Okay, okay. And that, and so you're basically wondering if the traffic that is expected from that multifamily project was taken into account when the surrounding traffic system was evaluated for this project? - Correct. - Okay, we'll get an answer to that. I think the applicant's transportation engineer is on deck and can explain how the analysis was done and what all was taken into account. - Okay. - And then the couple of things I think was the, you know, it's gonna impact the Evergreen public schools having, you know, the apartment building

51:08 and as well as this 98 development, 98 units here. So I'm just concerned that that hasn't been taken account of for the schooling. It seems that we're already at a max capacity with, you know, the detached units, portables for those schools. And then, you know, it would propose maybe a lower density detached single home project instead to reduce those concerns. That's all I had. - Okay, we'll get responses to those things. Thank you. Who else would like to testify in opposition to this project? - Raise a hand, yeah, I see one. Go ahead. - Brad James is the next one on the list and I have just sent a request to unmute.

52:05 Brad, you should be able to unmute yourself. There you go. - Yeah, yeah, can you hear me? - Yes, I can, go ahead. - Yeah, so my wife and I live off of- - 86. - 86th Street. So our concern has always been the intersection with 94th and 86. It's difficult to get out of our neighborhood now. This has been just exacerbate that situation, especially when we have to cross traffic to make a left turn to get to the Patton Parkway. And so I guess not necessarily in opposition, but just in recognition of the added problem that this is gonna create and not having a good understanding at all

53:01 of whether or not a traffic light on 88th Street would help us or actually make it even more difficult for us to get out and we don't have any other way out. So also our particular neighborhood that this is the only exit out of our neighborhood. That's it. - Okay, we will get an answer to that. And this is your two blocks to the south of this thing, right? - Correct, yeah. - Okay, we'll get an answer to that. Thank you. - Thank you. - I saw someone else, Laurie and Christie Davis raised a hand. Are they next, Richard? - Yes, they are next. - Okay, go ahead. - Well, it's gonna take me one second here. There we go.

54:00 Now they should be able to, Laurie and Christie should be able to. - Yep. Hello, good evening guys, everyone. Hi there. So I just have some questions. - Could you introduce yourself for the record, please? - Yes, thank you. I'm Laurie Davis and I reside at 9105 Northeast 90th street, which is immediately adjacent to 9115 Northeast 90th street and where the Clark regional wastewater pump station is presently located and where they also had undergone, they acquired a new easement in 2020 to expand and install industrial pressure vessels. - So you're right west of that pump station property. - Northwest, exactly, yes. - Okay. - I'm the most westerly neighbor. - Got it. All right. And what's your concern?

54:59 - So my concern is there's been some challenges between us and Clark regional wastewater district. And I pulled extensive public records regarding a recent project with the district here and have identified that there is a geotechnical report that indicates that the soils are class F liquefiable soil based upon a core sampling by a firm called Shannon and Wilson out of Lake Oswego. And they have identified a liquefiable layer in between 28.5 and 54 feet below the ground surface. - So this is a geotech report for that pump station property? - Correct, it is a site specific and the core sampling was conducted at 9115 Northeast 90th street. And my concern, I'm not here to complain or necessarily be anti-development or what have you, we're not necessarily opposed to those things, but our concern is making sure that the record is complete.

55:59 Our challenge that we also identified is that the geotechnical firm that completed the geotechnical report for the Auslan Acres subdivision currently at present according to the board of professional engineers and land surveyors does not have a certificate of authorization to operate in the state of Washington. - That's interesting. - And it's very interesting and you can verify that. Consequentially though, the sampling that they did, the sample was conducted at 14 feet. The ground sampling or the groundwater is at approximately 18 feet, but they only dug to 14 feet and they classified it as Class D stiff soil. And so our concerns here is that one, we presently have seismic soil with industrial equipment that is presently six feet from our home

56:59 and however much the setback is gonna be for the new homes that are gonna be constructed. But I just want to make sure that that seismic soil is addressed properly. And then in addition to that in 2017, there was an un-remediated 300,000 gallon wastewater spill at the Auslan Acres subdivision or the proposed subdivision that was not reported to the Department of Ecology as required by state statute of Clark by Clark Regional Wastewater District. Our challenge that we have is that they excavated near our home and created a breathing hazard for my spouse that we are now ongoing treatment for. And we are concerned because we have confirmation from the wastewater district that they have not done any further soil testing and they didn't do any form of remediation while disturbing that soil that can create bio aerosols.

57:57 Because in our area, of course, there are bacterias that are more resistant because of our temperate climate that can survive for decades. - If I could kind of interrupt. - Yes, please. - The points you're raising about this spill are really unrelated to the approval criteria that I have to evaluate as to whether to allow these lots to be created. - Okay. - This developer didn't cause this. It's not on this property. - It is on this property. It is on this property. - But it doesn't relate to any of the approval criteria. And so it's something that this developer, this property owner didn't do. And so I'm struggling to connect it to any of the criteria that I apply in deciding this case. - Right, so the owner of the Osland Acres, they permitted the easement for the wastewater district to be on. And now they're talking about going ahead

58:57 and doing a quick claim deed. I'm assuming to isolate that liability and it'll allow the project to go through. But the issue is, is that the soil, they discharged the full 300,000 gallons of wastewater at the Osland Acres site, where it is being excavated. So whether or not that's a planning issue, I'll let you guys determine that. But it is also, to me, it seems like it is a critical area because there is proof and documented proof that it hasn't been remediated. And there is a closing letter that was supplied to the Oslands by the wastewater district, strictly to just state that this is for you in the event you want to have a future property sale. That letter wasn't provided back to the Clark County or back to Clark County. So they went ahead and just closed out all those-- - Notice to future property owners. - Correct.

59:56 - Okay, what was the size of the discharge? How many gallons did you say? - Self reported, it was 300,000 gallons, but I did pull the SCADA historian record as well. Based upon their estimate, it was a 13 hour outage from their sensor. And they were estimating approximately 321 gallons per hour or per minute that was draining. However, the average before and after when the system is actually fully functional was closer to 900 to 1,000 gallons per minute. So that estimate has never been investigated by the Department of Ecology. The Department of Ecology also does not have record. Only a few thousand gallons is all that they have record of. - So I guess, I mean, this is not a county issue. This is, I mean, the county regulates the creation of new lots and that's what this application before me is.

1:00:55 You know, if, you know, these notice requirements are for future property owners, whether it happens or not, again, it's not, it doesn't pertain to any of the approval criteria that I review. And if there was a lapse in regulatory oversight, that's an ecology issue. And so again, it's the point, I get the point, it's an issue for you and it could be an issue for future property owners who buy lots in this development, but it doesn't relate to any of the standards that I administer and decide as to whether allow these lots to be created or not. - And I guess that's where the conflict is, is because where you have a property that is of this question, then what measures are there to protect the public from the development? - Well, there may be measures, but they're not anything that I administer.

1:01:54 I'm a creature of code. My authority is limited by what the code allows and that's not among them. - Sure. And I'll add grace to that and that's a fair comment there. I guess other than that, then, you know, our biggest concern, you know, we're just introducing that to the people that are here for the hearing. However, the geological hazards though, based upon, you know, 40.430, I just wanna add that the county has also tried to address that it's mapped as class C, but the title 40 code under 40.430 also states that where the maps and the definitions conflict, the definitions shall prevail. And so we have a geotechnical report that has not been submitted to the county because the wastewater district suppressed that report from going to the county. And I believe I have provided that in my public testimony so that you have record of what the seismic conditions are. And I'm not sitting here saying that we want to have

1:02:53 this project closed down, but we just want to be provided proper assurances because it's also not fair to the public to have 98 homeowners come in and buy something that they think is on stable ground when it's not. - Fair enough. Okay, we'll see what the applicant says. - All right, thank you. - Okay, thank you. Who else out there wishes to testify in opposition? Raise your hand. - Let's see. Right now I'm not seeing any more. Let's give it one more second. Oh, there we go. Alison Ward. Alison, you should be able to unmute yourself now.

1:03:43 (whispering) - I apologize, can you hear me now? - Yes, go ahead. Introduce yourself first, please, for the record. - Yeah, Alison Ward, and I live just down the road off 80th Street at 8104 Northeast 94th Street. I do want to say we are in agreeance with getting a traffic light at the end of where 88th meets down there. I know traffic gets pretty backed up in the morning times on my way to work. I do have a question to that. You mentioned widening 88th Street. Is that all the way from east to west, all the way to Andreessen, or how far is that going to go? And I'm just wondering, are we going to be intruding onto people's property and taking away a lot of their land right there? Are we going to be taking down all those trees just to widen the road? So that's kind of a concern of mine. And then also too, I know, I think Joe mentioned

1:04:42 multiple times that these homes are going to be single family homes, but from the land use hearing form, it says townhomes that are attached. So I was just like clarification on what the differences of that is for these new homes going in. Yeah. - We'll get an answer to those questions, yes. - Okay, and then just one more question. Just, I was just wondering why the applicant themselves isn't on this call and there's other people speaking on his behalf. Just wondering why, you know, he's not here to join and speak for this big project because, you know, members of the community, we're here, we're using our time to be here and we don't have people speaking for us, it's just us. So just wondering why the applicant himself isn't here. - It's a free country basically, but also I'm sure the applicant would not have a very intelligent response to some of these more granular technical questions that people have.

1:05:40 - I mean, neither do I, you know, I just don't have the money to pay for people to speak on my behalf. - But he does, and so that's why you have engineers and planners here to respond to some of these things. Those are the people that you want to provide those answers. Generally, your garden variety developer is, this is not what they do, they're the money people. - Yeah, I'd rather just go straight to the applicant, but those are all my concerns and questions. - Okay, thank you. Anyone else out there wish to testify in opposition? Go ahead and raise your hand. Understanding that you have the opportunity for at least a week following tonight to submit any written comments that you have. - Not seeing any right now. - Okay, all right, with that, I'll take the applicant's final rebuttal.

1:06:37 - Good evening, Scott Taylor again, sort of representing the applicant. We actually have the applicants here in our conference room this evening as well, and they're also online, so their whole team is in the call. And a very hands-on group, you know, HSR is a local company that has done lots of projects and the support, you know, increased new communities and always going by the book, you know, with the codes and following the rules. So appreciate everyone's comments. I'll try and go down the list here and sort of answer them in order. And then also I would like to have my traffic engineer, Chris Bremmer with Kittleson chime in and help answer some of the technical transportation questions. So first off, sounds like there's some new apartments going in over by Costco. The traffic engineer could talk to those. Those do seem like they're little ways away.

1:07:36 There was a second question about schools and school enrollment, and we reached out to the school district and got a letter from them confirming that students ride the buses to the middle school and high school, but they're all in the walking distance, you know, for sunset, and then we confirmed with staff that there is a safe walking and existing sidewalks that go north and west and connect to the Sunset Elementary directly. And so there's a safe walking route for students to walk there. On student enrollment-- - Scott, Scott, but the school district didn't in this case, and I've never really seen it comment on school capacity. And I see-- - No. Yeah, they used to make some comments on that when we would get these school letters, but they stopped doing the capacity or enrollment number portion. You know, it's just known by code that they are built to accept all new students that come into their districts.

1:08:36 As needed, they create new bus stops or additional capacity with portables or school improvements. And then, you know, our school impact fees that we pay all go to those systems to help purchase more land or do more school improvements or increase busing. And so the enrollment piece, you know, is a continuous evolving part all across Clark County for all the school districts. So yes, they're expecting, you know, this project now that we've reached out to them, you know, eight months ago and told them that it was coming. They gave us their initial feedback on busing and safe walking routes and which schools these kids will go to. So they will react and respond accordingly to these new students as they're coming in and make sure there's capacity for them at the three schools. So that's pretty stand schooling. Anything else you would add to that, Mr. Kerns or?

1:09:35 - No, that's my experience and observation also that school capacity is not a county issue. There isn't a criterion in the code about it because schools and school districts, it's entirely their management issue and they're obligated by state law to provide the service. And that's under state law, what the impact fee paid by developers goes to increase capacity. So it's a concern for a lot of existing homeowners in the area with kids, but it's a school district thing. - Correct, yes. - This is what I've seen over the years, okay. - Thank you. So to continue on answering some questions, our traffic engineer will talk about the 86th intersection and 94th Avenue.

1:10:31 Ms. Davis made comments on the pump station and challenges working with Clark Regional Wastewater and some of their past reports and past site work. Our engineers that worked on our soil study deemed that the soils are adequate for the subdivision construction. I don't believe other subdivisions in this area are as part of county code that they're required to look at those very deep subsurface soils that aren't traditionally looked at for subdivisions. For us, the main requirement is groundwater and looking at groundwater being at least five feet below your infiltration system. And so that's what our geotechs tested for and studied. The licensing of our geotech and their engineer that stamped the report is all in good standings.

1:11:31 We're not aware or can we really speculate on any past spills or other comments that were made. We can reach out to Clark Regional Wastewater and have them provide some feedback on this, I think, in our one week open record. We did have discussions with Clark Regional Wastewater a couple of weeks ago and just inquiring about their pump station and what they knew as far as the easement versus them owning the land. The county required that we put this pump station into a tract or on its own separate lot. And so I mentioned earlier at quit claim, that is just one method on how to transfer property to another owner. And so that was one concept we had on how we create a tract for the sewer pump station and then that could be dedicated or claimed, deeded to Clark Regional Wastewater. It could also be kept in ownership with HOA

1:12:31 or some other group, but it still will always have the easement and perpetuity to Clark Regional Wastewater. It makes sense that they would own that piece of property as well. So we still think that quit claim would be a appropriate method to transfer that after the final plot. But I think that's our solution for now is sort of reach out to Clark Regional. I know they've got a lot of back and forth over the years with the neighbor and their pump station and challenges with historic work there. So I'd like to use that as in the open record period to provide some feedback from Clark Regional. - Okay, these are all slab on grade type houses, are no basements, is that right? - Yeah, there'll be crawl spaces, but no basements. So traditional spread footings with, you know,

1:13:27 there could be slab on grade, it's not as common. - Okay. - So yeah, short stem walls that are the foundation walls. And so I think typically they have to be about three feet tall minimum. So, you know, to answer another question that Ms. Ward posed is, you know, these are single family attached homes. We are using the townhouse code that's allowed in this zone. And so along with townhouses, there's also narrow lots is another code section that we're be held to. And so, you know, providing guest parking and some other narrow lot requirements because these lots are less than 40 feet wide. And so townhomes is a term a lot of people don't fully understand. It's obviously a narrower home than a traditional single family ranch. And so, as you can see on the plans, there's some of these are three homes wide, some are four and some are two,

1:14:26 but they are all on their own separate lots. And so there are opportunities for future new home ownership opportunities. So there's no condos taking place or no site plans like apartments. So these are technically single family attached homes. We are also widening 88th street along our frontage. So it's pretty much what's shown here in the site plan. So along the entire Southern frontage from 91st Avenue to 94th Avenue is where we'll be widening the street and adding sidewalk. To the West, there's existing wider street and sidewalk. And then as you continue further West to other properties that are undeveloped, there are, you know, portions where the road is narrower. And so we will not be widening anything further to the West offsite, just along our frontage. - Okay. - So, and then we'll add, you know, street trees as shown in the plan there and the planter strips

1:15:26 and then curb and gutter. And there's no parking allowed on 88th or 90th streets and all street parking would be internal to the project. So I think that answered most of all those questions. I would like to open it up to Mr. Bremer from Kittleson to talk about some of the traffic questions. - Sure, go ahead. - Thank you, good evening. This is Chris Bremer from Kittleson. Let me just pause and make sure, can you hear me okay? - Yep, I can. - Okay, great, thank you. So again, Chris Bremer from Kittleson. I'm the engineer record for the traffic study and prepare that. I wanted to briefly respond to some of the comments and Mr. examiner, I'm trying, I'm going to point you to some specific elements of the traffic study for your reference and code citations. And I'm also gonna try to translate it to layman's terms so that everyone understands what I'm talking about. So if you have questions at the end, I would certainly pause and happy to loop back

1:16:25 on anything that I don't answer to your satisfaction. I'm gonna start. - Just to be clear, the original that you're referring to the original traffic study that was part of the application? - Correct. - Okay, so that for those of you out there in Zoom land, it's exhibit one, tab L. So that's the binder of application materials that started this whole process included in that binders, this traffic study that Mr. Bremer is referring to. - Thank you. - Go ahead. - So I'm gonna begin with Mr. Weather's question about what we call in process developments, other developments that are approved under construction, things like that new apartment project that was referenced on the west side of Costco. Referring you to page 20 of the traffic study, there is a list of all the approved developments that we accounted for. This list was provided by Clark County staff and included seven different projects in the area.

1:17:25 And in addition to that, we put a growth factor or annual growth on top of it. Specific to the Costco apartments, those were the apartments by Costco. Those were not directly included from their traffic study. That was not a project identified by county staff. And honestly, that's not unusual. It is a distance from the project and county staff go through and call the ones that have direct impacts on our intersections. So the seven that we specifically included, and then we use that annual growth rate to account for additional trips, which are happening, people going through neighborhoods, using the collector and arterial system, but not specifically tracking every single development in the county. So to my understanding, we have accounted for everything within the traffic study as requested by county staff, but we do not have a line item in there for the apartments next to Costco when you look at it.

1:18:21 Turning now to Mr. James' questions/comments about 88th Street, the new traffic light going in there, and then more specifically 86th Street. 86th Street, we've addressed in a few pages in the traffic study. As Mr. James noted that that neighborhood on the east side of 94th Avenue has only one way in and out today at 94th and 86th. This is described on the bottom of page 16 of our traffic study. And that neighborhood has potential for access to the east, but none of those roads have been connected. There's physically barriers to prevent connectivity to the east. So they are solely reliant on 86th and 94th today. I appreciate that it is a difficult intersection to make a left turn out of that neighborhood. We did conduct an analysis of the intersection

1:19:21 and found that both during the morning and evening peak hours, as has been alluded to, it is difficult to make a turn out there. From an Osland Acres proposal perspective, there is not a basis to require mitigation of this development at the intersection. And Mr. Examin, I'll refer everyone to page 28 of the traffic study where we go through a detailed breakdown of what I'm about to explain. But fundamentally there's two reasons why Osland Acres is not required to mitigate that level of service condition. One is the intersection of 88th Street is not regionally significant on the County Arterial Atlas. What that means is that it's basically a local street and the level of service criteria for the County does not apply to it. That's related to County Code Section 40.350.020.G.1.C.

1:20:18 And I'm reading that really quickly. It's in the traffic study, so you don't have to all write it down. It's documented in there. But for one, it's not a regionally significant intersection. The second reason why Osland Acres doesn't have to mitigate it is because the approach that is failing is that left turn movement from the side street of 86 onto 94th. And the Osland Acres project will not add left turns to either side street approach. The County Code criteria would speak to the need to mitigate it if we added more than five peak hour trips to the approach, which we don't. And so that's, again, 40.350.020.G1.C. All that said, that's the code-based response. Then there's the human response of I get that it's difficult to get in and out of there.

1:21:14 And we do think that the changes that this project's helping bring to bear in terms of the infrastructure investments will help the residents of 86th Street. And there's really two aspects of that will help. One is the new signal that will be installed at 88th and 94th. That will create a metering effect of southbound traffic on 94th where today people just come down the corridor southbound and they basically don't have to stop for anything southbound until they get to Patton Parkway. And so that fairly continuous flow of traffic during the peak hours makes it difficult to get out of the side streets simply because there's not a lot of gaps in the through traffic. Having that signal at 88th Street now and stopping traffic and serving movements there will start creating some more gaps in southbound traffic that will then benefit the 86th Street residents. The other piece, and this comes back to something you'd asked earlier as we talked about in our traffic study,

1:22:14 potential signal timing changes at Patton Parkway. And there's a discussion and recommendation in the traffic study that speaks to coordinating with county staff to explore signal timing changes, particularly during the morning peak hour. What we were seeing in the field is a little before eight to a little after eight in the morning, some of the local schools hit where their peak arrival period happens and there's a very significant queue southbound on 94th Avenue waiting for the signal at Patton. Since we made those recommendations, the county's actually implemented some signal timing changes and really reduced that warning queue issue. So there's some near-term benefit that has been realized and what will further happen as the new signal is installed at 88th and 94th is those two signals will be able to communicate with each other. We will be installing what you'll see in the conditions of approval as a traffic signal interconnect.

1:23:14 Those two signals will be able to work together and the county will be able to better manage some of the queuing and things that happen out there as a result of this additional infrastructure being put in. Staff mentioned that the signalization is a condition of approval if the city hasn't gotten there first. I can tell you both the city and this applicant are working together to share the cost of that signal. As was mentioned earlier, the signal design is well underway. We're anticipating the signal design approval in July of this year and certainly will be in place before any site-generated trips from home occupancy is happening. So bottom line, we've done the best we can within the code constraints and the ability of any one project to proportionally contribute and believe that we've met all the code criteria related to transportation. That was a lot of information and it concludes what I wanted to say, but if you have questions,

1:24:11 I'm happy to back up and revisit any of the above. - No, that is pretty comprehensive and I would refer people who are interested in traffic, which appears to be a lot of people. Your traffic study, exhibit one to this record, tab L is the study. One question I have is, I know I've seen this survey and these applications of a regionally significant impact at intersections. What was the diameter radius of that search ring for impacted regionally significant intersections? - Yeah, a great question. So for this project, in any project, that radius is determined based on the trip generation of the site. And in this case, a two mile radius was required. - And what's the trip generation, additional vehicle trips and the PMP?

1:25:08 - That's found on page 24 of the traffic study and it is 55 PMP car trips. That'd be in table six of the study. - Okay. - Two mile radius, okay. That covers a lot of the questions I saw coming up, 88th Avenue Street widening. Okay, I think that covers the questions that I have notes of. - Okay, well, I will leave it at that. I will just, for your reference, page five has the documentation. Again, page five of the traffic study on the two mile radius and why that radius if anyone's interested in going further in the weeds. Otherwise, I'll pause. Scott, is there anything else you or anyone wanted to say? - Not for the traffic stuff. Thank you very much, Chris.

1:26:06 - Okay, Scott, anything else you wanna add by way of final rebuttal? Understanding you'll have the written opportunity later on. - No, I think we've covered everything at this point. And so we really appreciate everybody's input. And believe that we have satisfied all the code requirements for this project. So thank you again. - Okay, I'm gonna turn to staff at this point to see anything that staff has heard they'd like to weigh in. We've seen Mr. Jardine has been quiet and now maybe his time to weigh in a bit since you're familiar with the concurrency in this project, Mr. Jardine. - Good evening, Mr. Herring's examiner, David Jardine, traffic engineering section manager again.

1:27:01 So I concur with the overview that Mr. Bremer had put together there. It is the study radius for the traffic study is or was two miles, and that is based off of the concurrency code that outlines the different radii or radiuses, however that's pronounced, based on the trip generation for the development. So one of the things that I might add to the explanation with regard to in process, Mr. Bremer also mentioned a growth rate for the county. It is 2% per year background growth rate and that like Mr. Bremer was talking about

1:27:59 does account for trips to and through the area that may be beyond that two mile radius or some of the developments that are smaller in nature. The 2% per year background growth rate is a pretty aggressive growth rate. So just trying to pick up all the trips we can and make sure that they're accounted for even though you may see developments like the apartment occurring, that background growth rate was put into place to account for those types of developments.

1:28:43 I think that's it for me unless you have additional questions. - No, it's just always good to hear from the county concurrency as to how the requirements work, how your review works, and what issues, data impacts are taken into account in these developments. So that's a very good input you provided. - Thank you, sir. - I guess one question I have, maybe this is Mr. Dawson County Engineering, the soil liquefaction issue that was raised by Ms. Davis relative to the pump station site, does that factor into the county's requirements for development? - Alistair Dawson Development Engineering again.

1:29:41 So I know that there was a brief discussion. This specific site did not have the leading indicators to trigger a full review of 40.430 for map geologic hazards onsite. I do believe, I'm speaking off the top of my head, is that I do believe that the liquefaction was very low to low. It is addressed in the geotech report, even though I didn't ask for it specifically. So I think that the applicant has met the intent from the county side as far as the report goes, and as far as how they deemed and classified the liquefaction of the site. So it was addressed. - So when you say it was addressed, is that in the geotechnical infiltration testing report?

1:30:39 - It was in the original application, yes. - Okay, so that's exhibit one, tab H, the geotech infiltration report. And that pertains to the soil's capacity to infiltrate stormwater, but also gets to somewhat these issues. I think that was-- - Yeah, it's the overall soils report that includes infiltration, but not specifically infiltration only. - Yeah, I think it's page four and five is what we're seeing afterwards. - In the geotech report? - Correct. Yes. - So tab H.

1:31:34 - Okay, I think that covers the issues that I saw arise during the public testimony. I guess, Mr. Dawson, anything else that you heard come up in testimony today that you want to comment on? - Nothing further. - Okay, Mr. Kinsman, do you hear anything? - Yeah, just one thing to address. Mr. Taylor brought up the conditions, A1A and E1C, and the verbiage of the, I think he said prior to construction, the county doesn't, staff doesn't have any objection to changing the verbiage to at construction

1:32:34 as opposed to, yeah. - Okay. All right. - That is all that I have, sir. - Okay, thank you. So I didn't hear any requests for additional time, but I assume that people will want to take advantage of the one week open record that we have, which takes us to, we're into June at that point. So today is Thursday the 28th, so the first Thursday in June is the fourth. So the record will remain open for the submission of any written comments by anybody, that's comments that are relevant to the project and the approval criteria. Those should be submitted by, be received by Mr. Kinsman no later than 5 p.m.

1:33:33 on June 4th. Is that the correct time, Joe? - That is correct, yep. - Okay, so you can hand deliver it, regular mail it or email it, but it has to be received by 5 p.m. on the 4th of June. After that, the applicant has an additional seven days until June 11th at 5 p.m. to provide final written rebuttal to everything that's come in up to that point or nothing. Sometimes applicants will weigh final rebuttal, but I think it's warranted in this case just to wrap things up. Joe, do you anticipate any need for further staff written comment during this open record period? - Not at this time, no. - Okay, so I'm looking for any, and any of you who testified tonight, if you wanted to submit additional comments, feel free to do so.

1:34:33 Anyone who's out there just listening, as I mentioned, written comments are, that's a particularly useful form for me and the other hearing examiner that when it comes time to sit down at the kitchen table and write the decision, if we've got your comments in writing, bullet pointed and we can notate those, it's a very useful tool as we go to evaluate these issues. Okay, with that, we'll leave the record open for, as I mentioned, public comment until 5 p.m. June 4th, applicant's final rebuttal, 5 p.m. June 11th. Does that sound acceptable to everybody out there by way of a concluding process at the end of the 11th, the record will close and my decision will issue approximately two weeks later. How does that sound to people out there? Any objections?

1:35:29 - Sorry, Scott, just a side note. If you do come down in person as the examiner had mentioned, and you're bringing it in physically in person, the permit center closes at 2 p.m. So, submitting after that. - The traffic that I'm wearing? - Yes, so 2 p.m. on the day of, otherwise you can submit it digitally at any time prior to five. - As long as it's received in time. Okay, fair enough, good warning. - Yep. - Okay. - So we agree with the one week and one week timing you've laid out, but you can't. And then your decision two weeks later, that was gonna be my only question. So that's typical. So we appreciate clarifying that and are on board with it. - Okay, very good.

1:36:29 With that, that concludes tonight's item. Record remains open and it also concludes tonight's hearing. I thank all of you for listening, for participating, weighing in, please stand by. The show is not over yet. Thank you very much and good night. [BLANK_AUDIO]